BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?

No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!



BAILII [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback]

England and Wales High Court (Technology and Construction Court) Decisions


You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Stratton & Anor v Patel & Anor [2016] EWHC 2032 (TCC) (03 August 2016)
URL: http://www.bailii.org/ew/cases/EWHC/TCC/2016/2032.html
Cite as: [2016] EWHC 2032 (TCC)

[New search] [Printable RTF version] [Help]


Neutral Citation Number: [2016] EWHC 2032 (TCC)
Case No: HT-2012-000013

IN THE HIGH COURT OF JUSTICE
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT

Royal Courts of Justice
Strand, London, WC2A 2LL
03/08/2016

B e f o r e :

Mr ter HAAR QC
(Sitting as a Deputy High Court Judge

____________________

Between:
JOHN MICHAEL STRATTON
(2) MUHAMMAD AZEEM KHAN-SHERWANI

Claimant
- and -


MAHESH SHANTILAL PATEL

- and -

MP BUILDING LIMITED
Defendant

____________________

Mr Karl King (instructed by FS Law) for the Claimant
Mr Matt Hutchings (instructed by Kidd Rapinet) for the Defendant
The Third Party was not represented
Hearing dates: 1 July 2016

____________________

HTML VERSION OF JUDGMENT
____________________

Crown Copyright ©

    Mr Roger ter Haar QC :

  1. I handed down my judgment (Neutral Citation reference [2014] EWHC 2677 TCC) hereafter referred to herein as "the judgment") in this case on the 1st August 2014.
  2. In the judgment I found that the Defendant was obliged to carry out remedial works following a fire which had caused significant damage to premises leased by the Defendant to the Claimants and used by the Claimants for the purpose of their pizza restaurant.
  3. For the purposes of this judgment I do not need to repeat the facts as I found them in the judgment.
  4. A significant issue between the parties was whether I should order the Defendant to pay the Claimants damages to enable the Claimants to carry out the necessary works, or whether I should accept the undertaking proffered by the Defendant to carry out the works. I decided to accept the Defendant's undertaking.
  5. There were arguments between the parties as to the terms of the undertaking, but in the end an undertaking was given to the Court and embodied in my Order dated the 19th December 2014.
  6. The works have now been very largely completed, but there remain a number of issues in dispute between the parties. It is the contention of the Defendant that those issues have been settled. This judgment is concerned only with that contention: other arguments which have been raised by the Defendant are dealt with in a separate judgment to be handed down at the same time as this. I have kept the settlement issues separate in case one or other of the parties wishes to any judge dealing with this case hereafter unaware that settlement offers were made.
  7. For the reasons set out below, I find that there was no settlement.
  8. After the terms of the undertaking had been settled on the 19th December 2014, remedial works were carried out by contractors engaged by the Defendant. The works were supervised by Mr. Birchall, a surveyor retained by the Defendant. Mr. Moor, a surveyor retained by the Claimants, had a watching brief.
  9. The Court has been provided with regular reports as to the progress of the works.
  10. It is the Claimants' case that the Defendant has not carried out the works diligently. That suggestion is denied by the Defendant.
  11. On the 12th January 2016 the Claimants' solicitor wrote to the Court saying:
  12. "The reinstatement works were not completed by the Defendant on the 11 December 2015 as there are still outstanding reinstatement works left to be resolved to the Claimants' satisfaction that requires further engagement by the experts.
    ….
    The Claimants may wish to apply in due course to fix a date for the assessment of the quantum of their losses of their income/business profits during the relaunch period as per the Minute of the Order of October 2014 …."
  13. On the 25th January 2016 I directed that the parties should set out their respective submissions as to the directions that each party wanted the Court to give. Following an agreed extension of time, these were to be served on the 12th February 2016. On that day the Claimants served their submissions seeking sundry directions and orders.
  14. The Defendant submits that before those submissions were served there had been a settlement between the parties.
  15. The starting point for the Defendant's argument is a letter written by FS Law (the Claimants' solicitors) to Kidd Rapinet (the Defendant's solicitors) dated the 1st February 2016 and headed "Without Prejudice Save as to Costs".
  16. In that letter FS Law identified certain items of work which the Claimants contended were outstanding. The letter referred to the Court's Order of the 7th October 2014 and said:
  17. "As you are aware the Order of 7 October 2014 also expressly provided for a further consideration of our clients losses and an assessment of damages under a number of heads including:
    2. The assessment of quantum of damages (if any) under the following heads of claim is adjourned with liberty to the Claimants to apply to fix a date for the assessment
    2.1 The quantum of any residual reinstatement works to the premises
    2.2 The quantum of any residual reinstatement works to or supply of the kitchen equipment and customer serving and accommodation facilities.
    2.3 The quantum of any business re-launch expenses and loss of income during the re-launch period.
    ….
    As to the various heads of damages set out … above, in the spirit of compromise and to limit further costs and on the basis that your client undertakes all outstanding works referred to by 4.00 p.m. on 3 February 2016, our clients:
    (i) Will forgo its claims for the quantum of the residual reinstatement works to the premises (save for the works that may be required to deal with the further leak damage reported on the 27 January 2016) and
    (ii) Works to or supply of kitchen equipment and customer serving and accommodation facilities
    However, they do have a sustainable claim in respect of 2.3 above.

