![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Network Rail Infrastructure Ltd v ABC Electrification Ltd [2019] EWHC 1769 (TCC) (08 July 2019) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2019/1769.html Cite as: [2019] TCLR 7, [2019] EWHC 1769 (TCC), [2019] BLR 522, 185 Con LR 1 |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (QBD)
Fetter Lane London, EC4A 1NL |
||
B e f o r e :
sitting as a Deputy Judge of the High Court
____________________
NETWORK RAIL INFRASTRUCTURE LIMITED | Claimant | |
and | ||
ABC ELECTRIFICATION LIMITED | Defendant |
____________________
Mr David Sears QC (instructed by Trowers & Hamlins LLP) for the Defendant
Hearing date: 26 June 2019
____________________
Crown Copyright ©
Miss Joanna Smith QC:
Introduction
2.1 By a contract dated 20 December 2012 ("the Original Agreement"), Network Rail engaged Costain to carry out works for Phase 3B of the West Coast Power Supply Upgrade Project Phase 3 ("the WCPSU"). Phase 3B involved a section of the West Coast Main Line ("the Line") running between Whitmore in Staffordshire and Great Strickland in Cumbria.
2.2 The Original Agreement incorporated the terms of the ICE Conditions of Contract, Target Cost version, First Edition ("the ICE Conditions") subject to a schedule of standard amendments used by Network Rail known as NR12 ("the NR12 Amendments").
2.3 By a Deed of Novation dated 31 March 2014, the Original Contract was novated from Costain to ABC. Thereafter, by a Deed of Variation executed by ABC on 22 September 2014 and by Network Rail on 19 January 2015 ("the DOV"), the works to be carried out by ABC were varied so as to include works within Phase 3A of the WCPSU, involving a section of the Line running between North Wembley in Greater London and Whitmore.
The Dispute
"any cost due to negligence or default on the part of the Contractor in his compliance with any of his obligations under the Contract and/or due to any negligence or default on the part of the Contractor's employees, agents, sub-contractors or suppliers in their compliance with any of their respective obligations under their contracts with the Contractor".
The words in bold were inserted into the ICE Conditions pursuant to the NR12 Amendments.
The Exercise of the Discretion to Grant Declaratory Relief
The Law on Interpretation
Network Rail's Case
(1) the defined term 'Disallowed Cost' in the Contract includes any cost due to a failure by ABC to comply with its obligations under the Contract;
(2) a cost incurred due to a failure by ABC to comply with the terms of the Contract, including the following, is a Disallowed Cost:
(a) any failure by ABC to start the Works on or as soon as reasonably practicable after the Works Commencement Date and/or thereafter to proceed with the works with due expedition, contrary to clause 41(2);
(b) any failure by ABC to substantially complete the works within the stated time for completion (or such extended time as may be allowed under clause 44 or revised time agreed under clause 46(3)) calculated from the Works Commencement Date, contrary to clause 43.
ABC's Case
"The term 'Disallowed Cost' in the Contract includes any cost incurred due to default on the part of the Contractor if, and only insofar as, the default constitutes a wilful and deliberate failure to comply with his obligations under the Contract" (emphasis added).
As I understood his submissions, Mr Sears now abandons any suggestion that the words "serious", "significant and material" and "persistent" should be included, although he does appear to maintain that a wilful and deliberate failure will inevitably be significant.
