[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Ove Arup & Partners International Ltd & Anor v Mirant Asia-Pacific Construction (Hong Kong) Ltd & Anor [2005] EWCA Civ 1585 (21 December 2005) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2005/1585.html Cite as: [2005] EWCA Civ 1585 |
[New search] [Printable RTF version] [Help]
COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM TECHNOLOGY AND CONSTRUCTION COURT
HH JUDGE TOULMIN CMG, QC
Strand, London, WC2A 2LL |
||
B e f o r e :
THE RT HON LORD JUSTICE MAY
and
THE RT HON LORD JUSTICE RICHARDS
____________________
OVE ARUP & PARTNERS INTERNATIONAL LTD & ANR |
Appellant |
|
- and - |
||
MIRANT ASIA-PACIFIC CONSTRUCTION (HONG KONG) Ltd & ANR |
Respondent |
____________________
Smith Bernal WordWave Limited
190 Fleet Street, London EC4A 2AG
Tel No: 020 7421 4040 Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
Andrew White QC and James Howells (instructed by Messrs Pinsent Masons) for the Respondent
____________________
Crown Copyright ©
LORD JUSTICE MAY:
Introduction
a) a design agreement made on 29th May 1995 between CEPAS and OAPIL and OAPHK on the terms of a letter of intent of that date as pleaded in paragraph 23 of the particulars of claim. This agreement did not incorporate the FIDIC terms.
b) a ground investigation agreement made on the terms of a written proposal dated 8th March 1996, which Mr Elliott, then Managing Director of CEPAS, signed on 15th or 16th March 1996. This agreement did incorporate the FIDIC terms.
It was thus in the claimants' interest to establish that the defendants were in breach of the design agreement; and in the defendants' interest to show that they were, if at all, in breach of the ground investigation agreement.
"The burden on a prospective appellant in these areas is nevertheless hard to discharge. In my view, the more complicated and technical the facts, the harder generally speaking is the burden. The reason again is obvious. The more complicated and technical the facts, the longer and more expensive would be this court's enquiry, whether by review or rehearing, and the more disproportionate would be the whole exercise for the parties and the court alike. Importantly, this court would have the disadvantage of not having heard any of the witnesses, including the experts, give oral evidence. I venture to think that, at the extreme, some questions of fact may be so complicated and technical that they should only be investigated in detail judicially once, provided that the resulting decision is not palpably incompetent."
And in paragraph 32, quoting from paragraph 141 of the main judgment in Thomson v Christie's [2005] EWCA Civ 555:
"The judge's factual conclusion … was a composite amalgam of a large number of particular judgments where an assessment of the weight and persuasiveness of each of the experts as witnesses was of critical importance. … it would, I think, be a travesty of the appellate process to interfere with the judge's composite judgment here … unless it were shown that he made one or more glaring and important misjudgments."
The design agreement
"The provision of technical site supervision and quality control by Arup/CEPA Slipform shall be based on the formation of a joint team. The detailed arrangements and associated fee are to be the subject of discussion and agreement at a later stage."
The proposal had offered to provide a small team of engineers on site whose roll was to include:
"… confirm that the design intent is being fulfilled."; and
"The team will cover approval of foundations for construction."
It was further said that:
"During site construction the Site Team will determine whether the design intent is being fulfilled and inform the Slipform Construction Manager of any work which is not fit for purpose together with proposals and plans to remedy the situation."
"As I understand it, the duty under the design agreement is to carry out the design. In order to achieve this, it may be necessary to have further information about the ground conditions. If this is the case, the designer will advise the client that more information is to be obtained. The client may enter into a separate agreement with the designer to provide or supervise the further investigations or instruct a third party to carry out the task. There is a clear distinction between the separate ground investigation and the verification of the design assumptions, which is an integral part of the designer's duty. The ground investigation itself is not within the normal contractual requirements of the original design contract."
Arup challenge parts of this definition of their design duty under this design agreement.
The design assumption
"Put shortly, Dr Redding was recommending a ground investigation by accurate and detailed mapping as his preferred way forward. He amplified his views in oral evidence. He envisaged recording on a map the variations in rock strength in the area in question, marking the orientation and dip of the discontinuities, and the nature and extent of weathering or alteration of the rock. The rock strength would be assessed by a point load machine."
