BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Capital Structures Plc v Time & Tide Construction Ltd [2006] EWHC 591 (TCC) (08 March 2006) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2006/591.html Cite as: [2006] BLR 226, [2006] CILL 2345, [2006] EWHC 591 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY & CONSTRUCTION COURT
B e f o r e :
____________________
CAPITAL STRUCTURES PLC | Claimant | |
- and - | ||
TIME & TIDE CONSTRUCTION LTD. | Defendant |
____________________
Official Shorthand Writers and Tape Transcribers
Quality House, Quality Court, Chancery Lane, London WC2A 1HP
Tel: 020 7831 5627 Fax: 020 7831 7737
MR. S. HARGREAVES (instructed by Hewitsons) appeared on behalf of the Defendant.
____________________
Crown Copyright ©
JUDGE DAVID WILCOX:
"We write to instruct:(a) That others are to be employed to comply with the 30th January 2004 direction insofar as it relates to the staircases, with the costs consequences set out in clause 4.5.
(b) The consequential immediate omission of the four metal staircases (recited as having a value of £44,500 in the addendum order) from the works instructed by the addendum order and … subcontract works as from the date of this letter.
This instruction is issued pursuant to clause 4.5 following the notice under that clause in our letter of the 24th March 2004. We are prepared as a gesture of goodwill, subject to your not challenging our entitlement to issue the omission instructions and to your providing the information requested below by the 14th April 2004, effectively to treat the instruction as a clause 4.2 variation amending the January variation instruction addendum order, and to value and pay for design work in respect of the staircases.
To that end we therefore request the issue of all design information in relation to the immediate element of the work referred to above to our site address, along with your cost for the completion of the design and drawings and all substantiating backup so as to allow an assessment to be made and values to be agreed for payment to Capital Structures Ltd. for the same.
Please forward all of the above requested information by 14th April 2004. Please note that we have not yet instructed others to carry out work in respect of the balconies, juliettes and other undelivered elements. Given the fact of their fabrication obviously others will have to be so instructed if a further termination notice has to be issued under clause 29.2.2."
"We write to give you notice pursuant to clause 29.2.1 that you have –(i) without reasonable cause wholly or substantially suspended the carrying out of the subcontract works and/or(ii) without reasonable cause failed to proceed regularly and diligently with the subcontract works in that you have withheld or delayed the delivery of fabricated balustrading, balconies and juliettes to the site or otherwise progress your subcontract works."
And then going on into greater detail to show what default there was. It continues:
"If you continue the above default for ten days from receipt of this notice, which is being delivered by hand delivery, then we may, in accordance with 29.2.1 on or within 10 days from the expiry of that 10 days by further notice determine the employment of your company under the subcontract."
The defendant also in that letter reserved the right to rely upon repudiatory breach in addition should a clause 29.2.2 notice have to be served.
"1. JL Construction is to make payment of £108,000, plus VAT, by CHAPS transfer to Capital Structures in respect of the material stored at Capital Structure's yard as jointly inspected on the 1st April 2004. Without derogating from paragraphs 6 and 7 below, both parties agree that the above stated sum is not and cannot be varied after payment.2. Prior to making the above CHAPS transfer Capital Structures will provide the vesting certificate in favour of JL Construction for the whole of the above material and the vesting certificate will contain a list of those materials. The vesting certificate will also incorporate agreed delivery dates. 3. The property in the above noted material will pass from Capital Structures to JL Construction immediately upon receipt of the CHAPS payment referred to under paragraph 1 and delivery will be made, as far as possible, in line with the agreed delivery dates.
4. Providing that access is allowed on or before the 30th April 2004 Capital Structures will return to site and ensure that all bolted connections comply with specification and that they are to the reasonable satisfaction of the building control officer. 5. When Capital Structures have complied with the requirements of 4 above, and when the building control officer has confirmed verbally or in writing that he is satisfied with the bolted connections then JL Construction are to immediately make payment to Capital Structures of £20,000 plus VAT by CHAPS transfer, this sum being part of the retention fund that is currently held by JL Construction. If the building control officer is not prepared to provide his confirmation that he is reasonably satisfied then the above payment is to be made immediately after the bolted connections have been completed in line with the requirements of the specification. 6. Capital Structures will remain liable for any defects in any work that they have executed and which arises from their faulty workmanship or materials for a period of 12 months following the date for the payment in paragraph 5 above."
Assuming any defects from faulty workmanship or materials, whether of defective works within the 12 month liability period, and whether the material works/remedial works are performed by the claimants or others, the alleged direct costs are not to exceed the balance of the retention held. There is a similar provision in relation to the carrying out of works to remedy latent defects in materials supplied only and not arising out of defective workmanship.
