BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> London Borough of Bromley v Heckel [2015] EWHC 3606 (TCC) (10 December 2015) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2015/3606.html Cite as: [2015] EWHC 3606 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
London Borough of Bromley |
Claimant |
|
- and - |
||
Stephen Heckel |
Defendant |
____________________
Mr Scott Allen (instructed by RPC LLP) for the Defendant
Hearing dates: 12th November 2015
____________________
Crown Copyright ©
Mr Justice Edwards-Stuart:
Introduction
The building contract between the School and/or SJH and Keyspace.
The building contract between the School and/or SJH and Vinstrata.
The tender documentation in respect of the supply and installation of a modular building by Keyspace.
The tender documentation in respect of the enabling works by Vinstrata.
The letter of appointment from the School to SJH.
A schedule of SJH's Professional Indemnity insurance.
"6.1.1 The School, rather than our client, contracted with Keyspace and VBLL. Our client is not in possession of the requested contractual documents.
6.1.2 As stated above, our client was verbally instructed by the School to "project manage" the construction of the Centre. No letter of instruction from the School exists. It is noteworthy that you have embarked on this cause [sic] of action without even acknowledging this basic point; and
6.1.3 There is no basis on which you are entitled to any documents or information relating to our client's insurance arrangements."
This could hardly have been clearer.
a. it was not an application for pre-action disclosure because the claim form had already been issued; andb. it was not an application for specific disclosure, because it was not limited to any particular class or classes of documents; and
c. since no Defence had been served, it was not immediately obvious what matters "were at issue between the Parties"; and
d. In the circumstances the disclosure sought went much wider than the ambit of standard disclosure.
The course of the application in more detail
"The facts stated herein are either true to my own knowledge or have been derived by me from the study of the documents in this matter."
The witness statement was not, as it should have been, supported by a statement of truth. The effect of this is that so far as the facts stated in the witness statement were derived by Mr Bradshaw from a study of the documents in the case, those facts were not supported by any form of assertion that they were true, only that they were not within his own knowledge because they had been derived from a study of the documents.
"13. I understand that the terms of SJH's involvement was set out in a written agreement ("the Contract"), which is (inter alia) the subject of this Application.
14. SJH organised two tenders - one for the construction of the building and another for the ground works. Tenders were returned to him and he advised the School of the outcome and recommended one company ("Vinstrata") for the ground works and the other ("Keyspace") to erect a pre-fabricated building over those ground works.
15. I understand that those contracts were made by SJH with the two companies, although no copy of either the tender papers or the contracts was ever produced either to the Council or to the school's officers. I am also seeking copies of those contracts in this application. "
"Again, in my experience as a Solicitor with extensive experience of dealing with contracts, I find it difficult to understand how the Defendant failed to enter into any formal written contracts."
This appears to be a further allegation that Mr Heckel entered into the building contracts on his own account. I find it difficult to understand what experience Mr Bradshaw may have had as a solicitor that has led him to think that Mr Heckel might have entered into formal building contracts in his own name on behalf of the School.
The application for an extension of time for service of the Particulars of Claim
"37. In my judgment, when regard is had to these authorities the key question must always be whether or not, at the time of issuing a Writ, the claimant was in a position properly to identify the essence of the tort or breach of contract complained of and if given appropriate time to marshall what it knew, to formulate Particulars of Claim. If the claimant was not in a position to do so, then the claimant could have no present intention of prosecuting proceedings, since it had no known basis for doing so. Whilst therefore the absence of present intention to prosecute proceedings is not enough to constitute an abuse of process, without the additional absence of known valid grounds for a claim, the latter carries with it, as a matter of necessity, the former. If a claimant cannot do that which is necessary to prosecute the claim by setting out the basis of it, even in a rudimentary way, a claimant has no business to issue a Claim Form at all "in the hope that something may turn up". The effect of issuing a Writ or Claim Form in such circumstances is, so the plaintiff/claimant hopes, to stop the limitation period running and thus deprive the defendant of a potential limitation defence. The plaintiff/claimant thus, unilaterally, by its own action, seeks to achieve for itself an extension of the time allowed by statute for the commencement of an action, even though it is in no position properly to formulate a claim against the relevant defendant. That must, in my judgment, be an abuse of process and one for which there can be no remedy save that of striking out the proceedings so as to deprive the claimant of its putative advantage. The illegitimate benefit hopefully achieved can only be nullified by this means. Whatever powers may be available to the court for other abuses, if this is an abuse, there is only one suitable sanction.
. . .
In my judgment therefore if Nomura, at the time of issuing its Claim Form, was not in a position to do the minimum necessary to set out the nature of the claim it was making, it would be seeking an illegitimate benefit, namely the prevention of further time running under the Limitation Acts for a claim which it could not properly identify or plead. That would be an abuse of the process of the court. Insofar as it sought to make any claim in contract, it would be necessary for it to be able to identify the particular contract and the alleged breach. In the case of any breach of tortious duty, it would be necessary for it to be in a position to identify the essential acts or omissions which constituted the breach of duty, negligence or negligent misstatement. For the purposes of negligent misstatement, Nomura would have to be able to identify what advice or information was inaccurate and what was given negligently, at least in essence. If Nomura was not in a position to do this, it was not in a position properly to issue a claim, since it could not have proceeded properly to plead Particulars of Claim without the off chance occurring that something would turn up. In such circumstances it could have no present intention to pursue a claim since it had no sufficient idea of the claim it wished to pursue."
Should the court exercise its discretion to extend the time?
"To my mind, the established principles, the amendments to the CPR that I have identified, and the terms of the Protocol all point in one direction: parties who issue late are obliged to act promptly and effectively and, in the absence of sound reasons (which will seldom if ever include a continuing failure to comply with pre-action protocol requirements) the proceedings should be served within four months or in accordance with any direction from the Court. A claimant who does not do so and (where the Protocol for Construction & Engineering Disputes applies) who does not obtain directions on notice does so at extreme peril."
"The Claim was issued to protect the Council against time bar. When the Claim was issued, we immediately applied for a Hearing of the matter now before this Court."