[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales Court of Appeal (Civil Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales Court of Appeal (Civil Division) Decisions >> Bothma & Anor (t/a DAB Builders) v Mayhaven Healthcare Ltd [2007] EWCA Civ 527 (14 May 2007) URL: http://www.bailii.org/ew/cases/EWCA/Civ/2007/527.html Cite as: [2007] EWCA Civ 527 |
[New search] [Printable RTF version] [Help]
COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
BRISTOL DISTRICT REGISTRY
(HIS HONOUR JUDGE HAVELOCK-ALLAN QC)
Strand, London, WC2A 2LL |
||
B e f o r e :
and
LORD JUSTICE DYSON
____________________
DAVID AND TERESA BOTHMA T/A DAB BUILDERS |
Appellant |
|
- and - |
||
MAYHAVEN HEALTHCARE LIMITED |
Respondent |
____________________
WordWave International Limited
A Merrill Communications Company
190 Fleet Street, London EC4A 2AG
Tel No: 020 7404 1400 Fax No: 020 7831 8838
Official Shorthand Writers to the Court)
THE RESPONDENT DID NOT APPEAR AND WAS NOT REPRESENTED.
____________________
Crown Copyright ©
Lord Justice Dyson:
"(i) The date for completion of the Contract,
(ii) Scope and validity of Architect's Instructions issued to date,
(iii) The issue and non-withdrawal of the Notice of Non-Completion, and
(iv) The sum of Valuation Number Nine …"
Paragraph 13 of the notice sought a number of remedies. These included:
"(i) That the Adjudicator make a finding of fact over the original date for Completion of the Contract and determine the revised date in the light of the agreed Extension of Time for completion granted by Mr Robin Hancock FRICS on 7 February 2006,
…
(iii) That the Adjudicator either order withdrawal of the Certificate of Non-Completion or declare [that] the same [was] invalid and improperly issued,
(iv) That the Adjudicator [determine] the true sum properly payable to [the Contractor] under Valuation Number Nine and order such sum to be payable forthwith together with interest …"
The sum sought by the Contractor by Interim Claim 9 was based on a gross valuation of £440,531.74. One item in that valuation, at the foot of page 3, reads:
"Steel kitchen portakabin@£28.80 per week, £1296, 45 weeks [and an item of delivery]".
The significance of that item is something to which I shall shortly return.
"The adjudicator may, with the consent of all the parties to those disputes, adjudicate at the same time on more than one dispute under the same contract."
It follows that, in the absence of such consent, an adjudicator has no jurisdiction to determine more than one dispute at the same time.
"I am in no doubt that on this aspect of the application Miss Lee's submission is correct. Any successful challenge to the issue of the certificate of noncompletion in the adjudication would have been, and indeed was, of no monetary consequence to the sum awarded under valuation 9. That is to be contrasted with valuation 10 where, based upon the assumed extension of time, the contractor claimed extra preliminaries."
A little later in paragraph 30, he said:
"… If the sums claimed under valuation 9 were liable to alter by reference to either the original completion date or the extension, then I can see the force of the argument that the extension issue and the completion date issue was all part and parcel of the financial claim, the single dispute as to what sum is due to be paid under valuation 9. However, on the facts here, that was not the case, and so in truth there were two independent disputes which Mr Hinchcliffe [the adjudicator] entertained."
When the matter came before me as a paper application for permission to appeal, I expressed the view that the judge's reasoning, to which I have just referred, was correct. I said that if Interim Claim 9 had included a claim for extended preliminaries and any other time related sums, there would have been a clear link between the figure claimed for Valuation 9 and the claimant's claim in relation to extensions of time and the validity of the certificate of non-completion. I also expressed the view that the judge's decision on the question of waiver was correct.
Lord Justice Waller:
Order: Application refused.