The caps therefore are modest and the period of liability very substantially truncated.
I go to para.10:
"In consideration of the above and save as set out above both parties acknowledge the above payments will be in full and final settlement of all and existing and/or future claims by Capital Structures, their servants, agents or any of them against JL Construction Ltd. in relation to or arising out of the works carried out at the above project and of all and any existing and/or future claims by JL Construction Ltd., servants, agents or against any of them against Capital Structures in relation to or arising out of the works carried out by Capital Structures at the above project.
It provides that:
"For the avoidance of doubt it is confirmed that if for any reason either party defaults on the terms of this agreement the parties are free to take any dispute to adjudication using the scheme rules under the Housing Grants Construction and Regeneration Act 1996."
In determining whether there has been illegitimate pressure the court takes account of a range of factors. These include whether there has been actual or threatened breach of contract, whether the person allegedly exerting pressure has acted in good or bad faith, whether the victim has any realistic practical alternative but to submit to the pressure, whether the victim protested at the time, and whether he affirmed and sought to rely on the contract. These are all relevant factors. Illegitimate pressure must be distinguished from the rough and tumble of the pressures of normal commercial bargaining.
See DSND Sub-Sea v. Petroleum Geoservices [2000] B.L.R.530, at p.545, and Carrillion Construction Ltd. v. Felix UK Ltd. [2001] B.L.R.1, in the judgments of Dyson J at p.6.
"In determining whether there was a coercion of will such that there was no true consent it is material to inquire whether the person alleged to have been coerced did or did not protest whether at the time he was alleged coerced into making the contract he did or did not have an alternative course open to him such as an adequate legal remedy, whether independently advised or whether after entering into the contract he took steps to avoid it."
That is derived from Pas On v. Lau Yin Lon [1980] A.C.614, in the speech of Lord Scarman at p.635. There is a further helpful passage at p.634, where the observation is made that:
"Commercial pressure without coercion is insufficient. If there is no sufficient coercion a threat to a pre-existing contractual obligation or an unfair use of a dominant bargaining position is insufficient to invalidate the consideration for the agreement."
"It now seems clearly established that a contract entered into under duress is voidable and not void. Consequently a person who has entered into a contact under duress may either affirm or avoid such contract after the duress has ceased and if he has voluntarily acted under it in full knowledge of all the circumstances he may be held bound on the ground of ratification, or if after escaping from duress he takes no steps to set aside the transaction he may be found to have affirmed it."
"At all times in connection with this adjudication JLC challenges the jurisdiction of the adjudicator to determine the matters in the referral notice. In particular, jurisdiction is disputed on the following bases:1.1. JLC was forced to enter into the settlement letter under economic duress, the details of which are set out in section A of the response above."
That contains many of the matters I have already made reference to:-.
"JLC therefore elects to have the settlement letter set aside and invite the adjudicator to conclude that for these reasons the settlement letter is voidable for JLC."
"I am accordingly of the option that is what is commonly called repudiation or total breach of a contract, whether acquiesced in by the other party or not, does not abrogate the contract thought it may relieve the injured party of the duty of further forfeiting the obligations which he has by the contract undertaken to the repudiated party. The contract is not put out of existence though all further performance of the obligations undertaken by each party in favour of the other may cease. It survives for the purpose of measuring the claims arising out of the breach and the arbitration clause survives for determining the mode of their settlement."
Similarly, in A & D Maintenance & Construction v. Pagehurst Construction, reported in 1999, Construction Law Journal at p.199, where I held that an adjudication provision similarly in those circumstances survives the termination of the contract.
"(a) enabled the parties to give notice at any time of its intention to refer a dispute to adjudication …"
And then going on to say:
"Even if the contract had been terminated the matters referred to the adjudicator remain disputes under the contract. Where there is a contract to which the Act applies, as in this case, and there are disputes arising out of the contract to be adjudicated, the adjudication provisions clearly remain operative just as much as an arbitration clause would remain operative. Had it been the intention of Parliament to limit the time wherein a party could give notice of intention to refer a matter to adjudication, in the exercise of his right under section 108(1) it could have imposed a clear limit."
"It must now be accepted as a possibility that circumstances which render the main contract voidable may also affect the agreement to arbitrate, and that in such cases the arbitrator may be deprived of the jurisdiction which he had at the outset ..."
And these are words that receive my emphasis:
"… if proper steps are taken to avoid the agreement from which his jurisdiction derives."
"If there has never been a contract at all there has never been as part of it an agreement to arbitrate. The greater includes the less. Further, a claim to set aside a contract on such grounds as fraud, duress or essential error, cannot be the subject-matter of a reference under an arbitration clause in the contract sought to be set aside."
In my judgment, that would apply equally to the adjudication provision.