[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> DBE Energy Ltd v Biogas Products Ltd [2020] EWHC 1285 (TCC) (20 May 2020) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2020/1285.html Cite as: [2020] EWHC 1285 (TCC) |
[New search] [Printable PDF version] [Help]
QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
Fetter Lane London, EC4A 1NL |
||
B e f o r e :
____________________
DBE ENERGY LIMITED |
Claimant |
|
- and - |
||
BIOGAS PRODUCTS LIMITED |
Defendant |
____________________
Miss Nicola Atkins (instructed by Mills & Reeve LLP) for the Defendant
Hearing date: 18 May 2020
____________________
Crown Copyright ©
Covid-19 Protocol: This Judgment was handed down by the Deputy Judge remotely by circulation to the parties' representatives by email and release to Bailii. The date and time for hand-down is deemed to be Wednesday 20 May 2020 at 14:00.
The Period from which interest should run
(i) Costs incurred prior to judgment
(ii) Costs to be incurred after judgment in respect of the replacement of the Pasteuriser Tanks
"In my view there is a fallacy at the heart of Mr Rainey's argument. It jumps from the true proposition that no remedial costs have yet been incurred to the false proposition that no loss has yet been incurred. The loss was incurred on 3 July 2001 and the fact that in the end the Judge – correctly so we are holding – favoured a computation of most of the loss by reference to the cost of a restoration not yet conducted does not alter the date of the loss. Informing therefore the Judge's exercise of discretion to award interest under s. 35A of the Act of 1981 should have been "the basic principle that interest will be awarded from the date of loss". So said Robert Goff J in a passage undisturbed on appeal in BP Exploration Co (Libya) Ltd v Hunt (No. 2) [1982] 1 ALL ER 925 at 975j; and he proceeded to add that "the mere fact that it is impossible for the defendant to quantify the sum due until judgment has been given will not generally preclude such an award"" (per Longmore LJ at [93]).
(iii) Loss of Revenue
Costs
a. First, that it has "resoundingly succeeded" on the issues of liability and made a substantial financial recovery.
b. Second, that Biogas has been wholly unsuccessful on its counterclaim.
c. Third, that Biogas has persistently failed to make or entertain realistic settlement offers, which demonstrates that DBE could not have obtained the same level of recovery without fighting through to the end.
d. Fourth, that Biogas has generally engaged in various forms of unreasonable conduct, including unreasonable pre-action conduct, unreasonable failure to mediate, the late introduction of documents and a supplemental bundle at trial and yet the limited deployment of those documents, the unreasonable denial of various aspects of the claim, the unreasonable and biased conduct of Mr Marshall (its technical expert), the unreasonable failure to cooperate on redactions to the Technical Experts' Joint Statement, the unreasonable application to expunge DBE's reply witness statements, the unreasonable dilatoriness in consenting to extensions of time and the unreasonable and disproportionate objections to ongoing disclosure.
a. DBE's pre-action conduct in effectively "bouncing" Biogas into a claim under the Shorter Trials Scheme without properly notifying Biogas of its intention to do so and affording Biogas no time for a Letter of Response.
b. DBE's failure during the proceedings themselves adequately to particularise its claim and, in particular, its alleged loss of revenue claim.
c. DBE's failure to provide any details on causation in respect of the Tank Heaters Claim in its statements of case or in its evidence, a failure which it is said led directly to the loss of that claim at trial. In particular, Biogas points to the fact that the main judgment finds that DBE's technical expert did not provide an opinion on the cause of the failure of the Tank Heaters in his expert report.
d. DBE's failure to provide a detailed breakdown of its loss claim, its failure to plead the method by which its Delay Claim had been calculated and its failure to serve either factual or expert evidence which assisted on the question of the Delay Claim. In this regard, Biogas points in particular to the confused evidence of Mr Sharratt (see the main judgment at paragraph 211) and to the court's rejection of DBE's attempts to try to supplement that evidence by way of a schematic served with its written closing submissions (main judgment paragraph 213).
a. First, the central issue (and the issue that took up far and away the most time at trial and in the main judgment) was the issue of liability. DBE won on this central issue.
b. Second, the issues arising in relation to liability were substantially the same in relation to both the Tank Heaters Claim and the claim in respect of the Pasteuriser Tanks. The length and cost of the trial would not have been significantly different if the claim had been limited to the claim in respect of the Pasteuriser Tanks. As is clear from the main judgment, there is a substantial amount of common background and the scope of the investigation at trial would have been very similar. The Technical experts would still have been required to produce their reports and give evidence on issues concerning liability, causation in relation to the Pasteuriser Tanks and mitigation of loss. The factual witnesses each covered issues arising in respect of both the Tank Heaters Claim and the claim in respect of the Pasteuriser Tanks. The evidence as to quantum in respect of the Tank Heaters claim (which had a relatively low value) was comparatively brief.
c. Third, the length and cost of the trial would not have been significantly different if the Delay Claim had been limited to a 2 week, rather than a 15 week, period. There was no expert evidence on the issue of delay and Mr Sharratt dealt with the point in only two paragraphs out of three statements provided for the trial. The Quantum experts would always have been required to provide evidence as to the daily/weekly loss of revenue that would be sustained by DBE by reason of the delay alleged to have been caused by the failure of the Pasteuriser Tanks.
