IN THE COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM TECHNOLOGY AND CONSTRUCTION COURT
(HIS HONOUR JUDGE DAVID WILCOX)
Strand London WC2A 2LL Thursday 8 August 2002 |
||
B e f o r e :
LORD JUSTICE JONATHAN PARKER
____________________
LEVOLUX A T LIMITED | ||
Claimant/Respondent | ||
- v - | ||
FERSON CONTRACTORS LIMITED | ||
Defendant/Applicant |
____________________
Smith Bernal Reporting Limited, 190 Fleet Street,
London EC4A 2AG
Tel: 020 7421 4040 Fax: 020 7831 8838
Official Shorthand Writers to the Court)
The Respondent did not attend and was not represented.
____________________
Crown Copyright ©
"Not later than 7 days before the final date for payment of any interim payment...the Contractor may give a written notice to the Sub-Contractor which shall specify any amount proposed to be withheld from the net amount notified under Clause 21.2.2, the ground or the grounds for such withholding and the amount of the withholding attributable to each ground...."
"24.1 Where a sum due under the Sub-Contract (as determined by agreement between the Parties, invoicing, adjudication, arbitration or litigation) is not paid in full by the final date for payment and no effective notice to withhold payment has been given under Clause 21.2.3, the person to whom the sum is due has the right (without prejudice to any other right or remedy) to suspend performance of his obligations under the Sub-Contract to the party by whom payment ought to have been made ('the Party in default').
24.1.1. The right may not be exercised without first giving to the Party in default at least 7 Days notice in accordance with clause 24.4 of intention to suspend performance.
....
24.4.1 Any written notice of intention to suspend pursuant to clause 21.6.1...."
which seems to be an error for 24.4.1 as that clause deals with mobilisation payments:
"....shall specify:
1. the name of the Project and the Contractor's Sub-Contract Order number;
2. the ground or grounds upon which the Sub-Contractor intends to suspend performance;
3. the amount alleged to be due but not paid in full; and
4. the date upon which it is intended to suspend performance
and shall be given to the Contractor by sending the same to the Managing Director at the office address shown on the Contractor's Sub-Contract Order and copied at the same time to the Project Manager at the site of the Sub-Contract Works by registered or recorded post."
"Without prejudice to any other power of determination, the Contractor may determine the Sub-Contract by notice to the Sub Contractor if:-
.1 any ground mentioned in Clauses 29.6.1, 29.6.2 or 29.6.6 has arisen; the Contractor has given notice to the Sub-Contractor specifying the relevant ground and facts; and such ground was in existence 10 days after such notice was given; or has arisen again at any subsequent time."
"....the suspension by the Sub-Contractor of the Sub-Contract Works (otherwise than in accordance with Clause 24), so that in the opinion of the Contractor the Sub-Contractor has not completed or will be unable to secure the completion of the Sub-Contract Works or any part thereof to which a specific period for completion applies by the expiry of the period or periods for completion of the same."
"29.8 If the Contractor shall determine the Sub-Contract for any reason mentioned in Clause 29.6, the following provisions shall apply:-
.1 all sums of money that may then be due or accruing due from the Contractor to the Sub-Contractor shall cease to be due or to accrue due."
"We are in receipt of your letter of 23rd January 2002 notifying us of payment due in respect of our valuation No 2 for works complete up to and including 20/12/01.
We do not recognise the valuation or payment dates stated as relevant to this payment. The works in question were completed prior to 20/112/01 and payment is due within 30 days of the Month End (ie by 30/12/02). These are the terms contained within our estimate, which are not refuted by the terms of your order.
As a consequence, unless payment is received in full of all monies currently notified due by 31/01/02, in the event that non-payment persists for a further 7 days, we shall have no option to suspend our works and obtain payment by alternative means if necessary.
As you are aware, the areas necessary to enable us to proceed with our works at site, are not available, and as a consequence we are currently off site. In the absence of receipt of the payment previously mentioned, we shall be unable to return to complete our works.
We are also in receipt of a letter dated 32/1/02 but unsigned which is headed 'Notice of with-holding payment'. We can only presume that this is directed at ourselves as a contra-charge regarding monies withheld from your account by your client. The notice does not enclose a narrative explaining the basis upon which you perceive all or part of these charges to be our responsibility.
....
We wholeheartedly refute any suggestion that we have been the cause of a delay on this contract. On the contrary our works have been constantly delayed by yourselves and the poor performance of other direct and indirect trades, and we reserve the right to submit our costs as a result of the delay and prolongation experienced.
We conclude by confirming that unless we receive payment in full of our legitimate entitlements by 31/01/02 we shall have no option but to suspend our works at the end of the statutory period. we shall have no hesitation in placing our argument, if necessary, in front of the appropriate legal authority. Please therefore, clarify by return, your specific intentions with regard to the payment, which is due by return."
"If, therefore, by the time an adjudicator makes a decision requiring payment by a party the contract has been lawfully terminated by that party (or that party has real prospects of success in supporting that termination) or some other event has occurred which under the contract entitles a party not to pay then the amount required to be paid by the decision does not have to be paid."
"Where a sum due under a construction contract is not paid in full by the final date for payment and no effective notice to withhold payment has been given, the person to whom the sum is due has the right (without prejudice to any other right or remedy) to suspend performance of his obligations under the contract t the party by whom payment ought to have been made ('the party in default')."
"The necessary implication of the award, which was a competent award within the Adjudicator's jurisdiction and arose out of the terms of the reference, is that the Claimant was entitled to suspend the works and that the purported determination based on wrongful suspension has no contractual effect."