![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] [DONATE] | |
England and Wales High Court (Technology and Construction Court) Decisions |
||
You are here: BAILII >> Databases >> England and Wales High Court (Technology and Construction Court) Decisions >> Southern Electricity Power Distribution PLC v OCU Modus Ltd [2025] EWHC 723 (TCC) (27 March 2025) URL: http://www.bailii.org/ew/cases/EWHC/TCC/2025/723.html Cite as: [2025] EWHC 723 (TCC) |
[New search] [Printable PDF version] [Help]
BUSINESS AND PROPERTY COURTS
TECHNOLOGY AND CONSTRUCTION COURTS (KBD)
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
SOUTHERN ELECTRICITY POWER DISTRIBUTION PLC | Claimant |
|
- and - |
||
OCU MODUS LIMITED | Defendant |
____________________
Michael Smith (instructed by HA Law Solicitors) for the Defendant
Hearing dates: 4, 5, 6 and 20 March 2025
____________________
Crown Copyright ©
Mr Justice Constable:
A. Introduction
B. The Adoption Agreement
"In accordance with this Agreement, the Contractor shall carry out and complete the Contestable Works [the works carried out by Modus] and perform all other obligations as are identified in this Agreement to be performed on its part."
"16. The Contractor shall construct and install the Contestable Works in accordance with this Agreement, the Schedules and Appendices."
"The Contractor shall bear all reasonable costs incurred by the Company in fault repair or rectification of other defects associated with Adopted Contestable Works during the Defects Correction Period unless such faults are caused by the Company."
"the period of two years after the Adoption in relation to the Contestable Works…"
"The Contractor shall bear all reasonable costs incurred by the Company in correcting any latent defects associated with Adopted Contestable Works subject to the provisions of the Limitation Act 1980…"
"the Parties acknowledge that all work on Adopted Contestable Assets may only be performed by the Company and that neither the Contractor nor the Customer may correct any defects after adoption."
C. The Law
(1) the normal position in cases of defective construction work is that the measure of loss is the cost of reinstatement. (Lord Cohen in East Ham Corporation v Bernard Sunley & Sons Ltd [1966] A.C. 406, 434-435, approving text from the Eighth Edition of Hudson's Building and Engineering Contracts which stated: 'There is no doubt that wherever it is reasonable for the employer to insist upon reinstatement the courts will treat the cost of reinstatement as the measure of damage';
(2) this is subject to reinstatement being a proportionate and reasonable course of action. If it is unreasonable to reinstate, the loss does not extend to reinstatement and the loss would generally be the diminution in value. (Ruxley Electronics v Forsyth [1996] AC 344);
(3) in assessing what is reasonable the correct approach is an objective one (Scutt v Lomax [2000] 1 WLUK 530 at [50]);
(4) it is for the claimant to prove causation, and if he relies upon a decision which he says was reasonable, it is for him to prove its reasonableness (Skandia Property (UK) Ltd v Thames Water Ltd 57 Con LR 65 at 79);
(5) the advice of an expert may be a material factor when determining what was a reasonable course of action (Axa Insurance UK Place v Cunningham Lindsey United Kingdom [2007] EWHC 3032 (TCC) at [268], [2007] All ER(D) 290); (Linklaters Business Services v Sir Robert McAlpine Ltd & Or [2010] EWHC 2931 (TCC); [2010] 133 Con LR 211 at [131]);
(6) once a course of action is established as reasonable, the starting point for recovery will usually mean the actual costs incurred if work has been done, from which there should be a reason to depart (Hall v Van de Heiden [2010] EWHC 586 (TCC) at [66]);
(7) once causation is established, it is for the defendant to allege and prove a break in the chain of causation, for example by establishing a failure to mitigate (Skandia Property (UK) Ltd v Thames Water Ltd 57 Con LR 65 at 79);
(8) the claimant has a duty to mitigate loss. That duty is not an exacting one. It is not enough for the wrongdoer to show that it would have been reasonable to take the steps he has proposed: he must show that it was unreasonable of the innocent party not to take them. This is a real distinction. It reflects the fact that if there is more than one reasonable response open to the wronged party, the wrongdoer has no right to determine his choice. It is where, and only where, the wrongdoer can show affirmatively that the other party has acted unreasonably in relation to his duty to mitigate that the defence will succeed (per Sedley LJ in Wilding v British Telecommunications plc [2002] ICR 1079 at [55]);
(9) there is no requirement for a party to be satisfied with reinstatement of an article to an inferior quality to that stipulated in the contract merely because it is cheaper for a contract breaker to supply that (Radford v deFroberville [1977] 1 WLR 1262 at 1248H);
(10) reasonable costs do not mean the minimum amount which, with hindsight, it could be held would have sufficed (The Board of Governors of Hospital for Sick Children v McLaughlin & Harvey Plc 19 Con LR 95);
(11) however, if there are two equally efficacious alternative remedial schemes and one is cheaper than the other, then prima facie the claimant is obliged to put in hand the cheaper of the two schemes (McGlinn v Waltham Contractors Ltd (No 3) [2008] Bus LR 233) Put another way, if the claimant in fact chooses a more expensive option in this scenario, this does not mean that he is acting unreasonably; but the additional cost is regarded as a consequence of the claimant's choice and not of the defendant's wrong (Hirtenstein v Hill Dickinson [2014] EWHC 2711 at [127]).
