BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Working Environments Ltd v Greencoat Construction Ltd [2012] EWHC 1039 (TCC) (24 April 2012) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2012/1039.html Cite as: [2012] BLR 309, 142 ConLR 149, [2012] EWHC 1039 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
WORKING ENVIRONMENTS LIMITED |
Claimant |
|
- and - |
||
GREENCOAT CONSTRUCTION LI MITED |
Defendant |
____________________
Fionnuala McCredie (instructed by Freeth Cartwright LLP) for the Defendant
Hearing date: 17 April 2012
____________________
Crown Copyright ©
Mr Justice Akenhead:
The Background Facts
Work Done | £1,504,539.95 |
Variations | £337,193.78 |
Cumulative Total | £1,841,733.73 |
Less 3% retention | £55,252.01 |
Net Total | £1,786,481.72 |
Breakdowns of the first two figures were provided. Allowing for previous payments, a total sum of £488,153.45 was claimed.
Work Done | £1,475,128.12 |
Variations | (£52,030.01) |
Cumulative Total | £1,423,098.11 |
Less items being withheld | (67,412.93) |
Sub-total | £1,355,685.18 |
Less 3% retention | £40,670.56 |
Net Total | £1,315,014.63 |
There were enclosed breakdowns of how these various sums were made up or calculated. £16,686.36 was said to be due for payment. In respect of the "items being withheld", the breakdown was headed "Notification of items being withheld from this Valuation", and it was summarised on the third page as follows:
"Liquidated Damages | tbc |
Replace fire protection | £13,123.00 |
Removal of plasterboard | £4,001.73 |
Attendance by Modus at crane Lift | £1,845.00 |
Damage to Ceiling installation | £12,500.00 |
Additional Greencoat Administration/TSM Time£16,712.70 | |
Weekend Supervision | £1,500.00 |
Builderswork/Fire Protection Return Visits | £5,000.00 |
Defective Works – Grilles | £10,730.50 |
Defective Works - Condenser Water Tank | £2,000.00 |
[Total] | £67,412.93" |
The Adjudication
"3. The Respondent has failed to value the properly executed works including variations and has found a lesser sum due of £16,686.36 in their summary of account dated 2 December 2011.
4. Further, variations properly completed are to the value of £318,362.90 whereas the Respondent has valued these at £-52.030.01…The account is thereby undervalued by £370,392.91 and paid short. This sum is due for payment at application No.10 on 14 January 2011 and interest will accrue on the underpayment from that date.
5. By their summary of account dated 2 December 2011 the Respondent also seeks to set off. The Referring Party avers that the sums [sic] £67,412.93 alleged by the Respondent to be owed to them by the Referring Party is[sic] not owed or payable in part or in whole and as such the Respondent has no right to set these monies off at interim application No. 10 or at all.
6. The Referring Party further avers that it is for the Respondent to show that their set off is lawful and they have an established right on the money claimed and taken. Further that in making such set off the burden of proof is on the Respondent as to liability of the Referring Party to pay and the sum which is to be paid.
7. The Referring Party aver [sic] that a right to set off either at common law, in equity or under the contract is not merely a matter of giving notice; the substantive sums must be payable or owed to the Respondent under the contract or at common law before any right to set off arises to which an effective notice can be given. The Referring Party avers that the Respondent has no such right and disputes both liability and quantum of the sums set off against application…No 10…
The nature and a brief description of the dispute
The dispute is over:
- Application No.10 and summary of account 2 December 2011 including:
- undervaluation of variations completed by £370,392.91
- Abatement of the contract sum work completed by £32,702.32
- Set off by the Respondent of £67,412.93
- The law of set off
Details of where and when the dispute has arisen
9. The dispute arose by the Respondent underpaying and deducting sums as set-off from interim payments application No. 10
Redress sought by the Referring Party
The Referring Party requests that the adjudicator:
A. Give a declaration that in the Respondent's summary of account dated 2 December 2011, the contract works properly completed are undervalued in the sum £32,702.32 or such sum as the adjudicator finds;
B. Give a declaration that in the Respondent's summary of account dated 2 December 2011 variations properly completed are undervalued in the sum of £370,392.91 or such sum as the Adjudicator finds;
C. Give a declaration that in the Respondent's summary of account dated 2 December 2011 they have wrongfully made a set off in the sum of £67,412.93 or such sums as the Adjudicator finds;
D. Decide that the Referring Party is to be paid:
the additional sum of £32,702.32 for undervalued contract work properly completed
the additional sum of £370,392.91 for variations properly completed or such sum as the Adjudicator decide
E. decide that the Respondent repay the sum wrongfully set off in the sum of £67,412.93 or such sum as the Adjudicator decide
