[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Grain Communications Ltd v Shepherd Groundworks Ltd [2024] EWHC 3067 (TCC) (29 November 2024) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2024/3067.html Cite as: [2024] EWHC 3067 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS IN LEEDS
Technology and Construction Court (KBD)
6 Grace Street Leeds LS1 2RP |
||
B e f o r e :
____________________
GRAIN COMMUNICATIONS LIMITED |
Claimant |
|
- and - |
||
SHEPHERD GROUNDWORKS LIMITED |
Defendant |
____________________
Mr Adam Beaumont (instructed by Ward Hadaway LLP) for the Claimant The Defendant did not appear and was not represented.
Hearing date: 30 September 2024
Handed down: 29 November 2024
____________________
Crown Copyright ©
This judgment was handed down by the Judge remotely by circulation to the parties' representatives by email and release to The National Archives. The date and time for hand-down is deemed to be 10:30am on 29 November 2024.
Her Honour Judge Kelly
Introduction
Background and Evidence
3. Obligations
3.2
The Contractor shall not do any work within the Framework Scope until it has received a Work Order for that work.
3.3
Notwithstanding clause 3.2, the Employer makes no representation or guarantee that it will issue a Work Order to the Contractor, and the Employer retains the absolute right to award works within the Framework Scope to other contractors. The Employer shall not in any event be liable to the Contractor whether in contract (including, without limitation, any indemnity), tort (including, without limitation, negligence), breach of statutory duty or otherwise for any loss of income, profits, production, business or opportunity (whether direct or indirect in nature)"
4. Work Order
4.1
If the Employer requires work to be carried out within the Framework Scope, the Employer shall, at its sole discretion, issue a Work Order instructing the Contractor to carry out and complete the Works in accordance with this Framework Agreement and such Work Order.
4.2
The Contractor acknowledges that the Employer has no liability to pay the Contractor for any works and/or services under this Framework Agreement unless and until the Contractor has signed and executed as a deed the relevant Work Order issued under clause 4.1.
SCHEDULE B – PRICING DOCUMENTS
1. Definitions
Unit Pricing - The pricing mechanism and approach elected by the Employer as detailed in this Schedule B and in each Work Order 2. Unit Pricing
2.1
The Unit Pricing applicable to each Work Order shall be clearly documented in the Work Order and, at the Employer's sole option, either be chargeable:
2.1.1 on a fixed Price Per Plot basis, whereby the following shall apply:
2.1.1.1 the Price Per Plot for delivering the requirements of the Work
Order shall be detailed in each Work Order;
the maximum number of Plots stated in each Work Order, providing all requirements of the Work Order have been duly completed…
SCHEDULE D - WORK ORDER TERMS AND CONDITIONS
1. Interpretation
The following definitions and rules of interpretation apply in this Work Order. 1.1 Variation means any addition to, omission from or other change in the Works or the period or order in which they are to be carried out.
8. Commencement and Completion
8.1 The Contractor shall commence the Works on the Commencement Date and complete the Works on or before the Completion Date subject to any extension of time under clause 8.3. The Contractor shall carry out the Works in accordance with any agreed programme.
8.2 The Works shall be carried out within standard working hours set out in the Order Information.
8.3 If the Contractor is delayed in completing the Works by the Completion Date for reasons beyond the Contractor's control, including, the ordering of any Variation (provided such Variation is not occasioned by the Contractor's default), the Contractor shall notify the Employer in writing and shall provide such details as the Employer reasonably requires. Subject to clauses 8.4, 8.6, 8.7 and 8.8, the Employer shall give such extension of time (if any) to the Completion Date as may be reasonable, and notify the Contractor accordingly.
8.4 Where any Variation is necessary as a result of any negligence, act, omission, breach or default of the Contractor or any person employed or engaged by the Contractor, the Variation shall be carried out by the Contractor entirely at the Contractor's own cost and expense and the Contractor shall not be entitled to any payment or to any loss and/or expense, or any extension of time to the period(s) of completion of the Contractor's obligations under this Work Order in respect of such Variation.
8.5 The Employer shall determine and notify the Contractor in writing of the date when the Works are complete.
8.6 Notwithstanding any other provision, the Contractor shall not become entitled to any payment, any loss and/or expense, or to any extension of time for the completion of the Works or any part of them on account of any circumstance arising by reason of any error, omission, negligence or default of the Contractor or of any sub-contractor or supplier, or of any of his or their employees or agents, including but not limited to the Contractor's failure to notify the Employer timeously setting out details of the information the Contractor requires to comply with the Contractor's obligations under this Work Order; or for any delay which is concurrent with another delay for which the Contractor is responsible.
8.7 Where NRSWA applies to the Works, the Employer shall make the relevant application to the street authority under NRSWA. The Contractor shall be entitled to an extension of time under clause 8.3 only to the extent the street authority agrees to such extension for completion and reinstatement, and not otherwise.
8.8 The Contractor shall constantly use his best endeavours to prevent delay in the progress of the Works, and to mitigate the effects thereof, however caused, and to prevent the completion of the Works being delayed or further delayed beyond the Completion Date.
8.9 If the Employer wishes to investigate the possibility of achieving completion of the Works before the Completion Date, it shall invite the Contractor to provide a quote identifying the time that can be saved and any additional associated cost. The Employer shall be under no obligation to accept the Contractor's quote, and reserves the right to negotiate any proposed costings with the Contractor.
11 Variations
11.1 The Employer may, without invalidating this Work Order, issue instructions requiring a Variation. The Contractor shall forthwith comply with all instructions issued to the Contractor under this clause 11.