D. The Facts
"- 6 Sheath repairs at PV substation cut out & sent to jointing school
- 2 joints in Joint Bay 6 cut out and replaced;
- 3 at Joint bay 13 cut out and replaced; sheath fault located at Joint Bay 15; 5 cores good from end to end (continuous sheath) C
- Circuit 1 – Red is faulty, yellow faulty - Only holding 1200kV.
- ¾ of cable route cleared of sheath faults. From Wroughton PV to Joint Bay 13 is clear, other side of the railway to Toothill - still possible faults."
could carry this out. A PD test is a test which can be carried out when the cables are either live or not, and its purpose is to identify insulation defects. Mr Phillipps gave evidence that he did not believe this test was, in fact, carried out.
(1) insulating material had been applied around the cables, indicating the presence of sheath repairs, but without any record of such repairs having been carried out;
(2) a section of the earth screen wires beneath the tubing had been removed and tests indicated open circuits on all six cables;
(3) there were no cable marker boards;
(4) the cables were laid flat rather than trefoil adjacent to joint positions;
(5) there were numerous sheath faults and unrecorded sheath repairs at various points along both circuits;
(6) minimal backfill sand was present and the backfill contained sharp, gritty material which may have caused the penetration damage to the joint outer covering;
(7) the fibre optic cables were laid incorrectly, in that they were laid direct into the ground without proper duct protection in that the green outer duct had twisted round such that the runs of the individual inner ducts changed colour at various points along the route.
(8) The Lloyds Report concluded:
"the quality of the installation was below that expected from a NERS approved contractor and had resulted in a significant number of sheath faults, some of which had not been recorded on the as-laid drawings."
"Regrettably, due to the slow progress made to date, coupled with lack of regular updates and a clear programme of works to completion, we must now inform you that the next step for us is to consult with Ofgem, with a view to go to determination. Whilst we would hope that we can resolve prior to determination, you will appreciate the financial impact, as well as impact on onward sale, of the solar park not being energised, is such that we feel it necessary to take these steps."
"The question as to the extent of works which should be undertaken.
The best case is to re test the circuits following isolation and review the results. Re energise and carry out a regime of outages and tests at 6 monthly intervals until be are confident that the circuits are not degrading further.
Worst case is to take the outage and test then systematically excavate each joint bay on a rolling program as provided to the customer and removal all joints on circuits that do not meet the 10M ohm criteria, a two stage program has been provided to the customer and is circa six months carried out over two financial years. This will result in compensation claims from the land tenant for crop damage and reinstatement of access roads and land in the join bay area. May in fact mean that we are removing good joints from the network. The doubling of the amount of joints on the circuits increasing the risk of future failure. Potential damage to circuits and joint adjacent to the works and currently meeting the required criteria. SEPD will become liable for any reinstate on highways opening notices. May leave SEPD with a large bill for works that are undertaken that can not be recouped from the ICP this cost if unrecoverable will need to be capitalised in some way and may not have any widget based health improvement score associated with it."