The True Interpretation of Clause 1(1)(j)(iii)
The Meaning of the Language Used
30.1 Clause 65 is a termination provision headed 'Default of Contractor'. Although Mr Sears does not rely on sub-clauses (1)(a)-(d), dealing with assignment by the Contractor without written consent, sub-contracting of the Works in breach of clause 3(3) and bankruptcy/administration (which he acknowledges are "probably not helpful when trying to understand what will constitute a 'default'"), he draws my attention to sub-clauses (1)(e)-(i) as follows:
"… if the Employer's Representative certifies in writing to the Employer with a copy to the Contractor that in his opinion the Contractor
(e) has abandoned the Contract without due cause or
(f) without reasonable excuse has failed to commence the Works in accordance with Clause 41 or
(g) has suspended the progress of the Works without due cause for 14 days after receiving from the Employer's Representative written notice to proceed or
(h) has failed to remove goods or materials from the Site or to pull down and replace work for 14 days after receiving from the Employer's Representative written notice that the said goods materials or work has been condemned and rejected by the Employer's Representative or
(i) despite previous warnings by the Employer's Representative in writing is failing to proceed with the Works with due diligence or is otherwise persistently or fundamentally in breach of his obligations under the Contract,
then the Employer after giving 7 days notice in writing to the Contractor specifying the event relied on may enter on the Works and any other parts of the Site provided by the Employer and expel the Contractor therefrom without thereby avoiding the Contract or releasing the Contractor from any of his obligations under the Contract."
30.2 Mr Sears contends that these sub-clauses are plainly concerned with breaches or 'defaults' of the Contractor arising in circumstances where it is acting, in his words, "without reasonable excuse or in contravention of an instruction" given by the Employer's Representative. He submits that each of these 'defaults' therefore constitutes a wilful and deliberate (in his skeleton he added, 'serious significant and material') failure to comply with the requirements of the Contract and that the insertion of the word 'default' by amendment into clause 1(1)(j)(iii) must have been intended to capture defaults of a similar type. He submits that it is only defaults of the type envisaged in clause 65 that the parties are to be taken to have had in contemplation when agreeing to the NR12 Amendment to clause 1(1)(j)(iii).
30.3 In my judgment there are a number of significant difficulties with this argument.
30.4 First, there is no basis in the Contract for the suggestion that the parties intended the word 'default' as it appears in clause 1(1)(j)(iii) to find its true meaning in the provisions of clause 65. The word 'default' is not used anywhere in the text of clause 65 itself.
30.5 Second, the word 'default' appears only in the heading to clause 65. In circumstances where clause 1(3) of the Contract expressly provides that "The headings and marginal notes in the Conditions of Contract shall not be deemed to be part thereof or be taken into consideration in the interpretation or construction thereof or of the Contract", I reject the suggestion that I can look at this clause for a "clue" to what the parties intended by the amendment to clause 1(1)(j)(iii).
30.6 In post-hearing notes dealing with the effect of a term which states that headings are not to affect the interpretation of a contract, the parties have drawn my attention to a number of authorities. Mr Sears submits that these authorities are "not to the point" because in fact he relies on the language of clause 65 itself (and not on the heading) as an indicator of the kind of 'default' which the parties had in mind when agreeing the amendment to clause 1(1)(j)(iii). However, at the same time he goes on to contend that his approach is consistent with the approach taken by the court in SBJ Stephenson v Mandy [2000] FSR 286 and Doughty Hanson & Co v Roe [2007] EWHC 2212 (both cases in which the court had to construe a term to the effect that clause headings were "for convenience only and shall not affect construction"). In the latter case, Mann J expressed the view at [71] that "the heading is descriptive of what the provision is about (that is doubtless the convenience – see SBJ Stephenson v Mandy…)". Mr Sears says that, taking this approach, ABC relies on the heading to clause 65 "as a signpost, for convenience, to inform the reader what the clause is about, namely the 'default' of the contractor".
30.7 I reject Mr Sears' submission that I should adopt the approach taken in these two cases. Clause 1(3) of the Contract is in different terms and makes no reference to the headings being "for convenience". Further, I agree with Mr Stansfield that I should prefer the later first instance decision in Gregory Projects (Halifax) Ltd v Tenpin (Halifax) Ltd [2009] EWHC 2639 (on the basis that it appears to have been reached after consideration of the earlier decisions in SBJ Stephenson and Doughty Hanson – see Colchester Estates v Carlton Industries [1986] 1 Ch 80, per Nourse J at 85) and that I am bound by the decision of the Court of Appeal in Rathbone Brothers Plc v Novae Corporate Underwriting [2014] EWCA 1464. In Gregory Projects, Lewison J identified that the cases (including those on which Mr Sears relies) were divided on whether a heading should be taken into account, but concluded at [28] "Where, as here, the contract says in terms that headings "shall not affect the interpretation" it seems to me that respect for party autonomy means that the headings cannot be allowed to alter what would otherwise have been the interpretation of the clause in question". In Rathbone Brothers, the Court of Appeal upheld the decision of Burton J that reference to a heading for the purposes of construction was not permitted, saying that "the heading cannot be used to cut back on the clear language used in the clause".
