BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?
No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | ||
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Shaylor Group Ltd v Valescure Property Ltd [2024] EWHC 750 (TCC) (04 April 2024) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2024/750.html Cite as: [2024] EWHC 750 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS
OF ENGLAND AND WALES
TECHNOLOGY AND CONSTRUCTION COURT (KBD)
Fetter Lane, London, EC4Y 1NL |
||
B e f o r e :
____________________
SHAYLOR GROUP LIMITED (in administration) |
Claimant |
|
- and - |
||
VALESCURE PROPERTY LIMITED (in liquidation) |
Defendant |
____________________
The Defendant did not appear and was not represented
Hearing date (held remotely): 20 February 2024
Further written submissions: 5 March 2024
____________________
Crown Copyright ©
Mr Justice Kerr:
Introduction
Facts
Works done and payment requests
The claimant's insolvency
Terms of the contract
"no further sum shall become due to the Contractor under this Contract other than any amount that may become due to him under clause 8.7.5 … ."
"following the completion of the Works and the making good of defects in them (or of instructions otherwise, as referred to in clause 2.35), an account of the following shall within 3 months thereafter be set out in a statement prepared by the Employer:
1. the amount of expenses properly incurred by the Employer, including those incurred pursuant to clause 8.7.1 and, where applicable, clause 8.5.3.3, and of any direct loss and/or damage caused to the Employer and for which the Contractor is liable, whether arising as a result of the termination or otherwise;
2. the amount of payments made to the Contractor; and
3. the total amount which would have been payable for the Works in accordance with this Contract;"
"if the sum of the amounts stated under clauses 8.7.4.1 and 8.7.4.2 exceeds the amount stated under clause 8.7.4.3, the difference shall be a debt payable by the Contractor to the Employer or, if that sum is less, by the Employer to the Contractor."
Assignment of the defendant's rights and obligations under the contract
The first adjudication
The second adjudication
Subsequent history
Submissions
"… while declarations are for the most part statutory in origin, they have throughout their history had a close affinity with equitable remedies which has left its mark upon them. This is especially evident in the discretionary nature of the declaration. This discretion is employed, as it was originally employed with regard to all equitable remedies, primarily to do justice in the particular case before the court. It is wide enough to allow the court to take into account most objections and defences available in equitable proceedings."
Reasoning and Conclusions
"where it is a condition of enjoying the benefit that a burden is assumed, the assignee cannot enjoy the benefit without discharging the burden".
Here, it is not the assignee but the other party, the claimant, which is denying the effectiveness of the assignment to transfer the defendant's rights and obligations to the assignee; yet relying on the effectiveness of the assignment to deny the incurring of expenses and the suffering of losses by the defendant.
Note 1 A £900 discrepancy appears to have crept in, probably through typographical error; the figure is £9,013,919 in the original interim payment application (no. 19); cf. £9,013,019 at paragraph 95 of the second adjudicator’s decision; but £9,013,919 at paragraph 96; cf. £9,013,019 at paragraph 36 of the first adjudicator’s decision. [Back]