Circuit 1
L1 5040V @ 15.58 MΩ
L2 4871V @ 3.36 MΩ
L3 4942V @ 5.0 MΩ
Circuit 2
L1 4875V @3.4 MΩ
L2 4907V @3.99 MΩ
L3 4949V @5.17 MΩ
(1) the abrasion of the outer sheath was of a variable standard and the dimension of 100mm was not complied with on most of the joints as required by the jointing instructions;
(2) braid wires at joints extended beyond the joints moisture barrier by between 10-35mm (at different locations), reducing the protection from moisture ingress and resulting in low sheath insulation resistance value when tested;
(3) a temporary wire binder was left in position in one location, when it should have been removed;
(4) there was poor core preparation of the semi-conducting layer on the strippable core screen cable resulting in an uneven finish, which would eventually lead to degradation of the joints in service;
(5) EPR tape was missing from constant force springs at joints. Two layers of EPR tape should have been applied, but, in some locations, there was no tape at all and, in other locations, PVC tape had been wrongly applied;
(6) where the braid protruded from the roll spring, it had not been trimmed in level with the copper wires. In some locations, the excess braid was folded back over the roll spring, but not all of the wires were folded back;
(7) some of the cable used did not contain any water swelling tape over the copper wire screen, which reduced the ability of the tape to prevent the movement of water around the copper wire screen, leading to a low sheath resistance;
(8) the use of sharp/coarse backfilling material caused external damage to the joints with minimal fine fill in some locations. The impact damage caused as a result of the inadequate backfilling material permitted water ingress causing green Verdigris and resulted in damage to the internal jointing components that would reduce the intended stress control of the joints and eventually lead to electrical failure of the joints; and
(9) repairs had been purported to be carried out by covering joints in heat shrink repair sleeves, however:
(a) there was a failure to remove excess sealant off from around the end of the sleeve;
(b) in some locations, multiple sleeves had been applied to the joints indicating damage to the outer cold shrink damage and the failure of the first repair to rectify this issue;
(c) wrinkle marks and an uneven surface on the heat shrink repair showed that the tube had not been fully shrunk, as it should have been, leading to susceptibility to mechanical damage and inadequate flow of materials under the sleeve;
(d) the adhesion between the cable sheaths and the repair sleaves was poor, likely as a result of poor abrasion, poor cleaning of the cable jacket or a lack of heat when shrinking down the sleeve;
(e) the Repair Sleeve Instructions states that the over sheath of the cable should only be abraded for 75mm, but this was not achieved;
(f) the quality of the abrasion found under the repair sleeve was either entirely absent or poor with only light abrasion found;
(g) the Repair Sleeve Instructions state that 38mm mastic should be applied under the repair sleeve. However, in some locations no mastic was applied at all, in other locations mastic was applied over the repair sleeve rather than under the repair sleeve and, where mastic was used, the mastic was only 18mm wide and had little adhesion to the repair sleeve. As a result, there was a reduction in the protection provided from the ingress of moisture, such that moisture was present under the repair sleeves.
(10) The EA Report concluded that:
"the quality of the work raises concern regarding the jointer training, level of competence and work conditions during the installation."
"The General conclusion from the E.A Technology report was that the joints had failed due to poor Jointing Practices. One of the recommendations from the report was to replace the cable circuits. SSEN stated that the findings of this report has dented their confidence in the quality of the remaining joints on the circuits and requested that these joints be replaced."
"Due to the uncertainty over the quality of the workmanship, the Durkin Option 2 [i.e. replacement along the same route] appears to be the most feasible and cost effective option. In addition to the replacement of cables and joints, consideration should be given to removing the backfill material around the ducts and replacing it with sand or CBS. Also, the reinstatement materials and top soil should be installed to the correct specification.
If a double circuit outage cannot be tolerated for an extended period, it would be necessary to consider a third option of constructing one completely new circuit offline, and rehabilitating one existing circuit later."
"I totally agree with your summary that Option 2 would be the preferred option. Unfortunately as SSE will be looking to recover the costs form the ICP who installed these circuits, we have to be very careful how we proceed. If we can get the contractors to give us price on both options this will give us some evidence to present to senior management who can then make the final decision how they would like to proceed with these works. Could you put together a bill of quants for both options…."