11.2 Any oral instructions given by the Employer requiring a Variation shall be confirmed in writing by the Employer.
11.3 The Contractor shall not be entitled to payment for any Variation for which the instruction is not given or confirmed in writing.
11.4 Variations shall be valued by the Employer on a fair and reasonable basis with reference to, where available and relevant, rates and prices in the Pricing Document.
11.5 Notwithstanding any other provision of this Work Order, the Contractor shall not become entitled to any additional payment for any Variation where the Variation has been instructed on account of any circumstance arising by reason of any error, omission, negligence or default of the Contractor or of the Contractor's subcontractors or suppliers, or of any of the Contractors or their employees or agents.
"Can we just have conformation [sic] that all contracts signed will not be going ahead as mentioned today".
"Dear Peter
Thank you for your emails. As discussed, it remains our current intention to continue with all Work Orders signed between Grain Communications Ltd and Shepherd Groundworks Ltd.
However, as mentioned on Monday's call, we are in further discussions with relevant stakeholders in relation to our build programme, and it currently does not look like we will be able to commence Works on Site in relation to the following Work Orders before the end of 2023:
* Blyth Phase 3;
* Newcastle Phase 8;
* Newcastle Phase 9; and * Wallsend Phase 5.
All other Work Orders are unaffected.
We will continue to keep in touch with you regarding our programme for the Works under these Work Orders and will let you know when anything changes. Regards
Richard"
The Claimant cancelled the permits granted on 24 October 2023 for re-submission at an appropriate future date as the works would not commence before the end of 2023.
The Law
b. The Unfair Contract Terms Act 1977;
c. Construction Law – Julian Bailey (2020) Vol II at paragraph 7.23;
d. Marks and Spencer plc v BNP Paribas Securities Services Trust Company
[2016] AC 742;
e. BP Refinery (Westernport) Pty Ltd v Hastings Shire Council (1977) 52 ALJR
20;
f. M Harrison & Co (Leeds) Ltd v Leeds City Council (1980) 14 BLR 118;
g. Norwest Holst Construction Ltd v Co-Operative Wholesale Society Ltd [1998]
EWHC (TCC) 339;
h. Mannai Investments Company Limited v Eagle Star Life Assurance Company
Limited [1997] AC 749;
i. North Midland v Cyden [2018] EWCA Civ 1744;
j. Omak Maritime Ltd v Mamola Challenger [2010] EWHC 2026 (Comm).
(1) A term can be implied into a contract provided the term which a party seeks to imply is not illegal or contrary to an express term of the contract.
(2) A term can be implied if it is reasonable and equitable, is necessary to give business efficacy to the contract, is so obvious it goes without saying, is capable of clear expression and does not contradict any express term of the contract.
(3) The effect of a variation instruction depends on the substance of what is said in the instruction. Variation instructions are not to be read strictly or pedantically.
(4) The variation must be evident from the document said to constitute a variation instruction.
(5) An instruction need not contain the word postpone in postponing certain works.
(6) What is required is that any variation instruction complies with the requirements of the contractual clause for variations.
The Issues
(1) Is the Claimant's application inappropriate to be decided in Part 8 proceedings?
(2) Did the email of 24 October 2023 amount to a variation or a cancellation of the Work Order in breach of contract?
(3) Did the terms of the Work Order preclude an implication of a term preventing the Claimant from postponing the works?
(4) In any event, if there was a breach of any such implied term, is the Defendant precluded from recovering loss of profit or mobilisation and demobilisation costs as a result of:
a. the provisions of the Work Order and framework agreement; and/or
b. the application of compensatory damages limiting the Defendant's recovery to that which could have been recovered under the Work Order?
Is the Claimant's application inappropriate to be decided in Part 8 proceedings?
Did the email of 24 October 2023 amount to a variation or a cancellation of the Work Order in breach of contract?
"84. However, I do not consider that under the definition of a Variation in this Contract that GCL can cancel the commencement of the whole of the Works, or postpone the commencement of the whole of the Works without clear words which would convey to the reasonable recipient that that is what was intended so that the Contractor would know that the Variation mechanism had been triggered under the Contract.
85. In my opinion, the reasonable recipient of the email issued by GCL on 24th October 2023 (12:13) would not understand that it was being issued either as a Variation to the Work Order, under clause 11.1, or as confirmation of an oral variation to the Work Order, under clause 11.2, for the simple reason that it does not make any mention of the fact that it is being issued either as a Variation, or as a confirmation of any oral variation that may have been given in the telephone conversation held on Monday 23rd October 2023.
86. As it seems to me that GCL's email seeks to cancel the commencement of the Works under the Work Order and is not labelled in any respect as a Variation I do not consider that it can be interpreted as something that in my opinion it was not intended to be."
11.2 for there to be a variation of the terms and conditions of the Work Order.
Did the terms of the Work Order allow the implication of a term preventing the Claimant from postponing the works?
In any event, if there was a breach of any such implied term, is the Defendant precluded from recovering loss of profit or mobilisation and demobilisation costs as a result of:
a. the provisions of the work order and framework agreement; and/or
b. the application of compensatory damages limiting the Defendant's recovery to that which could have been recovered under the Work Order?
Defendant's submissions concerning the recovery of loss of profit, mobilisation and demobilisation costs.
Conclusion
a. That the Claimant is not and was not in breach of the terms of the Blyth Work Order, or the Framework Agreement by informing the Defendant of the postponement of the Blyth Phase 3 works via its email from Richard Cameron to Peter Shepherd, dated 24 October 2023.
b. To the extent the Claimant is in breach in respect of declaration a. above, the Claimant is not liable to the Defendant for the mobilisation, demobilisation or loss of profit allegedly suffered by the Defendant under the Blyth Work Order, or the Framework Agreement.