BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Adonis Construction v O'Keefe Soil Remediation [2009] EWHC 2047 (TCC) (05 August 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/2047.html Cite as: [2009] CILL 2784, [2009] EWHC 2047 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
ADONIS CONSTRUCTION |
Claimant |
|
- and - |
||
O'KEEFE SOIL REMEDIATION |
Defendant |
____________________
Karim Ghaly (instructed by Steptoe & Johnson) for the Defendant
Hearing date: 21st July 2009
____________________
Crown Copyright ©
MR JUSTICE CHRISTOPHER CLARKE :
The facts
"suitability testing must be carried out prior to commencement of our works to prove the suitability of the site soils for stabilisation …"
and that
"the level or amount of any liquidated or consequential damages are to be agreed prior to any contractual commitment."
Adonis did not respond to the quotation.
4th March 2008
"We confirm our intention to enter into a sub-contract with you in accordance with your sub-contractors obligations contained within the following documentation ..."
Numerous documents were then specified, some of which, including the Minutes of the pre-start meeting, were to follow. The letter continued;
"The order for Soil stabilisation and associated works is to be for the fixed price of £ 38,710.8 Net, and will be Lump Sum strictly in accordance with the conditions within the JCT 98 – SFBC WITH CONTRACTORS DESIGN subcontract form DOM 2. You are to carry out these works in 1 Weeks, commencing 06/09/2008. We require receipt of your Method Statement and Risk Assessment for above named project no less than four weeks prior to commencement."
O'Keefe was invited to take the letter as "…an instruction to proceed procurement [sic] of all necessary labour and materials to enable you to meet the on site date…" The letter further provided:
"In the unlikely event that the sub contract does not take place you will be entitled to claim for substantiated costs up to the date of abortion. No loss of profit or consequential loss will be allowed."
"We look forward to receiving your formal order…
Within our quotation you will find we'd requested 14 day payment terms, which I hope will not be a problem for you. We've also carried out suitability testing on the material…
However, as we discussed the results of these will not be available until after we've completed our works.
I confirm the plant and labour will arrive on Thursday as agreed."
The draft order
"DRAFT SUB-CONTRACT ORDER [No order number]
The appended attestation page is to be duly signed Under [sic] seal and returned to the undersigned within 7 days."
"All costs in relation to adjudication to be borne by the Sub-Contractor."
("the costs clause").
"Note: In the event that the test results are not compatible with the treatment carried out then any remedial works and all associated costs, including consequential costs, will be the sole responsibility of O'Keefe Soil Remediation Ltd – as agreed L. Horsley/S. McQuade 5.3.08." [Emphasis added]
"The appended attestation page is to be duly signed and returned to the undersigned, by the following method as a deed within 7 days".
"Provided always that the candidate material is as described in ACL email dated 28.2.08."
Was there a construction contract in writing?
"The appended attestation page is to be duly signed under seal and returned to the undersigned within 7 days."
That was, in my judgment, a specification of a required mode of acceptance, which never occurred, rather than a term to be performed once the contact had been made by some other mode of acceptance.
"A contractual acceptance has to be a final and unqualified expression of assent to the terms of the offer. Conduct will only amount to an acceptance if it is clear that the offeree did the act in question with the intention of accepting the offer. But the test as to whether there has been such agreement is an objective one. It follows that conduct which demonstrates an apparent intention to accept can be sufficient, despite uncommunicated mental reservations on the part of the offeree. However, it seems to me that for that situation to arise, the conduct in question must be clearly referable to the offer and, in the absence of knowledge of the offeree's reservations, not reasonably capable of being interpreted as anything other than acceptance. Where the offeror knows that the offeree continues to have significant mental reservations about his offer - for example an unwillingness to accept certain terms of the offer or a determination to insist upon the incorporation into the contract of certain counter-proposals of his own - I doubt that a contract could be brought into existence by conduct."
"in all cases where there is a decision on one dispute or difference, and the adjudicator acts, materially in excess of jurisdiction or in breach of the rules of natural justice, the decision will not be enforced by the Court."