BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Queen's Bench Division) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Queen's Bench Division) Decisions >> Harrow Green Ltd v DDG Group Ltd [2010] EWHC 421 (QB) (04 March 2010) URL: http://www.bailii.org/ew/cases/EWHC/QB/2010/421.html Cite as: [2010] EWHC 421 (QB) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
Harrow Green Limited |
Claimant |
|
- and - |
||
DDG Group Limited |
Defendant |
____________________
(Ms Kate Vaughan-Neil instructed by Finers Stephens Innocent, 179 Great Portland Street, London, W1W 5LS for the Defendant)
____________________
Crown Copyright ©
HH Judge Anthony Thornton QC:
A. Introduction
(1) What was the nature of the parties' contract; and
(2) Was the dispute compromised or was the contract varied on 13 February 2008 as alleged by the defendant?
B. Contract Factual Matrix
1. LDA compensation projects
(1) The relocating party must have acted reasonably to mitigate his loss by reference to the alternative premises. The burden of proof is on the acquiring authority to show that the relocating party has not mitigated his losses.
(2) The expenditure claimed must have been the natural, direct and reasonable consequence of the compensated party's dispossession from the land taken and must not be too remote. The burden of proof is on the relocating party.
(3) There must be no double compensation and no breach of the principle of equivalence. The loss claimed must not be claimed under another head of loss. The burden of proof is on the relocating party.
(4) The relocating party must not have received value for money for his expenditure. The compensated party must rebut the presumption in law that he has received value for money.
Mr Norman explained that a party receives value for money if he receives a compensation payment which includes an element representing payment for something over and above the business or property being compulsorily acquired.
(1) The relocating party would obtain an estimate or quotation for the necessary costs of removal, relocation, refurbishment and installation which would be submitted to the acquiring authority for its consideration.
(2) Negotiation would then take place between professional representatives on both sides based on both the submitted estimate or quotation and all other relevant evidence in an attempt to agree a "full and final" figure to be paid by the acquiring authority as compensation for disturbance. That negotiation would seek to apply the principles of the compensation code already summarized.
(3) Failing agreement on a "full and final" figure, the acquiring authority would make a payment on account to the relocating party.
(4) In cases where a payment on account is made, the relocating party would agree, or seek to agree, a "full and final" figure with the acquiring authority once the relocation and all associated works had been completed. That figure would not necessarily be greater than the payment on account and, if it was smaller than that payment, the relocating party would have to repay the balance to the acquiring authority.
2. Negotiations
"I have put together the attached spreadsheet which shows how I perceive the various sub-categories of the monies awarded by the LDA for your relocation should be allocated. I hope this is agreeable. I need to invoice 50% of this as soon as possible as Harrow Green have obviously incurred a considerable financial outlay in the fitting out of the premises to date, can you please raise a Purchase Order number to invoice against."
C. Issue 1 – Contract Terms
1. Parties' Contentions - Contract
"It was agreed with Mr Purves that HG would carry out the works that we had identified and agreed for the fixed price of £170,326 … It was certainly not agreed that the £170,326 would only form an initial payment on account with further costs incurred by HG being paid by DDG."
Mr Kanbi's witness statement merely confirms that Mr Purves confirmed that HG would carry out these works at a price of £170,326."
"50% of the agreed final costs for the M+E fit out and relocation of DDG manufacturing facility".
The second installment was invoiced on 15 February 2007 as:
"Sum invoiced for installment costs for the M+E fit out and relocation of DDG manufacturing facility".
Thus, so it was contended, the use of the words "agreed final" to describe the costs being claimed in the first invoice evidenced the earlier agreement that the sum to be paid for HG's work would be £170,326. This was so even though the second invoice merely referred to the second tranche of this payment as being "for installment costs", which is a clear reference to an interim and not a final payment. Mr Purves accepted that those two words were mistakenly added to the invoice by whoever prepared the invoice and it is clear, given their context and the background that I have set out that they do not evidence an underlying agreement. I find that the word "final" is a bookeeper's error for "installment" and that the first invoice, like the second, should have been worded "agreed installment costs".
2. Discussion
D. Issue 2 – Compromise or Contract Variation
1. Parties' contentions – Compromise or contract variation
"During the course of a further meeting with Mr Purves on 13 February 2008 to try and finalise the documentation for the compensation claim to the LDA. I made it clear to Mr Purves that I did not accept that DDG had any further liability to HG and Mr Purves agreed that HG would accept in settlement of its claim for the additional monies whatever sum may be agreed and paid to DDG by the LDA."
2. Discussion
3. Conclusion – Compromise or contract variation
E. Overall Conclusion
HH Judge Anthony Thornton QC
Schedule to Judgment
Issue 1: The nature of the parties' contract.
The parties entered into a simple contract whose express or implied terms were as follows:
(1) The claimant would carry out such relocation work and any further work at the site as would be agreed with or instructed by the defendant for a reasonable sum.
(2) The reasonable sum to be paid to the claimant by the defendant for the contract work would be ascertained and agreed by the claimant and the defendant once the claimant had concluded its work at the site.
(3) Once the claimant had completed its contract work, it would provide all details to the defendant that were reasonably needed to enable the defendant to establish what relocation work and any further work the claimant had undertaken under the contract and what the reasonable sum was that the claimant was entitled to be paid by the defendant for carrying out that work.
(4) The claimant would provide the defendant with all reasonable assistance in relation to the defendant's negotiations with the LDA for the defendant's recovery of statutory compensation from the LDA.
(5) The reasonable sum to be paid by the defendant to the claimant would take account of all relevant factors including, but not limited to, the sum that was paid or payable by the LDA to the defendant by the LDA as statutory compensation for the defendant's relocation.
(6) The reasonable sum paid or payable by the LDA to the defendant as statutory compensation would not be determinative of the sum that would be payable to the claimant but it would provide guidance, along with all other relevant factors, as to what that reasonable sum should be.
(7) The reasonable sum to be paid to the claimant by the defendant would be ascertained by the defendant and agreed by the defendant with, and paid to, the claimant after the defendant had had a reasonable opportunity to negotiate and agree with the LDA the statutory compensation that the defendant was entitled to be paid by the LDA.
(8) The claimant would be paid by the defendant, by way of a payment on account, a reasonable part of the sum that the defendant received by way of an interim payment of statutory compensation from the LDA.
Issue 2: The alleged compromise or variation of the contract.
The parties reached no agreement on 13 February 2008 to compromise the claimant's claim or to vary the contract or otherwise.