30.8 Whilst Mr Sears is right that these decisions were both specifically concerned with the question of whether a heading can be used to interpret the clause to which it is attached, nonetheless I can see no sensible basis for the proposition that a heading to one clause in a contract may be used, however obliquely, as a guide to the construction of an entirely different clause, where the parties have agreed (as they have in this Contract) that headings are not to be taken into account in the interpretation or construction of the Contract. Further and in any event, it seems to me that ABC is in reality seeking to use the heading of clause 65 to suggest that when the parties refer in the Contract to a 'default' they were intending to refer to the types of default identified in clause 65 itself, a proposition which does seem to me to involve construing the provisions of clause 65, an approach which cannot be countenanced in light of the authorities to which I have just referred.
30.9 It is difficult to see how Mr Sears could begin to make out his case as to the relevance of clause 65 and, in particular, as to the fact that the kinds of 'default' identified therein must have been the only kinds of default contemplated by the parties when agreeing to the NR12 Amendment, if the heading to clause 65 is ignored, as the parties have agreed it should be.
30.10 Third, and in any event, there is no common-sense reason for thinking that the concept of default in clause 1(1)(j)(iii) was intended to be the same as the concept of default insofar as that concept is used in clause 65 (whether regard is had to the heading of clause 65 or not). Indeed, it is not at all clear why the ability to deduct Disallowed Cost should be in any way equivalent to the right to terminate the Contract. Whilst it is hardly surprising that breaches of Contract giving rise to the entitlement to terminate are (at least) serious breaches, it does not to my mind follow that breaches of a similar type are the only breaches which entitle the deduction of Disallowed Cost, the consequences of which are likely to be much less serious. Common sense suggests a broader and less stringent test; a test which is more in line with the natural and ordinary meaning of the word 'default'.
30.11 Fourth, I agree with Mr Stansfield that the suggestion by ABC that a failure to act without reasonable excuse or in contravention of an instruction is the same for these purposes as a 'wilful and deliberate' failure (so as to justify the conclusion that the word default in clause 1(1)(j)(iii) means only 'wilful and deliberate' default) is extremely surprising. Seen in the context of delay, a reasonable excuse will give rise to an extension of time and, absent a reasonable excuse, there will be a default. But that default need not be 'wilful and deliberate' on the ordinary meaning of those words (see De Beers UK Limited v ATOS Origin IT Services UK Limited [2010] EWHC 3276 (TCC) per Edwards-Stuart J at [206]). Furthermore, it is entirely unclear how it is said that the contravention of an instruction fits with a scenario in which the Contract is in delay or indeed what the relevance of an instruction might be in circumstances where the Contract must be completed by a particular date. ABC's own reading of clause 65 does not begin to support the construction of the word 'default' for which it contends in clause 1(1)(j)(iii).
31.1 Clause 39 is concerned with the power of the Employer's Representative to instruct the removal and replacement of unsatisfactory work and materials not in accordance with the Contract. Clause 39(2) provides that:
"In case of default on the part of the Contractor in carrying out such instruction the Employer shall be entitled to employ and pay other persons to carry out the same and all costs consequent thereon or incidental thereto as determined by the Employers' Representative shall be recoverable from the Contractor by the Employer and may be deducted by the Employer from any monies due or to become due to him and the Employer's Representative shall notify the Contractor accordingly with a copy to the Employer".