F. Decide that the Respondent is to pay the sums decided by the Adjudicator within 3 days of his decision.
G. Decide or otherwise direct that the Respondent pays the Adjudicator's fees and costs in the undertaking of this Adjudication…"
"31. Pursuant to clause 4.10.3 of the Sub-Contract, the Respondent has until 6 January 2012 in which to serve a withholding notice against the sums applied for by the Referring Party in the Application. The Respondent issued a withholding notice on 5 January 2012, a copy of which is appended at Tab 2 ("the Withholding Notice") together with a copy of the accompanying covering letter from the Respondent to the Referring Party of the same date. The Adjudicator will note from the Withholding Notice that the Respondent has deducted the sum of £199,944.23.
32. As the Withholding Notice does not form part of the purported dispute referred in this adjudication (because the adjudication was prematurely referred before the Withholding Notice was issued) the Adjudicator is unable to consider the effect of the same on any sum that might be due to/from the Referring Party by the final date of payment. Furthermore, the Respondent does not confer any such jurisdiction on the Adjudicator. The Respondent wishes to clarify that the Withholding Notice and the accompanying covering letter are appended simply to evidence the existence of the Withholding Notice and to establish that the same has been served within the time limits set out in the Sub-Contract. The inclusion of the Withholding Notice is not and should not be constructed as a waiver of any of the Respondent's jurisdictional objections.
33. As the Adjudicator cannot consider the effects of the Withholding Notice in this adjudication, the Adjudicator cannot direct as to payment as he cannot properly determine what sums might be due to/from Referring Party under the terms of the Sub-Contract by the final date for payment without considering the effect of the Withholding Notice. All he can do (subject to the foregoing) is to decide the value of the Certificate, not what should be paid by whom and to whom by the final date for payment. Such is the impossible position that the Adjudicator is placed in by the Referring Party; he cannot properly decide what sums might be due to/from the Referring Party without considering the effect of the Withholding Notice and this is beyond his jurisdiction. It cannot be the intention of Parliament that a party can seek payment in adjudication before the other party has had the opportunity to issue a withholding notice and/or before the final date for payment has lapsed."
"Liquidated Damages | [Not known as at 2nd Dec] |
Replace fire protection | £13,163.00 [+] |
Removal of plasterboard | £5,205.89 [+] |
Attendance by Modus at crane Lift | £1,160.00 [-] |
Damage to Ceiling installation | £7,276.75 [-] |
Additional Greencoat Administration/TSM Time | £13,712.59 [-] |
Weekend Supervision | £4,752.00 [-] |
Builderswork/Fire Protection Return Visits | £4,525.00 [-] |
Defective Works – Grilles | £2,600.00 [-] |
Defective Works - Cooling Tower Water Tank | £2,000.00 |
[Total] | £54,395.23" |
"10. Liquidated Damages £120,000.00
Further to our notice of Non-Completion dated the 2nd November the costs of liquidated and ascertain damages applicable to [WE].
11. Defective Works – Pumps £9,629.00
The cost of replacing the undersized pumps.
12. Lack of co-ordination and BREEAM £11,520.00
An omission due to the fact [WE] did not co-ordinate all the services or expend resource on the BREEAM obligations."
The total for withholding was £199,944.23.
"Of Greencoat "withholding" letter" 5th Jan to WEL (Response to Referral tab 2) which of the 12 heads does Greencoat intend to set off from monies otherwise due on 14th January?"
The response from Greencoat's solicitor was on 28 February 2012:
"As you will recall, the Respondent has raised issues concerning your jurisdiction in the Response relating to, inter alia, the 5 January 2012 letter and the consequences thereof. The Respondent reserves its right to rely on any and all the jurisdiction matters it has raised before and during this adjudication should it become necessary for it to do so.
In light of the above, the Respondent relies on 1-9 of the set off/counterclaim items as set out in the Response and the Respondent otherwise repeats its previous submissions on jurisdiction. The Respondent also repeats that no discourtesy is meant to you by it raising these issues on jurisdiction. Such issues have arisen because of the way that the Referring Party has conducted itself before and during this adjudication, not because of the way that you have conducted the same."
