[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Babcock Marine (Clyde) Ltd v HS Barrier Coatings Ltd [2019] EWHC 1659 (TCC) (28 June 2019) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2019/1659.html Cite as: [2019] BLR 495, [2019] EWHC 1659 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS & PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
BABCOCK MARINE (CLYDE) LIMITED |
Claimant |
|
- and - |
||
HS BARRIER COATINGS LIMITED |
Defendant |
____________________
Ms Jennifer Jones (instructed by Hill Dickinson LLP) for the Defendant
Hearing dates: 18th June 2019
____________________
Crown Copyright ©
Mrs Justice O'Farrell:
i) the defendant's application for relief from sanctions and an extension of time for service of its Part 11 application contesting the jurisdiction of the court;
ii) the defendant's application for the claim form to be set aside or for proceedings to be stayed pursuant to CPR 11(6) on the ground that the Courts of England and Wales do not have, or should not exercise, jurisdiction to determine the dispute;
iii) the claimant's application for further directions, if appropriate, in the adjudication enforcement proceedings.
The Contract
"A dispute arising under or in connection with this contract is notified to the Employer's and Contractor's commercial management organisations who shall use all reasonable endeavours to resolve through negotiation. If the dispute is not resolved within three days the matter shall be escalated to commercial senior management who shall have 3 days to resolve. If the dispute is not resolved the matter shall be escalated to commercial directors, who shall have 3 days to resolve. If resolution fails, the dispute shall be decided by the Adjudicator in accordance with clauses 93.2, 93.3, 93.4 (and 94.1 if specified in the Contract Data)."
"The Adjudicator is to be agreed by both parties or upon failure to be appointed by the chairman of the institute of arbitrators ...
The Adjudicator nominating body is The Chartered Institute of Arbitrators (Scottish Branch)."
"The Parties appoint the adjudicator under the NEC Adjudicator's Contract current at the starting date. The adjudicator acts impartially and decides the dispute as an independent adjudicator and not as an arbitrator."
"The Adjudicator's decision is binding on the Parties unless and until revised by the tribunal and is enforceable as a matter of contractual obligation between the Parties and not as an arbitral award. The adjudicator's decision is final and binding if neither Party has notified the other within the times required by this contract that he intends to refer the matter to the tribunal."
"A Party may refer a dispute to the tribunal if
- the party is dissatisfied with the Adjudicator's decision
- the Adjudicator did not notify a decision within the time allowed and a new adjudicator has not been chosen,
except that neither Party may refer a dispute to the tribunal unless they have notified the other Party of their intention to do so not more than four weeks after the end of the time allowed for the Adjudicator's decision."
"The tribunal is Arbitration.
If the tribunal is arbitration, the arbitration procedure is in accordance with the Scottish Arbitration Code, prepared by the Scottish Council for International Arbitration, The Chartered Institute of Arbitrators (Scottish Branch)."
"12.1 This contract is governed by the law and statutes of the country where the site is.
12.2 No change to this contract, unless provided for by the conditions of contract, has effect unless it has been agreed, confirmed in writing and signed by the Parties.
12.3 This contract is the entire agreement between the Parties.…"
"In the event of any discrepancy in the contract the documentation shall take precedence in descending order as listed:
(a) Additional conditions
(b) Conditions of contract, NEC 3 Engineering and Construction Short Contract (June 2005)
(c) Contract Data
(d) Employer's Invitation to Tender
(e) Contractor's Tender Submission
(f) Any other documents forming part of the contract."
The Variation Agreement
"This revised value, less the provisional sum, relates to the following:
"1) Full and final settlement of any claims relating to this contract in [its] present form with the sole exclusion of the extra over cost of treating the 6no. large Strongbacks. For the avoidance of doubt, claims for additional costs can only be made for events which may occur in the future, in accordance with the provisions of the NEC Short Contract dated 1st December 2014 which may lead to a Compensation Event."
…
5) Confirmation of agreement to the original Contract dated 1 December 2014 and full acceptance of the terms and conditions contained therein.
…
Application for payment shall be submitted by the 15th of each month…"
"This agreement shall be governed by and construed in accordance with the Laws of Scotland and any dispute which may arise between the parties concerning this agreement shall be determined by the Courts of Scotland in line with the original Contract dated 1 December 2014."