"There is no allegation that Dr Redding's revised estimate was negligent. In my view it was not negligent but it had to be understood in the context that it was a preliminary assumption which was to be subject to a detailed process of verification. It was important to emphasise, as Dr Redding did in both the original and revised memorandum, and again in oral evidence, that the estimate was intended to enable the design to be progressed in its preliminary form.
Dr Redding said clearly in oral evidence that he had been surprised to discover that his preliminary design assumptions were used for the final design. I accept his evidence. His was intended to be a working assumption which would need to be verified before work on the final design was complete. The verification process could have been expected to provide the design team in London with an assessment either confirming the design assumption or indicating the changed assumption that the designers would need to take into account. In his oral evidence Dr Endicott [one of Arup's expert witnesses] agreed that a degree of reassessment was required as the design went on.
Dr Oldroyd in London did not wait for any confirmation of the crucial assumption as to the maximum load bearing stress before starting the detailed design of the boiler unit."
"There was already a gap in Arup's chain. Dr Redding made what he intended to be a highly provisional assessment which had been implemented by the design team as a firm assessment. Dr Oldroyd's witness statement (para 41) made it clear that it was for the Geotechnical team to undertake particular studies. He would wait until they responded with the relevant information and until he received further information he would proceed on the basis of the existing assumption."
"Dr Oldroyd explained in his statement that he understood that it was intended that Dr Redding's assessment should be confirmed by further ground investigation work. He said that there was also to be surface mapping and visual inspection by the Arup geologist on the site who was supervising the ground investigation. It is apparent that Arup agreed to proceed with the detailed design leaving the load bearing assumption (which Dr Littlechild thought was conservative) to be verified later."
The ground investigation agreement
Mr Manning on site
"It follows from this that Mr Manning and Arup knew that the existing information on ground conditions was unreliable and needed to be subjected to a detailed and careful verification process, the results of which were communicated to the design team. They also knew that there was a particular concern that the quality of rock was variable under the main power plant including the boiler house."
Mr Pascall on site
"5 Bases to be founded on un-fractured rock. All formations to be approved by CEPAS and where necessary brought to level and consolidated using mass concrete as directed by CEPAS."
"It was essentially different in character to the task which Dr Redding had expected to be undertaken before the detailed design stage (or at the latest in the verification of the completed detailed design). It was not based on detailed geological mapping required to verify a preliminary design assumption."
"None of this evidence is consistent with Mr Pascall undertaking a detailed verification whether by mapping or otherwise to confirm or modify Dr Redding's preliminary design assumptions.
… I am satisfied that the exercise which he was undertaking was a form of verification that the ground would sustain the bearing pressures that he had been given by Dr Oldroyd on the basis that the geological team had already reached a firm assessment. It was clearly not the type of systematic verification contemplated by Dr Redding in January 1996. It amounted to using a hammer and taking a view on the basis of his great experience, but it was not a detailed examination."
"I find that Mr Pascall is an excellent geologist who found himself, rather against his will, in Sual with a very ill defined role which did not include a specific task of verifying the load bearing capacities of the rock in the boiler area. If he had by chance found evidence in the course of his cursory examination, which was inconsistent with the bearing capacities which he had been given by Dr Oldroyd, he would no doubt have recorded it in the site report, or raised the problem in a document which would have been retained and to which my attention would have been drawn. Clearly, whatever he did, it did not put him on enquiry that Arup was taking a serious risk in designing the boiler house on this site. Short of this he would not have any incentive to flag up problems to the design team in London (or to his superiors) at a time when Arup had already completed the detailed design and he had not been given the specific task of verifying the design assumptions."
The judge was not prepared to make other positive findings on the basis of a recollection many years later of events which Mr Pascall had no cause to remember until over 9 months after they had happened.
Events after Mr Pascall left site
a) The foundations rested on naturally shattered and completely weathered material located on a geological fault.
b) The rock below the foundations had been shattered, lifted and left in a loose state by blastings.
c) The foundation rested on backfill to an excavation (i.e. on compressible made ground).
In his witness statement, he thought that for G2 the weathered material was the most likely cause and in any event a substantial cause of the settlement. He had seen no evidence of rock backfill which could have produced the amount of settlement at G2 and G5. He thought that blast damage could have been a major contributory factor if it had occurred. But he felt that, given the appearance of the rock in the trial pit next to G2 which could have been excavated by hand, he would have been very surprised to see any blasting in these areas following completion of the site formation works, because the rock was not strong enough to require blasting. On the incomplete information before him, he thought that the cause of the movement had to be a combination of weathered material and blasting.