The adjudicator replied on the same date:
"Thankyou. I have understood this to mean that Greencoat will not attempt to set off heads 10, 11, 12 in the 5th Jan Notice of Withholding".
Greencoat's solicitors replied 30 minutes later:
"It is the Respondent's position that you do not have jurisdiction to decide items 10, 11 and 12 for the detailed reasons stated in the Response. The Respondent does, however, reserve its position in respect of these items come enforcement should it become necessary for it to do so."
The brief and elliptical response was:
"I am clear as to jurisdiction. I have no power to deal with items 10 11 12 If [sic] there is no intention to set off. Intention is not clear and I will bring them in."
These Proceedings
The Law
"The decision of the adjudicator shall be binding on the parties, and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides for arbitration or the parties otherwise agree to arbitration or by agreement) between the parties"
Since a dispute may involve only declaratory as opposed to directive relief, it is therefore within the confines of this paragraph that, if there is a declaration as to rights, the parties must respect and comply with that decision as if it was right even though final dispute resolution has not yet occurred; they must do so until such final resolution occurs and the decision is conformed, varied or set aside.
"54. It is, I believe, accepted by both parties, correctly in my view, that whatever dispute is referred to the Adjudicator, it includes and allows for any ground open to the responding party which would amount in law or in fact to a defence of the claim with which it is dealing. Authority for that proposition includes KNS Industrial Services (Birmingham) Ltd -v- Sindall Ltd [2001] 75 Con LR 71.
55. There has been substantial authority, both in arbitration and adjudication, about what the meaning of the expression "dispute" is and what disputes or differences may arise on the facts of any given case. Cases such as Amec Civil Engineering Ltd -v- Secretary of State for Transport [2005] BLR 227 and Collins (Contractors) Ltd -v- Baltic Quay Management (1994) Ltd [2004] EWCA (Civ) 1757 address how and when a dispute can arise. I draw from such cases as those the following propositions:
(a) Courts (and indeed adjudicators and arbitrators) should not adopt an over legalistic analysis of what the dispute between the parties is.
(b) One does need to determine in broad terms what the disputed claim or assertion (being referred to adjudication or arbitration as the case may be) is.
(c) One cannot say that the disputed claim or assertion is necessarily defined or limited by the evidence or arguments submitted by either party to each other before the referral to adjudication or arbitration.
(d) The ambit of the reference to arbitration or adjudication may unavoidably be widened by the nature of the defence or defences put forward by the defending party in adjudication or arbitration…
In my view, one should look at the essential claim which has been made and the fact that it has been challenged as opposed to the precise grounds upon which that it has been rejected or not accepted. Thus, it is open to any defendant to raise any defence to the claim when it is referred to adjudication or arbitration. Similarly, the claiming party is not limited to the arguments, contentions and evidence put forward by it before the dispute crystallised. The adjudicator or arbitrator must then resolve the referred dispute, which is essentially the challenged claim or assertion but can consider any argument, evidence or other material for or against the disputed claim or assertion in resolving that dispute."
"65. On the severability issue, I conclude, albeit obiter in the result, as follows:
(a) The first step must be to ascertain what dispute or disputes has or have been referred to adjudication. One needs to see whether in fact or in effect there is in substance only one dispute or two and what any such dispute comprises.
(b) It is open to a party to an adjudication agreement as here to seek to refer more than one dispute or difference to an adjudicator. If there is no objection to that by the other party or if the contract permits it, the adjudicator will have to resolve all referred disputes and differences. If there is objection, the adjudicator can only proceed with resolving more than one dispute or difference if the contract permits him to do so.
(c) If the decision properly addresses more than one dispute or difference, a successful jurisdictional challenge on that part of the decision which deals with one such dispute or difference will not undermine the validity and enforceability of that part of the decision which deals with the other(s).
(d) The same in logic must apply to the case where there is a non-compliance with the rules of natural justice which only affects the disposal of one dispute or difference.
(e) There is a proviso to (c) and (d) above which is that, if the decision as drafted is simply not severable in practice, for instance on the wording, or if the breach of the rules of natural justice is so severe or all pervading that the remainder of the decision is tainted, the decision will not be enforced."
(f) In all cases where there is a decision on one dispute or difference, and the adjudicator acts, materially, in excess of jurisdiction or in breach of the rules of natural justice, the decision will not be enforced by the Court.
In my view, this reflects the policy of the 1996 Act in that adjudication decisions are to be binding on the parties pending final resolution of the given disputes.
Discussion
Decision
Costs and Interest