![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Baldwin & Anor v Pickstock Ltd [2017] EWHC 2456 (TCC) (05 October 2017) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2017/2456.html Cite as: [2017] EWHC 2456 (TCC) |
[New search] [Printable RTF version] [Help]
QUEEN'S BENCH DIVISION
BIRMINGHAM DISTRICT REGISTRY
TECHNOLOGY AND CONSTRUCTION COURT
B e f o r e :
sitting as a Judge of the High Court
____________________
(1) FREDERICK DENNIS BALDWIN | ||
(2) SOMA CONTRACT SERVICES LIMITED | Claimants | |
and | ||
J R PICKSTOCK LTD | Defendant |
____________________
Mr Paul Clarke, instructed by Clarke Willmott LLP, appeared for the Defendant
Trial date 20 September 2017
____________________
Crown Copyright ©
HHJ SIMON BARKER QC :
The parties and the issues
The terms of the parties' agreement
"Should I resign as Adjudicator prior to reaching my Decision due to what I consider is a valid challenge to my jurisdiction to decide the dispute referred to me, then the Referring Party will be liable for payment of my fees and expenses".
D is the Referring Party.
"9 (1) An adjudicator may resign at any time on giving notice to the parties to the dispute.
(2) An adjudicator must resign where the dispute is the same or substantially the same as one which has previously been referred to adjudication, and a decision has been taken in that adjudication.
(3) Where an adjudicator ceases to act under paragraph 9(1)-
(a) the referring party may serve a fresh notice under paragraph 1 ".
The critical phrase in issue for the purpose of ascertaining the meaning and scope of the parties' agreement is "at any time".
"11 (1) The parties to a dispute may at any time agree to revoke the appointment of the adjudicator. ".
"13 The adjudicator may take the initiative in ascertaining the facts and the law necessary to determine the dispute, and shall decide on the procedure to be followed in the adjudication. In particular he may-
(f) obtain and consider such representations and submissions as he requires, and, provided he has notified the parties of his intention, appoint experts, assessors or legal advisers,
(g) give directions as to the timetable for the adjudication, any deadlines, or limits as to the length of written documents or oral representations to be complied with, and
(h) issue other directions relating to the conduct of the adjudication".
"14 The parties shall comply with any request or direction of the adjudicator relation to the adjudication".
"17 The adjudicator shall consider any relevant information submitted to him by any of the parties to the dispute and shall make available to them any information to be taken into account in reaching his decision".
"19 (1) The adjudicator shall reach his decision not later than-
(a) twenty eight days after receipt of the referral notice , or
(b) forty two days after receipt of the referral notice if the referring party so consents, or
(c) such period exceeding twenty eight days after receipt of the referral notice as the parties to the dispute may, after the giving of that notice, agree.
(2) Where the adjudicator fails, for any reason, to reach his decision in accordance with paragraph (1)
(a) any of the parties to the dispute may serve a fresh notice under paragraph 1 and shall request the adjudicator to act in accordance with paragraphs 2 and 7;
(3) As soon as possible after he has reached a decision, the adjudicator shall deliver a copy of that decision to each of the parties to the contract".
The parties are at odds on whether paragraph 19 affects or limits the proper construction of the phrase "at any time" in paragraph 9.
In addition, the following paragraph, referred to in the Scheme under the heading Adjudicator's decision, is also relevant :
"22A (1) The adjudicator may on his own initiative or on the application of a party correct his decision so as to remove a clerical or typographical error arising by accident or omission.
(2) Any correction of a decision must be made within five days of the delivery of the decision to the parties.
(3) As soon as possible after correcting a decision in accordance with this paragraph, the adjudicator must deliver a copy of the corrected decision to each of the parties to the contract.
(4) Any correction of a decision forms part of the decision".
The imperative to deliver a decision or corrected decision "as soon as possible" is enforced strictly, see Lorraine Lee v Chartered Properties (Building) Limited [2010] EWHC 1540 (TCC), and delivery should ordinarily be understood to be required forthwith absent good cause and explanation.