The dispute
The proceedings
Relief from sanctions
Legislative framework
"Subject to the rules of this Schedule, persons domiciled in a part of the United Kingdom shall be sued in the courts of that part."
"Persons domiciled in a part of the United Kingdom may be sued in the courts of another part of the United Kingdom only by virtue of rules 3 to 13 of this Schedule."
"A person domiciled in a part of the United Kingdom may, in another part of the United Kingdom, be sued –
(a) in matters relating to a contract, in the courts for the place of performance of the obligation in question…"
"If the parties have agreed that a court or the courts of a part of the United Kingdom are to have jurisdiction to settle any disputes which have arisen or which may arise in connection with a particular legal relationship, and, apart from this Schedule, the agreement would be effective to confer jurisdiction under the law of that part, that court or those courts shall have jurisdiction."
"Nothing in this act shall prevent any court in the United Kingdom from staying, sisting, striking out or dismissing any proceedings before it, on the grounds of forum non conveniens or otherwise, where to do so is not inconsistent with the 1968 Convention or, as the case may be, the Lugano Convention or the 2005 Hague Convention."
Summary of the parties' positions
i) the Variation Agreement incorporated a choice of court clause into the Contract, namely, the Scottish courts, and that choice of jurisdiction should be respected in accordance with rule 12(1) of Schedule 4;
ii) alternatively, the place of performance, whether performance of the underlying contractual obligations or payment of the adjudication award, was Scotland, giving the Scottish courts special jurisdiction in accordance with rule 3(a) of Schedule 4;
iii) alternatively, this court should stay the current proceedings on the ground that the Scottish courts are the most appropriate forum for resolution of this matter.
i) the choice of court clause in the Variation Agreement conflicts with the arbitration agreement in the Contract, which has priority; in any event the choice of court clause is limited to disputes under the Variation Agreement and does not apply to adjudication enforcement;
ii) Rules 12 and 3 of Schedule 4 do not displace Rule 1 and the Court should not interfere with Babcock's choice to sue HSBC in its place of domicile;
iii) the Court's discretion should be exercised in favour of Babcock and no stay should be imposed.
Jurisdiction clause
i) "this agreement shall be governed by and construed in accordance with the Laws of Scotland"
ii) "any dispute which may arise between the parties concerning this agreement"
iii) "shall be determined by the Courts of Scotland"
iv) "in line with the original Contract dated 1 December 2014."
Entitlement to adjudication enforcement
"…a party such as the claimant, who has a decision in its favour from an adjudicator, is in a much better position than most to argue that the court should exercise its discretion to continue to an enforcement hearing."
"I accept [Comsite's] submission that, even if the Austrian court did have exclusive jurisdiction, that would not prevent the English court from exercising jurisdiction to enforce the decisions of an adjudicator, or to decide matters relating to the enforcement of such a decision, such decisions being of a temporary nature… Ultimately, a dispute may be determined by arbitration, but that does not prevent enforcement of the temporary decision of an adjudicator … whilst ultimately the Austrian court may be the appropriate forum in which the substantive dispute or disputes between Comsite and AAG should be settled (to adopt the wording of article 23) that does not prevent the English court enforcing the temporary decision of an adjudicator properly made in relation to the Building Services sub-contract. The agreement that the Austrian court have jurisdiction is not undermined or ignored by the conclusion that the interim decision of an adjudicator can be enforced by an English court. Enforcement of such a decision is without prejudice to the final merits and determination by the Austrian court. The agreement that the Austrian court have jurisdiction does not prevent the court considering this part 8 application by Comsite…"
"[13] … In Ballast Plc v Burrell Co (Construction Management) Ltd [2001] SLT 1039. Lord Reed noted:
"It appears from the cases cited to me that different views have been taken as to the appropriate legal framework within which to address the issues raised by adjudicators' decisions: in particular whether the adjudicator is to be regarded as a decision-maker, albeit one whose statutory powers and duties have been clothed in contractual form (the approach adopted by Lord Macfadyen in Homer Burgess Ltd v Chirex (Annan) Ltd, as I understand his opinion), or whether adjudication should be regarded as a contractual procedure (as Dyson J appears to have regarded it in, for example, Macob Civil Engineering Ltd v Morrison Construction Ltd [1999] BLR 93)."