31.2 If Mr Sears is right in his construction, then this provision would only permit the Employer to employ and pay another contractor to remove and replace unsatisfactory work and materials where ABC had wilfully and deliberately failed to comply with an Instruction. Aside from the potential for disputes over whether any failure on the part of ABC has in fact been wilful and deliberate, the clause would not operate in circumstances where ABC (for whatever reason) forgot to comply or indeed where it took steps to comply but did so incompetently. In my judgment a lacuna of this sort cannot sensibly have been what the parties intended. The more natural interpretation of this provision, consistent with the natural and ordinary meaning of the word 'default' is that, whatever the circumstances giving rise to a failure to carry out the instruction, the Employer is entitled to employ a third party to complete the works and to recover the costs of so doing from ABC.
The Clause in its Contractual Context
34.1 ABC contends that if default in clause 1(1)(j)(iii) covers any failure to fulfil an obligation under the Contract, as Network Rail contends, then clauses 1(1)(j)(i) and 1(1)(j)(ii) of the Contract (which also form part of the definition of Disallowed Cost) would be rendered otiose. These clauses provide that Disallowed Cost includes:
"(i) the cost of work of repair amendment reconstruction and rectification or making good defects where such work is carried out to parts of the Works supplied or carried out by sub-contractors and is required under the term of the sub-contract to be at the sub-contractor's expense
(ii) the cost of repair amendment reconstruction rectification and making good defects after the date of substantial completion which in the opinion of the Employer's Representative is necessary solely due to the use of materials or workmanship not in accordance with the Contract"
34.2 In addition, Mr Sears points out that these clauses make very specific provision for the detailed circumstances in which non-compliance with contractual obligations will give rise to Disallowed Cost. In relation to clause 1(1)(j)(i), only where the cost of such work is required under the term of the sub-contract to be at the sub-contractor's expense, and in the case of clause 1(1)(j)(ii), which is mirrored in clause 49(3), only where costs are incurred after the date of substantial completion. Accordingly, he says, the parties cannot have intended the words in clause 1(1)(j)(iii) to cover any cost due to any failure on the part of the Contractor to comply with its obligations under the Contract: first because such a reading would render other provisions of the Contract redundant and second because the parties were plainly concerned to identify detailed circumstances which would give rise to Disallowed Cost.
34.3 Mr Sears relies in particular on the following extract from the speech of Lord Neuberger in Arnold v Britton at [17]: "Unlike commercial common sense and the surrounding circumstances, the parties have control over the language they use in the contract. And again, save in a very unusual case, the parties must have been specifically focussing on the issue covered by the provision when agreeing the wording of that provision". As I understand it, Mr Sears says that the court should not look at the provisions of clause 1(1)(j)(iii) alone, but in conjunction with the other provisions of clause 1(1)(j) on which the parties must have focussed at the time of agreeing the NR12 Amendments. He points out that clause 1(1)(j)(iii) appears in close proximity to clauses 1(1)(j)(i) and 1(1)(j)(ii) which, on Network Rail's interpretation, it rendered otiose. Mr Sears submits that because clauses 1(1)(j)(i) and 1(1)(j)(ii) were not deleted, the parties must be taken to have intended the word 'default' in clause 1(1)(j)(iii) to have a restricted meaning.
34.4 As to redundancy, I accept Mr Stansfield's submission that sub-clauses 1(1)(j)(i) and 1(1)(j)(ii) are part of the ICE Conditions, whereas the word 'default' has been added to clause 1(1)(j)(iii) by the NR12 Amendments. There is always potential for an amendment by way of an addition to a contract to render another part of it redundant and that may just be the inevitable consequence of the amendment. It is in my judgment unsurprising that an amendment agreed in the NR12 Amendments may have rendered certain terms of the ICE Conditions unnecessary or superfluous. Furthermore, I accept that the court must be cautious in interpreting an amendment by reference to pre-existing parts of a standard form contract, which may not be a helpful indicator as to the parties' intentions in agreeing upon the amendment.