"Formations for the original G2 and G5 footings comprised fresh/moderately to completely decomposed Grade III/IV rock with open fractures caused by blast damage. The highly weathered and blast damaged rock was the primary cause of the settlement of the pad foundation."
The judge said that the factual cause of the damage remains somewhat difficult to discern from the Arup report. He then said at paragraphs 327-9 of his judgment:
"The very process of investigation has made the task of reaching conclusions on the cause of the damage a more complicated one. Mr Bowden said in re-examination that because Arup had used rock breakers to break the ground around the foundations it was difficult to tell later whether the damage was caused by blasting or by the rock breakers. Mr Higson agreed in cross-examination that it was difficult to tell whether or not there was damage caused by blasting.
Arup's expert, Dr Endicott, had to concede in cross-examination that there was no evidence of blast damage at G2 and none on three sides of G5 although there was some evidence of cracks and open joints at a trial pit on the fourth side. Even here he qualified his answer by saying that it might be a local feature, although the associated question of the presence of loose debris required further analysis.
Arup's case in the end is that it is extremely difficult to reach a conclusion as to the failure of G2 and G5 but because the contractors have (they say) a proven record of incompetence, the cause must be blasting. They say that the conditions had changed dramatically from those found by Mr Pascall and that this must have been caused by the incompetence of the contractors."
Breach of duty – the judge's decision
"What Mr Pascall was undertaking was a rough and ready exercise confirming generally that the basis for the design was correct. It was far removed from the detailed systematic mapping which Dr Redding had envisaged and which became particularly important in view of the qualifications on the estimate of 3MPa which Dr Redding had made. The record which Mr Pascall made of his visit and his inspection on 23rd July was cursory and reflected (as he thought) the unimportant nature of the task and his attitude to it. This was also reflected in the fact that he did not present any report to the design team and threw away any notes made on site presumably because he thought that they were of no importance.
I conclude that Mr Pascall was not attempting to and did not fulfil Arup's obligation to verify its provisional estimate of a bearing capacity of 3MPa in the course of his inspection. In this, he was not personally acting negligently. The task of verification which in the circumstances of this case required detailed and systematic mapping was never undertaken by Arup. In this regard Arup was negligent."
Causation
"Arup's case is predicated on the premise that the settlements were large and occurred at an extraordinary low load which cannot be explained by the known and observed geology on the site. Secondly, they say that the condition of the G2 and G5 formations in 1997 was very different from those that Mr Pascall had observed in July 1996. They go on to say that their theory is made the more plausible by the poor performance of the contractors on site and is supported by the fact that the thickness of the blinding measured in August 1996 did not correspond with the thickness of the blinding measured in 1997. Thus it must be inferred, so they say, that the formations were altered by the contractor after July 1996.
Arup also say that Mr Brice's witness statement (albeit contradicted in his later evidence) indicated that G5 was altered after the time of Mr Pascall's inspection, that the contractor's records show further excavation after the 23rd July 1996, and that whereas Mr Pascall said that he did not see loose, blasted rock or fill left in situ, there are strong indications that the formation suffered from such defects at the time when they were examined in 1997"
(1) What Mr Pascall saw in 1996 was not what was found in 1997.(2) The claimants' own evidence demonstrated a change of levels; thus there was a contradiction at the heart of the claimants' case.
(3) The blindings uncovered below the foundations in 1997 were substantially thicker than the blindings that had been laid in early August 1996.
(4) The excavation into which Mr Pascall stepped on 23rd July 1996 was at a higher level than the formation uncovered in 1997.
(5) NSBC records showed that further excavation was done at G2 and G5 after Mr Pascall's inspection.
(6) Moreover, the claimants needed to prove that Arup's alleged negligence was an effective cause to the settlements. If notwithstanding the requirements of the design in note 5, the contractor proceeded to construct on formations that did not have a valid approval, such causation was negatived. The design was only intended to be used in conjunction with inspection and approval of the actual formations.
"I have concluded that the formation levels were not lowered after 23rd July 1996. I have also concluded that the ground that was found beneath the foundations G2 and G5 in 1997 was in situ ground. Paragraph 58.8 of the Particulars of Claim identified the physical properties of the ground both in July 1996 and in May 1997. I have specifically rejected Arup's contention that the damage was caused by damage through blasting or the use of fill or loose rock fragments in so thin foundations."
