![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> O'Donnell Developments Ltd v Build Ability Ltd [2009] EWHC 3388 (TCC) (18 December 2009) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2009/3388.html Cite as: [2009] EWHC 3388 (TCC), 128 Con LR 141 |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
O'Donnell Developments Limited |
Claimant |
|
- and - |
||
Build Ability Limited |
Defendant |
____________________
Mr Simon Lofthouse QC (instructed by HBJ Gateley Wareing) for the Defendant
Hearing dates: 4th December 2009
____________________
Crown Copyright ©
The Hon. Mr. Justice Ramsey :
Introduction
(1) Whether ODD was entitled to £148,468.67 pursuant to the correction to the decision in Adjudication 8A in respect of sums paid.
(2) What Order should be made as to costs.
Background
(1) In respect of the calculation of sums paid against Valuation 25: At Item N of the table in the Decision where the Adjudicator calculated the sum due, the Adjudicator had set out the total of the payments to be deducted from the value of the works. In doing so the Adjudicator had included payments made against the value of the sub-contract works up to Valuation 25 but had also included a sum paid for loss and expense awarded in the decision in Adjudication 7 dated 28 August 2009, which was after the date of Valuation.
(2) In respect of the calculation of retention: At Item K in the table in the Decision the retention figure was calculated as 3% of the gross value of the works, including loss and expense (at Item F) and not 3% of the gross value excluding loss and expense.
Proceedings
Correction of sums paid
The Slip Rule
The Threshold Question
"If the parties are in dispute as to the obviousness (or otherwise) of the alleged 'slip', or the adjudicator does not accept that an error has been made, or does accept it but only some time after the publication of the decision, then it is thought that the approach in Bouygues will remain appropriate."
Review of the exercise of the slip rule
"The figure for the amount paid to date includes a payment by BAL in respect of the Decision of the Adjudicator in Adjudication No 7 of the gross sum of £148,468.58. We would refer you to paragraphs 162 to 184 of the Decision in Adjudication No 7 in this regard. The sum represents additional loss and expense incurred by ODD as a result of delays to the Sub-Contract Works which the Adjudicator determined were the responsibility of BAL. Consequently, this sum is additional to the amounts set out in [Application for Payment] 25 and Valuation 25 and should not have been deducted from the total sum awarded in this adjudication. In deducting this amount from the sum you have awarded, in effect you have restricted the effect of the Decision of the Adjudicator in Adjudication No 7.
We note that the figure in respect of the amounts paid to date was determined on the basis of our recent e-mail exchange, and we apologise for not making clear during that exchange that part of the sums paid to date represented loss and expense."
"The first matter ODD wishes you to "correct" is that an additional £148,468.58 for loss and expenses is due as a result of the effect of the Adjudicator's Decision in Adjudication 7. This is not a patent error in that it is a simple arithmetical error. It should not be forgotten that the loss and expense now raised by ODD was not referred to in any of the documents which has formed part of this adjudication. It is BAL's position that it cannot be a patent error if you are now being asked to consider something ODD chose (or forgot to) make you aware of at the appropriate time. You clearly considered the amounts due to ODD and the effect of any sums previously paid to date. For you to now "correct" your decision as ODD seeks you would in fact be addressing your mind to an issue for the second time clearly in breach of paragraph 50(c)[of YCMS] above. "
"I have considered the matters identified and the authority referred to. I conclude that there is an implied term that I may correct a slip provided the correction is made promptly. In this instance, the alleged slips were identified within 24 hours of the publication of my Decision and BAL has provided its comments within 48 hours of the publication of my Decision.
Therefore if my Decision does contain a slip, then my view is that I can now correct it."
"In this instance, in addressing the question of whether ODD was entitled to further payment my intention was to give effect to my findings in relation to the matters decided by me and also the matters decided by previous Adjudicators. In that regard, my failure to account for the fact that the amount paid to date included (on BAL's schedule) £148,468.67 in respect of additional loss and expense awarded in Adjudication No.7 was an inadvertent slip and did not reflect my intention. Similarly, the failure to omit the amount of loss & expense from my calculations of the retention was also an inadvertent slip and did not reflect my intention. I therefore consider it appropriate to correct those slips."
Costs
Summary
(1) ODD is entitled to summary judgment for £148,468.67;
(2) ODD is entitled to its costs of the summary judgment application to be assessed on an indemnity basis to 25 November 2009 and from that date on a standard basis, if not agreed;
(3) ODD is entitled to its costs of BAL's withdrawn application to stay execution, to be assessed on a standard basis, if not agreed.