34.5 Indeed it would appear that the parties were not overly concerned at the prospect of duplication in this Contract in any event, as is clear from the fact that Disallowed Cost under clause 49(3)[1] will fall within the definition of Disallowed Cost in both clause 1(1)(j)(vi) ("any such cost identified in the Contract as a Disallowed Cost or as part of the Fee or which does not form part of the Total Cost") and clause 1(1)(j)(ii).
34.6 I also accept Mr Stansfield's submission that the mere fact that a natural interpretation of a contract term could render another term redundant is an insufficient basis for the adoption of an unnatural construction, especially where a standard form is involved (See Beaufort Developments v Gilbert Ash [1999] 1 AC 266, per Lord Hoffmann at page 274B, Mutual Energy v Starr Underwriting Agents [2016] EWHC 590 (TCC) [2016] BLR 312, per Coulson J at [35] and Spire Healthcare v Royal & Sun Alliance Insurance [2016] EWHC 3278, per HHJ Waksman QC at [15]). These cases appear to me to contain general statements of principle to which I must have regard and paragraph [16] of HHJ Waksman QC's judgment in Spire Healthcare, to which Mr Sears expressly drew my attention, does not assist ABC. That paragraph makes it clear that the redundancy argument has a role to play in the exercise of contractual interpretation but that "It all depends upon the construction issue in question, the effect of the alternative interpretation and the contractual context as a whole". In my judgment the other factors in this case to which I must have regard point so plainly towards the use of the natural and ordinary meaning of the word 'default' that the redundancy argument is insufficient to tip the balance. Further, and in any event, it can provide no assistance on the question of what exactly the parties intended the word 'default' to mean if they did not intend it to carry its natural and ordinary meaning.
34.7 Further, I am not persuaded that the extract from Lord Neuberger's speech in Arnold v Britton on which Mr Sears relies in fact provides him with the support he seeks to extract from it. Lord Neuberger is there emphasising the fact that, absent unusual circumstances, the parties must be taken to have been focussing on the issue covered by the provision itself, in this case that Disallowed Cost would include costs incurred by reason of the default of the Contractor, and are to be taken to have meant what they said.
34.8 In my judgment, Mr Sears' point about individual clauses making specific provision for circumstances giving rise to Disallowed Cost does not take matters further. Disallowed Cost as defined in the Contract includes seven limbs (clause 1(1)(j)(i)-(vii)), only one of which is concerned with Disallowed Cost as identified elsewhere in the Contract. The parties plainly did not intend Disallowed Cost to be restricted only to cost identified elsewhere in the Contract. Insofar as clause 49(3) makes express provision for Disallowed Cost, that is perhaps unsurprising in circumstances where the requirement to carry out works of repair, amendment, reconstruction and rectification or making good of defects was based on the instruction of the Employer's Representative.
34.9 Finally Mr Sears sought to rely on the provisions of clause 39(2) (already set out above) in support of the proposition that the parties could not have intended any cost due to any failure to comply with the obligations under the Contract, because clause 39 is, he said, an example of a clause that contemplates 'default' whilst not making provision for the costs of that default to be treated as Disallowed Cost. However, as became clear during the course of argument and as I understood him to concede, costs incurred by the Employer under this provision do not fall within Total Cost and so do not need to be treated as Disallowed Cost.
The Purpose of the Contract
Commercial Common Sense
The Claim for Declaratory Relief
Note 1 49(3)“…the cost of all work carried out by the Contractor under sub-clause (2) of this Clause after the date of substantial completion that in the Employer’s Representative’s opinion is necessary due to the use of materials or workmanship not in accordance with the Contract or to neglect or failure by the Contractor to comply with any of his obligations under the Contract shall be a Disallowed Cost”. [Back] Note 2 8(7)(a) “The Contractor shall carry out and complete the Works in an economic and efficient manner and shall not at any time engage greater resources for the Works than are reasonably required for the carrying out and completion of the Works in accordance with the Contract”. [Back]