Lord Reed decided to approach the issues raised by adjudication within a contractual framework; noted that his contractual approach differed to that adopted by Lord Macfadyen in Homer Burgess; and thus did not treat the adjudicator as a "statutory decision maker". At paragraph 29 Lord Reed explained that the adjudication process flowed from the parties' contract and was subject to the express and implied terms of the contract:
"Each party to the contract is therefore to be regarded as having a contractual right to refer a dispute to adjudication; and each party equally has a contractual duty to comply with the adjudicator's decision. These rights and duties only exist, however, within limits which are set by the terms of the contract. The right to refer a dispute, for example, is confined to disputes arising under the contract: paragraph 1(1) of the Scheme. Since adjudication has a contractual basis, the construction and effect of paragraph 23(2), and in particular words – 'The decision of the adjudicator shall be binding on the parties, and they shall comply with it' – depends on the construction of the express and implied terms of the contract."
…
[77] …Both companies are domiciled in Scotland and the effect of the clause is that both companies will have to raise court actions in England (as the defender has presently done). Thus the effect of the clause is equal on both parties. It was argued that in the circumstances of the present case the pursuer is the party who has been successful at the adjudication and it will now have to raise an action in England. However, I do not see how this imposes any extra obligations on the pursuer. An action to enforce the decision of the adjudicator can be raised as easily in England as in Scotland. It was argued by Mr Massaro that the unfairness of this in the circumstances of enforcement of an adjudication decision was illustrated by a scenario where the country to which jurisdiction had been prorogated did not have a knowledge of the 1996 Act and did not appreciate its nature. This does not assist the pursuer's argument. The English court has a full understanding of adjudication.
[78] The final argument advanced by the pursuer in support of its construction was based on this: adjudication is a sui generis system of dispute resolution created by section 108 of the 1996 Act. It is thus statutorily based and is conceived in the benefit of contractors such as the pursuer. Thus it is not covered by the clause.
[79] The above argument is I believe misconceived. The right to go to adjudication is a contractual right in terms of clause 8. In my judgement it cannot be looked upon as being independent and separate from the contract from which it arises. It is not a standalone right. I accept the analysis of the structure of adjudication as set out by Lord Reed in Ballast plc v Burrell Co."
Schedule 4 to the 1982 Act
Forum non conveniens
"In my opinion, having regard to the authorities (including in particular the Scottish authorities), the law can at present be summarised as follows.
(a) The basic principle is that a stay will only be granted on the ground of forum non conveniens where the court is satisfied that there is some other available forum, having competent jurisdiction, which is the appropriate forum for the trial of the action, i.e. in which the case may be tried more suitably for the interests of all the parties and the ends of justice.
(b) … in general the burden of proof rests on the defendant to persuade the court to exercise its discretion to grant a stay…
(c) The question being whether there is some other forum which is the appropriate forum for the trial of the action, it is pertinent to ask whether the fact that the plaintiff has, ex hypothesi, founded jurisdiction as of right in accordance with the law of this country, of itself gives the plaintiff an advantage in the sense that the English court will not lightly disturb jurisdiction so established … In my opinion, the burden resting on the defendant is not just to show that England is not the natural or appropriate forum for the trial, but to establish that there is another available forum which is clearly or distinctly more appropriate than the English forum…
(d) Since the question is whether there exists some other forum which is clearly more appropriate for the trial of the action, the court will look first to see what factors there are which point in the direction of another forum… to adopt the expression used by my noble and learned friend, Lord Keith of Kinkel, in The Abidin Daver [1984] A.C. 398, 415, when he referred to the "natural forum" as being "that with which the action had the most real and substantial connection." So it is for connecting factors in this sense that the court must first look; and these will include not only factors affecting convenience or expense (such as availability of witnesses), but also other factors such as the law governing the relevant transaction (as to which see Crédit Chimique v. James Scott Engineering Group Ltd., 1982 S.L.T. 131), and the places where the parties respectively reside or carry on business.
(e) If the court concludes at that stage that there is no other available forum which is clearly more appropriate for the trial of the action, it will ordinarily refuse a stay ...
(f) If however the court concludes at that stage that there is some other available forum which prima facie is clearly more appropriate for the trial of the action, it will ordinarily grant a stay unless there are circumstances by reason of which justice requires that a stay should nevertheless not be granted. In this enquiry, the court will consider all the circumstances of the case, including circumstances which go beyond those taken into account when considering connecting factors with other jurisdictions… "