d. Fourth, each party can be criticised (with some justification) for its conduct at differing times in the proceedings and Biogas is right to say that insofar as its own unreasonable conduct has caused DBE to incur additional costs, those will be recovered as part of my order. However, in my judgment, Biogas' criticisms of DBE's approach to the Tank Heaters Claim and the Delay Claim have considerable force. In short, the Tank Heaters Claim was doomed to failure by reason of the lack of any adequate evidence on causation (see paragraphs 156-166 of the main judgment). It should not have been pursued and it was unreasonable of DBE to pursue it absent appropriate evidence. The Delay Claim of 15 weeks was, on any proper analysis of the evidence, over-stated. It was not supported by Mr Sharratt's evidence and (as became plain during closing submissions) it was ultimately necessary for DBE to seek to explain that evidence by reference to a schematic which bore no relation to it (see paragraphs 207-214 of the main judgment). Again, this was, in my judgment, unreasonable and resulted in an exaggeration of the amount of DBE's claim.
The Scope of the Costs Order
Costs of the Pre-action Protocol and Mediation
a. In relation to the pre-action protocol, I am not content that DBE did in fact comply satisfactorily with the Protocol. The key pre-action events concerning the claim in respect of the failure of the Pasteuriser Tanks appear to me to be as follows:
i. within a day or so of the failure of the Pasteuriser Tanks, DBE wrote to Biogas intimating a claim. However, the letter was not expressed to be a letter of claim, it did not provide detailed particulars of DBE's alleged loss and damage and it did not inform Biogas that it had any particular time in which to reply. Furthermore, it made no suggestion that DBE was considering making use of the Shorter Trials Scheme.
ii. There then followed some email exchanges between the parties which are somewhat ambiguous as to Biogas' precise position on the potential for mediation, but which make it quite clear that Biogas intended robustly to defend any proceedings which might be commenced against it.
iii. On 11 February 2019, RPC, on behalf of DBE, wrote to Biogas for the first time asking for its confirmation that it would agree to mediate the dispute. Absent much in the way of a positive response, RPC chased again by letter of 1 March 2019 and then by email on 6 March 2019, making it clear that proceedings would be issued if a positive response was not received.
iv. On 7 March 2019 (some 5 weeks or so after the failure of the Pasteuriser Tanks), Mr Newey responded to RPC to say that DBE's claims were now being investigated by Biogas' insurers "who will contact you in due course".
v. On 15 March 2019, Mr Newey emailed RPC pointing out that their reference to proceedings was premature in circumstances where Biogas had not received a protocol compliant letter yet and stating that once this had been received then Biogas' position would be made clear.
vi. This email appears to have hit home, because on 27 March 2019, RPC wrote a formal letter of claim pursuant to the Pre-Action Protocol for Construction and Engineering Disputes to Biogas. Whether or not this letter was adequate in the particulars that it provided is neither here nor there, because importantly its final paragraph gave Biogas only 7 days in which to respond (as opposed to the 14 days for acknowledgment and 28 days for reply provided for in the Protocol).
vii. By email dated 3 April 2019, Biogas said that it would respond but that it needed more time and it expressly referred to its email as constituting an acknowledgment under the Protocol. It confirmed that it would respond on or before 24 April 2019 – i.e. within the 28 day Protocol period.
viii. Instead of waiting for a response, DBE commenced proceedings on 9 April 2019.
ix. In my judgment, this chain of events does not evidence proper compliance with the Pre-Action Protocol by DBE. This was not a case in which Biogas had been dragging its feet for a significant period of time after first receiving notification of a potential claim. Whilst there had been a few weeks' delay, as at 3 April 2019, there is no reason to suppose that Biogas would not have provided a detailed letter of response to the letter of claim by 24 April 2019 or that it would have refused thereafter to mediate.
b. In relation to the costs of the failed mediation, DBE's skeleton argument for the consequentials hearing contained no details as to what had taken place at that mediation. Mr Cheung took me to a Without Prejudice Save as to Costs letter dated 1 November 2019 written by RPC following the mediation (which asserted that Biogas had not put forward any viable defence on liability and pointed out that the focus of the mediation on the part of Biogas on alternative remedial solutions had been misguided) but I do not consider that this letter is sufficient on its own to enable me to judge the rights and wrongs of what took place. I understand that the parties both made global offers to settle and that those offers came relatively close to each other, but I have no further information about what occurred. I note in this regard that in Vellacott the parties agreed that the court could be given information about what had been going on behind the "without prejudice" curtain that would ordinarily be drawn across a failed mediation – a stance that was not adopted in this case. In the circumstances I am not in a position to conclude that justice requires DBE to recover its costs of the mediation. The parties will each bear their own costs.
DBE's Costs of successfully opposing Biogas' application to transfer the case out of the Shorter Trials Scheme
DBE's costs of applying to redact the Technical Expert's Joint Statement
Payment on Account of Costs
a. that a reasonable sum should reflect an estimation of the costs that the receiving party is likely to be awarded by the costs judge in the detailed assessment proceedings or as a result of a compromise of those proceedings; and
b. that a reasonable sum would often be one that is an estimate of the likely level of recovery, subject to an appropriate margin to allow for error in the estimation.