He added in paragraph 510:
"In so far as it is necessary to elaborate how the movement of the foundations occurred, I accept the theory of Professor Hudson, set out in his evidence, as being on the balance of probabilities the most likely explanation."
a) There is no documentary evidence that the blinding poured between 6th and 9th August 1996 was later dug up and re-poured, nor any quantity surveyor's records pointing to unaccounted for quantities of blinding.
b) Arup compare an average thickness against an actual thickness at particular points on two of four sides only of the formation. Records show that the blinding was of variable thickness.
Grounds of appeal
(1) The judge was wrong to hold that Arup had a duty under the design agreement to verify the 3MPa design assumption and that they were in breach of their duty;(2) The judge's decision as to the causation of the failure of G2 and G5 was wrong.
(1) Arup were obliged under the design agreement to carry out their design with the skill and care of ordinarily competent engineers for work of this kind. This is not contentious.
(2) A competent foundation design requires a sufficient knowledge of the ground conditions to determine a safe bearing capacity for foundations.
(3) If the designing engineer's knowledge of the ground conditions is insufficient to enable him to determine a safe bearing capacity, he may work initially upon assumptions. But he has an obligation to see to it that the requisite additional information is acquired to verify the assumptions. He does not necessarily have to get the additional information personally, but he must see to it that someone does, and he must see to it that the client knows that the additional information has to be obtained. Absent an explicit warning and disclaimer, it would not be sufficient for a designer, whose initial design is based on an unverified assumption, to leave it to the client alone to obtain and evaluate the additional information. The designing engineer is responsible for the design, and he should normally see to it that the necessary additional information is conveyed back to him, so that he may judge that it is sufficient for the purpose of his design.
(4) I do not construe the words "confirm that the design intent is being fulfilled" in the omitted part in the May 1995 proposal as embracing verification of the foundation design assumption. In the context of site supervision, this meant seeing that the contractor is building in accordance with the design intent. I do not consider that any contrast with the "approval of formations for construction" yields a more extended meaning.
(5) In any event, omission of the Technical Site Supervision section did not diminish Arup's obligations as designers.
(6) I do not construe the words "approving ground conditions for foundations" in the ground investigation agreement as extending to verifying the foundation design assumption. This again was a site supervision obligation.
(7) Arup's submissions suppose – and on the facts need to suppose – that verification of the foundation design assumption only required surface examination of the foundation formation such as a site supervisor would habitually do. There may be many contracts for which this might be sufficient, but not, on the facts, this contract. Dr Redding's and Dr Oldroyd's evidence made it quite clear that more extensive investigation, such as I have briefly described, was here needed. The judge so found – see paragraphs 194, 213 and 451 of his judgment. He was on the evidence, including the expert evidence, right to do so. Appropriate additional information sufficient to verify the foundation design assumption might have come from the geotechnical and geophysical investigations which Arup undertook to supervise. But, in the event, those investigations yielded little that was relevant.
(8) I accept Arup's submissions that foundation design is not an exact science, and that perfect and complete knowledge of the ground may be impossible to achieve. That does not, however, mean that a foundation designer does not have to see to it in appropriate circumstances that his assumptions are verified to the extent that a reasonably competent design would require. The judge had ample evidence to determine, as he did, what the required extent was in this case.
a) they say that the judge misunderstood and misused an Arup internal memorandum dated 1st September 1995. This submission refers to paragraphs 30 to 38 of the judgment. I find this entirely unpersuasive. The judge's decision was justified and correct without reference to this document on the straightforward lines indicated in paragraph 91 above.
b) Mr Bartlett submitted that what may at one stage have been a provisional design ceased to be so when CEPAS instructed Arup to proceed with the detailed design and to issue it to the contractor for construction. I find this entirely unpersuasive. Such instructions did not absolve Arup from producing a proper design. A proper design required verification of the design assumption.
c) Arup explicitly qualified their design by Note 5 on the relevant drawing which stated "Bases to be founded on unfractured rock. All formations to be approved by CEPAS …". This was, they say, well known to CEPAS. This note was not, in my judgment, sufficient to perform or otherwise get rid of Arup's obligation as to verification of the design assumption. It was essentially an instruction to the contractor. The judge was entitled to hold both that it was Arup themselves who needed to be satisfied that a sufficient verification process had been undertaken, and that superficial site inspection of the formation was insufficient for this purpose.
Causation - discussion
Conclusion
Lord Justice Richards: I agree.
Lord Justice Mummery: I also agree.