[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Parkway Construction Ltd (In Liquidation) v Howard De Walden Estates Ltd [2014] EWHC 1533 (TCC) (15 May 2014) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2014/1533.html Cite as: [2014] EWHC 1533 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
PARKWAY CONSTRUCTION LIMITED (in liquidation) |
Claimant |
|
- and - |
||
HOWARD DE WALDEN ESTATES LIMITED |
Defendant |
____________________
Ronan Hanna (instructed by Taylor Wessing LLP) for the Defendant
Hearing date: 9 May 2014
____________________
Crown Copyright ©
Mr Justice Akenhead:
Background
"2.22 If the Contractor fails to complete the Works….by the relevant Completion Date, the… Contract Administrator shall issue a certificate to that effect…
2.23.1 Provided:
.1 the Contract Administrator has issued a certificate under rule 2.22; and
.2 the Employer has informed the Contractor in writing before the date of the Final Certificates that he may require payment of, or may withhold or deduct, liquidated damages,
the Employer may, not later than 5 days before the final date for payment of the debt due under the Final Certificate, give notice in writing to the Contractor in the terms set out in clause 2.23.2.
.2 A notice from the Employer under clause 2.23 shall state that for the period between the Completion Date and the date of practical completion of the Works…:
.1 he requires the Contractor to pay liquidated damages at the rate stated in the Contract Particulars or lesser rate stated in the notice, in which event the Employer may recover the same as a debt; or
.2 that he will withhold or deduct liquidated damages at the rate stated in the Contract Particulars…from monies due to the Contractor."
"If the Contractor's employment is terminated…
.1 the Employer may employ and pay other persons to carry out and complete the Works and to make good any defects of the kind referred to in clause 2.30…
.3 …clauses 8.7.4, 8.7.5 8.8 shall thereupon apply and any other provisions of this Contract which require any further payment or any release of retention to the Contractor shall cease to apply;
.4 within a reasonable time after the completion of the Works the making good of defects…an account of the following shall be set out in a certificate issued by the...Contract Administrator or a statement prepared by the Employer:
.1 the amount of expenses properly incurred by the Employer, including those incurred pursuant to clause 8.7.1…and of any direct loss and/or expense to the Employer and for which the Contractor is liable, whether arising as a result of the termination or otherwise;
.2 the amount of payments made to the Contractor; and
.3 the total amount which would have been payable for the Works in accordance with this Contract.
.5 If the sum of the amounts stated under clauses 8.7.4.1 and 8.7.4.2 exceeds the amounts stated under clause 8.7.3, the difference shall be a debt payable by the Contractor to the Employer or, if that sum is less, by the Employer to the Contractor."
The Particulars of Claim
"…Design information was effectively provided on a "design as the Contract went along" basis, which meant that the Claimant was prevented from progressing its work, organising its supplies and lead times properly or working on anything other than limited work fronts at the same time. Particulars of the Claimant's position as to the delays caused to the Claimant by this approach to design provision by the Defendant are also set out in the Claimant's formal notification under clause 2.19.1 of 23rd December 2008."
This letter, not attached, only seeks to "provide general areas of delay which have prolonged the works" with a detailed submission being "presently drafted". It refers in very general terms to some but not all the heads of delay set out in the later May 2010 delay claim and provides no explanation as to how or for how long the Works were delayed at all or by any of the general matters raised in the letter.
"Following our meeting a few weeks ago, I will have to issue a certificate on non-completion for the project as no explanation for an extension of time has been received. I still believe that a maximum of 10 week extension from the 22nd September is the most that can be justified, although I will review your information and the level of damages once I receive your details."
It relied on this as an admission by Mr Fisher "that some extension of time is due".
The Summary Judgment Application and evidence
"1.1 the Completion Date be extended beyond the time when the Claimant's involvement on the Contract ceased (March 2009)…or for such alternative period as the court can determine on the facts matters [sic] set out in the Particulars of Claim and without carrying out a full analysis of the matter is notified to the Contract Administrator…
1.2 alternatively, the Defendant extend the Completion Date to allow for a reasonable period to have completed the Works beyond the time when the Claimant's involvement on the Contract ceased (or for such alternative period as the Defendant shall reasonably determine on the facts set out in the Particulars of Claim and other matters notified to the Defendant by the Claimant and any order made pursuant to sub-paragraph 1.3 below).
1.3 alternatively, any late or inadequate design and information provision in respect of the gantry, stair enclosure and staircase would in principle entitle the Claimant to an extension of time to allow the Claimant a reasonable period of time to complete the Works from the time of such provision being properly made.