    The letter then set out a calculation of the amount due under 2.3 totalling £11,119.31 and continued:

    "Our clients are willing to settle the above matters on the following terms:
  18. On the following day, FS Law wrote another "Without Prejudice Save as to Costs" letter. After some explanation, the letter concluded:
  19. "For the avoidance of doubt, our clients' "Without Prejudice" offer of yesterday must be reviewed in the light of the matters set out herein. In particular, our clients revise their "Without Prejudice Offer" as set out in paragraph 12 as follows:
    (a) Loss of Income @ £214.45 per day (average rate claimed within our clients Amended Particulars of Claim) x 52 days = £11,151.40
    (b) Food wastages on the 15 January 2016 value £177.36
    (c) Lost wages @ £39.90 per hour for the 15 January 2016 = £219.45
    (d) South Eastern Electric costs for smart meter and re-energising power £ [to be advised]
    (e) Cost of Gastronome units £ [information with the experts]"
  20. In my view this letter amounted to a retraction of the offer contained in the first letter of the 1st February 2016.
  21. There are obvious difficulties with acceptance of this revised offer given the open nature of items (d) and (e).
  22. There followed a series of emails all on the 2nd February 2016:
  23. i) Kidd Rapinet to FS Law:

    "Thank you for your second letter of yesterday, 1 February 2016, and your first letter of today, 2 February 2016.
    We are taking instructions in relation to your without prejudice save as to costs proposals contained therein and we would therefore request an extension to the deadline for a response to 12 noon tomorrow."

    ii) FS Law to Kidd Rapinet:

    "We would be content to extend the deadline for your client's response to 12 noon tomorrow but on the basis that the time for the Claimants' Response to the Notice to Admit should be extended until the 12th February 2016."

    iii) Kidd Rapinet to FS Law:

    "We are instructed to agree to the terms of extension set out in your email sent at 15.48 today."
  24. On the 3rd February 2016 FS Law wrote as follows:
  25. "Further to our "Without Prejudice" letters of 1st and 2nd February 2016, our clients have drawn our immediate attention to a misstatement that was made that requires us to obtain their immediate further instructions.
    Under the circumstances we confirm that the "Without Prejudice Offers" made in our letters of the 1st and 2nd February 2016 are formally withdrawn until further notice.
    For the avoidance of doubt, they are not capable of acceptance by your client by 12 noon today."
  26. It is the Defendant's case that it was not open to the Claimants to withdraw the offers made in FS Law's previous letters because consideration was given in the email exchanges referred to above for keeping the offers open until 12 noon, that consideration being the Defendant's agreement to an extension of time for service of the Claimant's Response to the Notice to Admit.
  27. Because I have concluded for the reasons set out below that the Defendant did not accept those offers before the 12 noon deadline, I do not have to decide whether withdrawal of those offers was a course open to the Claimants.
  28. At 11.39 on the 3rd February 2016 Kidd Rapinet emailed a two page letter to FS Law which contained 10 numbered paragraphs:
  29. i) At paragraph 2 (iii) Kidd Rapinet referred to an email from Mr. Birchall to Mr. Moor which listed out various items of outstanding work. The letter contended that 10 of the listed items had been completed, that 3 items required no work, that three items would be completed by the end of the week, offered £1,500 in respect of another item and reserved the Defendant's rights in respect of one more item;

    ii) By paragraph 3 offered a draft Tomlin Order for "your early consideration and agreement";

    iii) By paragraph 5 agreed to pay at total of £6,492.59, being a total of £12,013.67 less a set off of £7,021.08;

    iv) By paragraph 6 agreed to pay the reasonable costs of the installation of a new smart meter and the reasonable costs of re-energising the power at the premises;

    v) By paragraph 10 said that "if the terms of the draft Tomlin Order are agreed, our client is content to forego pressing for a substantive response to its Notice to Admit Facts dated 20 January 2016."

  30. It is the Defendant's contention that this amounted to an acceptance of the Claimants' settlement offer.
  31. I reject this contention for the following reasons:
  32. i) In my view the terms of Kidd Rapinet's letter amounted to a counter-offer rather than an acceptance of FS Law's offer, particularly in respect of the items of work which were outstanding;

    ii) Whilst paragraph 6 addressed item (d) of FS Law's 2nd February letter in terms which could be construed as an agreement, item (e) does not seem to me to have been addressed;

    iii) I construe the letter as offering terms of agreement which would be embodied and finally agreed in a Tomlin Order, the terms of which were yet to be finalised.

  33. I will invite submissions from the parties as to what, if any, order should be made to give effect to this judgment.


BAILII: Copyright Policy | Disclaimers | Privacy Policy | Feedback | Donate to BAILII
URL: http://www.bailii.org/ew/cases/EWHC/TCC/2016/2032.html