BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Costain Ltd. v Wescol Steel Ltd. [2003] EWHC 312 (TCC) (24 January 2003) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2003/312.html Cite as: [2003] EWHC 312 (TCC) |
[New search] [Printable RTF version] [Help]
TECHNOLOGY AND CONSTRUCTION COURT
The Strand London WC2A 2LL |
||
B e f o r e :
____________________
COSTAIN LTD |
CLAIMANT |
|
-v- |
||
WESCOL STEEL LTD |
DEFENDANT |
____________________
MR BOULDING QC AND MR STANSFIELD (Instructed by Walker Morris) appeared for the Defendant
____________________
Crown Copyright ©
Friday, 24th January 2003
"Unless we receive payment in cleared funds of our client's final account by 11th November 2002, we put you on notice that we will commence an adjudication to claim the full value of our client's final account as set out in the summary, or such other sum as the adjudicator shall find is due to Wescol. If we do not hear from you by that date, we will consider that you have no comments to make and that you do not disagree with our definition of the dispute."
That letter was answered by a letter dated 7th November 2002. The following points were made by the claimant in that letter. First that there could be no dispute presently as to the value of Wescol's final account since that was not yet due for determination. And then there was reference to the sub-contractor's obligation to provide documents. The letter stated,
"If the documents now provided with your letter are purported to be those documents, then you must allow adequate time for their examination."
Then it was stated again that the demand for payment was premature. The letter went on to say that there had been continuous, close and positive dialogue between the parties in relation to progressing agreement of the valuation of the defendant's work, ceasing only with their insolvency. It was stated that the joint administrative receiver had indicated an intention that the dialogue should resume through Curry and Brown. And the letter continued,
"Curry and Brown's failure to date to communicate with us has, therefore, been a surprise although we trust this oversight will be remedied. We are, of course, continuing to give attention to the material sent with your letter and we will respond in detail in due course. It seems to us that none of these circumstances points to the existence of a dispute."
And then it went on to say,
"There has been no dispute concerning extension of time. Extensions have been given. Although the specified procedures in respect of extensions of time cease to apply upon the determination of Wescol's employment, it should be noted that the time-scale allowed for final review of interim extensions is 16 weeks."
And then it said,
"Without prejudice to the generality of the foregoing, the decisions which Wescol will ask the adjudicator to make will include the following:
(1) Payment of the sum due to it under the contract forthwith or at such future date as the adjudicator shall determine;
(2) A declaration as to the value of its final account;
(3) A declaration as to its entitlement to an extension of time."
And then the actual referral was made on 19th December.
"Any dispute or difference arising under the sub-contract may be referred to adjudication."
"Notices, referral particulars, accompanying documents, written statement of contention, material, the adjudicator's decision, correspondence and the like, shall be sent by fax and first class post forthwith to the address of the party …" etc
And then,
"This Clause shall take precedence over Clause 38A.4.2 as to the mode of service of documents for the purposes of this Clause 38A."
38A.4.2 says,
"The referral [and] its accompanying documentation … and the copies thereof to be provided to the other party, shall be given by actual delivery, or by fax, or by registered post, or recorded delivery."
Clause 38A.9 is perfectly clear, and it is common ground that in this case the documents were not sent by the method prescribed by that sub-clause.
"Any failure by either party to enter into the JCT adjudication agreement or to comply with any requirement of the adjudicator under Clause 38A.5.5, or with any provision in or requirement under Clause 38A shall not invalidate the decision of the adjudicator."
So, he says, the Clause 38A.9, in effect, is not binding, or at least does not invalidate a decision of the adjudicator.
"Within 7 days from the date of such notice or the execution of the JCT adjudication agreement by the adjudicator, if later, the party giving their notice of intention shall refer the dispute or difference to the adjudicator for his decision."
The point was originally taken by Mr Mort that, because that was not an absolute 7-day limit but there was an alternative given, therefore the clause did not fall within the statutory provisions; therefore the statutory scheme itself applies. However, Mr Boulding pointed out that this particular qualification to the time limit was expressly deleted by an amendment to the contract; and it is now common ground that Clause 38A does comply with the requirements of the Act and, therefore, the statutory provisions are not invoked. That agreement seems to imply that the provision in Clause 38A.5.6, that the failure to comply with any requirement under Clause 38A shall not invalidate the decision of the adjudicator, does not apply to Clause 38A.4.1.