1.4 [the] Defendant is not entitled to deduct Liquidated and Ascertained Damages in the sum of £630,857.14 or, alternatively, the Defendant is not entitled to deduct Liquidated and Ascertained Damages to the extent that the contract falls to be extended pursuant to any order pursuant to sub-paragraphs 1.1-3 above.
1.5 the Claimant is in principle entitled to loss and expense commensurate with such extension of time and is awarded under sub-paragraphs 1.1-3 above.
1.6 the Defendant is not entitled to deduct or take into account the sums set out and referred to in sub-paragraphs 29.4 of the Particulars of Claim when calculating the sums otherwise due to be Claimant.
1.7 the Defendant is not entitled to deduct or take into account the sums set out and referred to in sub-paragraphs 29.5-29.6 of the Particulars of Claim when calculating sums otherwise due to the Claimant unless it shall have provided to the Claimant by [-] April 2014:
.1 reasonable and complete details of the allegedly defective and incomplete works sufficient for the Claimant to understand what is alleged by the defendant,
.2 particulars of the documents/contractual provisions allegedly not complied with all completed by the Claimant by reason of the alleged defects incompletions [sic],
.3 reasonable and complete details of what work was allegedly carried out by and/or on behalf of the Defendant to rectify and/or complete the allegedly incomplete and defective work.
.4 particulars out how the sums claimed as deductions by the Defendant were caused by and/or relate to the information provided pursuant to sub-paragraphs 1.1-3 above.
1.8 in breach of clause 8.7.3 of the Contract the Defendant has failed to provide a proper account and/or certificate as required therein,
1.9 the Defendant provide on or before [ April 2014] a proper account and/or certificate (taking into account the orders and declarations made pursuant to paragraph 1.1-8 above) as required by clause 8.7.3 of the Contract,
1.10 the Defendant do pay the sum accounting/certified pursuant to paragraph 1.9 about it the Claimant pursuant to sub-clauses 8.7.4 of the Contract."
The Law and Practice
"93. In Swain v. Hillman Lord Woolf gave this further guidance at pp 94 and 95:
"It is important that a judge in appropriate cases should make use of the powers contained in Part 24. In doing so he or she gives effect to the overriding objectives contained in Part 1. It saves expense; it achieves expedition; it avoids the court's resources being used up on cases where this serves no purpose, and, I would add, generally, that it is in the interests of justice. If a claimant has a case which is bound to fail, then it is in the claimant's interests to know as soon as possible that that is the position. Likewise, if a claim is bound to succeed, a claimant should know this as soon as possible….
"Useful though the power is under Part 24, it is important that it is kept to its proper role. It is not meant to dispense with the need for a trial where there are issues which should be investigated at the trial. As Mr Bidder put it in his submissions, the proper disposal of an issue under Part 24 does not involve the judge conducting a mini trial, that is not the object of the provisions; it is to enable cases, where there is no real prospect of success either way, to be disposed of summarily."
(6) Whether the claim should be summarily struck out
94. For the reasons which I have just given, I think that the question is whether the claim has no real prospect of succeeding at trial and that it has to be answered having regard to the overriding objective of dealing with the case justly. But the point which is of crucial importance lies in the answer to the further question that then needs to be asked, which is - what is to be the scope of that inquiry?
95. I would approach that further question in this way. The method by which issues of fact are tried in our courts is well settled. After the normal processes of discovery and interrogatories have been completed, the parties are allowed to lead their evidence so that the trial judge can determine where the truth lies in the light of that evidence. To that rule there are some well-recognised exceptions. For example, it may be clear as a matter of law at the outset that even if a party were to succeed in proving all the facts that he offers to prove he will not be entitled to the remedy that he seeks. In that event a trial of the facts would be a waste of time and money, and it is proper that the action should be taken out of court as soon as possible. In other cases it may be possible to say with confidence before trial that the factual basis for the claim is fanciful because it is entirely without substance. It may be clear beyond question that the statement of facts is contradicted by all the documents or other material on which it is based. The simpler the case the easier it is likely to be to take that view and resort to what is properly called summary judgment. But more complex cases are unlikely to be capable of being resolved in that way without conducting a mini-trial on the documents without discovery and without oral evidence. As Lord Woolf said in Swain v Hillman, at p 95, that is not the object of the rule. It is designed to deal with cases that are not fit for trial at all."
