BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Hart (t/a D W Hart & Son) v Smith & Anor [2009] EWHC 2223 (TCC) (03 September 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/2223.html Cite as: [2009] EWHC 2223 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
MR S G HART T/A D W HART & SON |
Claimant/ Part 20 Defendant |
|
and – |
||
MR DENNIS SMITH (1) MRS JACQUI SMITH (2) |
Defendants/ Part 20 Claimants |
____________________
Patrick Clarke (instructed by Ashfords LLP) for the Defendants
Hearing dates: 19 August 2009
____________________
Crown Copyright ©
HH JUDGE TOULMIN CMG, QC :
Judgment
1) Payment by Hart of the sum of £7,381.20 under Interim Certificate 25.2) Payment by Hart in the sum of £138,185.79 under the Notice of Withholding.
3) Payment of interest on (1) and (2).
4) A declaration that Mr and Mrs Smith were entitled to a Certificate of Non-Completion in respect of each section of the work on the barns.
5) Payment of the adjudicator's fees.
6) Payment of Mr and Mrs Smith's legal costs.
1) There was no sum due in respect of Interim Certificate 25.2) There was no sum due under the Withholding Notice.
3) No interest was due.
4) While an entitlement to sectional certificates of non-completion may exist, the adjudicator could only reasonably give a one word positive or negative answer to the question posed. The adjudicator had not been asked in the referral to determine the extent of any delay to the works nor was he in a position to do so.
5) Mr and Mrs Smith should pay the adjudicator's fees.
6) Mr and Mrs Smith were not entitled to recover the costs of the referral.
Issues 1 and 3: Mr and Mrs Smith are entitled to be repaid the sum of £7,381.20 by Hart together with interest at the contract rate.
Issues 2 and 3: Mr and Mrs Smith are entitled to be paid the sum of £4,112.04 under the Notice of Withholding together with interest at the contract rate.
It is clear that this sum related to the claim in respect of the collapsed wall.
"In response Hart does not consider that the Smiths are entitled to any of the monies set out in the Withholding Notice. I agree with Hart that monies are not due for LD's, refinancing and legal costs and I set out below my reasons"
"37. I have found under Issue 4 that the Smiths are entitled to Certificates of Non-Completion. Clause 2.32 makes it clear that until the certificates are issued the Smiths cannot require Hart to pay the LD's"
"49. Clause 2.31 of the contract is quite specific 'if the contractor fails to complete the works or a section by the relevant completion date, the architect/contract administrator shall issue a certificate to that effect' I have underlined the word 'shall' as that is the important word which makes the requirement mandatory. Hart did not complete any of the Sections by the contractual dates and no extensions of time have been granted. Therefore as soon as the completion dates in the contract were passed without the work being completed, a certificate of delay should have been issued."
The Contentions of the Parties
"The Defendant's position is that the falling due of liquidated damages for delay is a natural consequence of that declaration (subject to the actual issue of the appropriate notices)"
Decision
"Where the parties to a construction contract engage in successive adjudications, each focussed upon the party's current rights and remedies, in my view the correct approach is as follows: at the end of each adjudication, absence special circumstances, the losing party must comply with the adjudicator's decision. He cannot withhold payment on the grounds of his anticipated recovery in a future adjudication based on different issues. I reach this conclusion both on the express terms of the Act and also from the line of authority referred to in this judgment."
1) Are both decisions valid?2) If yes, are both decisions enforceable?
3) If yes, the court should give effect to both decisions but in a way which does not favour one party or the other.
4) How each decision is to be enforced is a matter for the Court exercising its duty to act fairly.
"53a) Where it follows logically from an adjudicator's decision that the employer is entitled to recover a specific sum by way of liquidated and ascertained damages, then the employer may set off that sum against monies payable to the contractor pursuant to the adjudicator's decision provided that the employer has given proper notice (in so far as is required)
b) Where the entitlement to the liquidated and ascertained damages has not been determined expressly or implied by the adjudicator's decision then the question of whether the employer is entitled to set off liquidated and ascertained damages will depend on the contract and the circumstances of the case."