Cs' claim in contract
"When interpreting a written contract, the court is concerned to identify the intention of the parties by reference to "what a reasonable person having all the background knowledge which would have been available to the parties would have understood them to be using the language of the contract to mean", to quote Lord Hoffmann in Chartbrook Ltd v Persimmon Homes Ltd [2009] UKHL 39 . And it does so by focussing on the meaning of the relevant words in their documentary, factual and commercial context. The meaning has to be assessed in the light of (i) the natural and ordinary meaning of the clause, (ii) any other relevant provisions of the [contract], (iii) the overall purpose of the clause and the contract, (iv) the facts and circumstances known or assumed by the parties at the time that the document was executed, and (v) commercial common sense, but (vi) disregarding subjective evidence of the party's intentions".
Decision as to proper meaning and scope of "at any time" in paragraph 9
Cs' further contentions
"15 When the adjudicator asks for more time in circumstances like this[2], I consider that there is a clear obligation on the part of both parties to the adjudication to respond plainly and promptly to the request. If in breach of that obligation, one party does not respond at all, there must be a very strong case for saying that they accepted, by their silence, the need for the required extension. The adjudicator can do no more than work out that he needs a short extension, and seek agreement from the parties to such an extension. Common sense, as well as common courtesy, requires a prompt response. If one party does not respond at all to the adjudicator's request, it seems to me that party runs a very clear risk that his silence will be taken to amount to acquiescence to the required extension.
18 assume that Speedwell did not agree to the two-day extension sought by the adjudicator. In those circumstances, I consider that Speedwell's silence in response to the request for an extension, and their conduct summarised in paragraphs 11 and 16 above[3], means that, at the very least, Speedwell are estopped from denying that the adjudicator's decision of 4th April was a valid decision and/or was reached in time. Both by their failure to say in terms that they did not agree to the extension that had been requested, and their participation in the exchange of information all the way through to the latter part of 3rd April they represented that the adjudicator had until 5th April to reach his decision. If they had made their position clear (which, on this assumption, was to the effect that they did not agree to any such extension), then both Yule and the adjudicator would plainly have acted differently so as to avoid the suggestion that the decision was out of time".
" In the light of the clear warning in Yule that parties are under an obligation to make their objections plain and that silence may be taken as acquiescence this is, in my view, a clear case where it was not open to GD City to do nothing until 1 March 2013[4] and then to attempt to spring a procedural trap without any prior warning".
The facts
"After that I want no further uninvited submissions & I will require 3 working weeks thereafter within which to reach my Decision i.e. until Tuesday 7th June (allowing for the 30th May Bank Holiday), as previously advised in my 11th April email timed at 14.58".
This constituted a request by C1 for agreement to extensions of time totalling in excess of 10 weeks beyond the 28 day period under paragraph 19(1)(a) of the Scheme.
"We refer to our previous emails regarding the timetable for your decision and note that our client was anticipating receiving it by Friday 27 May 2016.
Unfortunately, neither we nor our client has any record of having received your decision by that date. Further, assuming a hard copy might have been sent by post over the bank holiday weekend we waited until today to raise this issue. No decision has been received today (31 May).
Can you please kindly confirm what the position is?"
Mr Craik had been a named recipient of C1's 13.5.16 email, as had been a trainee or assistant solicitor under Mr Craik's supervision.
" the position concerning the date my Decision is due is that I have been proceeding as per my 13th [M]ay email below as I do not recall having received any objection to the Decision date of 7th June stated therein".
Also on that day C1 sought apparently missing documents from D and M Ltd.
" so that we all know where we stand on this issue, & so as to avoid any possible abortive work &/or wasted expenditure, I require ASAP [D's] clear & unequivocal confirmation of their agreement to me now having until 7th June to reach my Decision".
" the fact remains that in principle that constitutes a valid challenge to my jurisdiction by [D] which now leaves me with no alternative other than to hereby formally resign as Adjudicator as expressly provided for at para 3.2 of my 1st March 2016 Terms and Conditions".
In consequence C2 sent an invoice for the sum claimed to D.
Decision
Note 1 References to M Ltd also include M Ltds solicitor acting in the adjudication. [Back] Note 2 Late on in the 28 day period or extended time, new information is provided by party and in order to do the job properly the adjudicator wants to afford the parties an opportunity to comment and may need to ask for a couple of extra days to take the comments into account. [Back] Note 3 Email communications between the adjudicator and the parties and delay in responding to the adjudicators request and failure by Speedwell, when responding on 3rd April and providing 65 pages of invoices, to state that they regarded that as the last date for reaching a decision. [Back] Note 4 The day after the 28 day deadline for reaching a decision, absent an agreed extension. [Back]