Discussion
(a) What the Particulars of Claim are seeking to do is to focus and rely upon the gantry and stairway complaints which on any account are thought by both parties to have only begun to have had an effect (if any) in or after December 2008 in the sense that Parkway appears to think that it has established by way of admission by Mr Fisher on December 2008 to the effect that some entitlement to extension of time was due for other reasons for events which occurred before then.
(b) It is absolutely clear however that there is a factual dispute about whether there is any entitlement to extension of time for the pre-December 2008 events. The so-called admission is at best a limited one. Mr Fisher in the e-mail in question is actually saying first that he will have to issue a certificate of non-completion because to date no explanation in relation to any extension of time claim had been received from Parkway. That is another way of saying that Parkway had not up to that time established any such entitlement. He only goes on to say that "a maximum of" 10 weeks extension is the most that could be justified. That is not an admission in any event that 10 weeks extension is justified but that at most 10 weeks could possibly be justified; the tone of the letter however is that it has not yet been justified.
(c) The reality seems to have been however no arguably comprehensive extension of time claim was submitted until about May 2010 some 18 months later. That was by way of an expert's report which is not even prayed in aid by Parkway in these proceedings; arguably, that expert was not independent and its contents have not sought to be supported as such by Parkway.
(d) Mr Fisher addresses the issue why the pre-December 2008 events were on analysis of the contractual fault or responsibility of Parkway. There is little evidence from Parkway which is supportive of any challenge to this, other than the alleged admission on 2 December 2008, which, even if it was a clear admission (which it is not), is not in some way binding or even of much weight, particularly where there is evidence supported by statements of truth that no grounds exist for any such extension of time.
(e) There are the clearest factual disputes on the evidence before the court whether the gantry and stairway matters gave rise to any delay. Unsurprisingly, the contract between the parties in Clause 2.11.2 calls for information and instructions to be provided "at the time it is reasonably necessary for the Contractor to receive" them. That raises currently irreconcilable factual and evidential issues between the parties, namely as to whether Parkway actually reasonably needed the information relating to these areas of the works before that time that it actually received it.
(a) The first is the argument that, once there is a termination for insolvency or indeed otherwise, any accrued right including for liquidated damages for delay in favour of the Employer (HDW in this case), is eradicated or, as put in argument, wiped clean. One only has to articulate the point to appreciate that, in the absence of the clearest wording, this would make no commercial sense at all. One could take an example of a contractor in culpable delay of 2 years on a 1 year contract whose employment is terminated for its fault; it would be extraordinary if the accrued rights to liquidated or indeed common law damages were eradicated. In my view, this interpretation is so unlikely as, at the very least, to give rise to a highly arguable case otherwise, If I had to decide that point now, I would decide that Parkway was wrong and that accumulated rights of action remain enforceable on and after termination.
(b) Although initially pressed otherwise, Mr Jones properly conceded that it was reasonably arguable that a statement had been provided by HDW under the provisions of Clause 8.7.4. Once he accepted that, his argument that the Court should in effect order that HDW or the Contract Administrator should do it again must fail because it does not have to be repeated. What much of the argument about this failed to appreciate is that there would be little or no point requiring HDW to redo this as the evidence suggests that it would come up with the same answer and also that any damages flowing from a failure to issue such an account or statement would only be whatever the current facts would reveal after a trial. Thus, if no extension of time is due, probably HDW would be entitled to the full liquidated damages claimed and Parkway would be entitled to little or no related loss and expense. Another problem and obstacle for Parkway in this regard is that its Particulars of Claim do not plead let alone explain that there has been a contractual termination or in fact that it was or became insolvent and if so when; the Court does need to tread carefully in inferring these types of fact.
(c) A slightly better argument was deployed by Mr Jones which related to the scope of any conditions precedent relating to the imposition of liquidated damages. The wording of Clause 2.23.1 does suggest that the Contract Administrator's certificate is a pre-condition but here it was not argued that there was not one, a valid concession, given that one seems to have been issued on 3 December 2008. It is also arguable that the Clause 2.23.1.2 notice is a necessary pre-condition but there is strong evidence that time and time again such notice was given not least during the Pre-Action Protocol process. Mr Jones' point was that on analysis the further notice which follows the proviso wording ("the Employer may…give notice in writing to the Contractor in the terms set out in clause 2.23.2") was also a pre-condition. This is an arguable issue which does not fall for decision but, if I had to decide the point now, I would have decided that it was not a pre-condition because it is not subject to proviso type language.
Decision