'It was subsequently found that there were several sheath faults on the cables. Further fault locations were carried out to locate these sheath damages, many defects were found. The faulty joints were inspected by an independent body, and the quality of
the Jointing was found to be substandard. The reports recommendation stated that consideration should be given to the replacement of the cable circuit because of the
potential safety risks to personnel and the likely continuing degradation of the circuit. It was agreed by SEN Policy that the minimum request would be to replace all the joints on the circuit. Several meetings were held with the ICP to give them the opportunity to carry out the remedial works. As no agreement could be reached it has been decided that SSEN would undertake these works and seek to recover the costs from the ICP. It should be noted however that the cable has not faulted over the last 12 months.
Following a recent meeting with strategic investments the Solar Park Owner has stated their concern over the loss of generation revenue due to the outages required to carry out the remedial works. They would prefer any outages to be taken in Autumn/ winter time to reduce these losses. The developer Solar Park Owner is now awaiting our proposal for carrying out remedial works. It is understood that some contribution will could be made towards the remedial works if there is an option to reduce the time that the Solar Park is offline. Several options are proposed in this brief paper for discussion prior to arranging a meeting to agree the most appropriate way forward with the developer Solar Park Owner.
…The ICP has indicated that they do not agree that there is a need to replace all the joints and that they do not have the funds to cover the costs for such an undertaking.
Several options have been considered for the proposed remedial works and these are outlined further below. The most important factor in coming to the recommended proposal is the minimal loss of generation time. Partial replacement/overlay of sections/joint replacement would all provide a compromised installation and severely impact the generation time and create a large financial impact because of that.
Conclusion
The most commercially sensible option considering the impact on the loss of generation, which is estimated at £50k per day, is to completely overlay the existing circuits. There are two horizontal directional drills along the route and it is proposed that these are maintained and reused. The existing easement is sufficient to allow another trench to be installed whilst maintaining the existing circuits live. The downtime would be minimised with this option as the works required that will impact the generation is the replacement of the cable within the horizontal directional drill and the final terminations at either end. This option will also present SSEN with the confidence to accept responsibility for the circuit on an ongoing basis. This option is dependent on the developer contributing to the capital cost of replacement of the defective circuits.'
Option 1: compromised final installation, with potential faults remaining on the existing cable; additional risk with twice the amount of cable joints on the remediated circuits;
Option 2: re-use of existing ductwork installed by the ICP which may be defective;
Option 3: 'produced' [reduced] level of protection in agricultural areas as cables are directly ploughed; slightly higher risk of sheath damage during cable installation; higher safety risk during installation, ploughing new cable circuits adjacent to the existing live circuit;
Options 4 and 5: installation of system under the control of SEPD, providing greater confidence for future liability.
'By way of background as discussed Swindon Solar Farm Limited is 100% owned by myself, but was in part funded by a long-term investment being made by 3 local authority's namely Warrington, Thurrock and Newham. As you know we lease the land from the science [museum] group and in addition we provide extensive payments from the revenue generated by the project to local community schemes. In simple terms the Swindon project is a very public one with some very big public backers that relies on the income we generate each year to in the main assist with the provision of front line services to the residents in their areas, the funds are used in a variety of ways ranging from adult and social care to innovative projects to help people in fuel poverty so in simple terms this is a large public interest project.'
Having identified the wider impact of the loss of the solar parks revenues in a way that was plainly designed to put pressure on SEPD, notwithstanding the absence of any legal obligation to recompense SSF for lost revenues, the email then set out the proposed resolution working with SEPD, as follows:
'1. SSE is to agree to lay a new cable next to the existing one as soon as possible in qtr. 1 2018 this would then only mean we would have a small outage programme for connections etc.
2. By SSE agreeing to a new cable this would guarantee SSE and us as owners that a correct cable fit for purpose and duration would be in place going forward.
3. As owner, we have recognised that it would appear SSE has been defrauded in some way in agreeing to adopt the current cable and SSE will need to take the appropriate legal action against the relevant parties to recover the various sums owed to affect the new cable etc. we have a lot of data and can get hold of additional information to assist SSE in such a claim and would be willing do so in return for the confirmation on the cable etc.
4. In addition, as owner we are also willing to look at making some form of financial
contribution to SSE to assist with the new cable works.'
'After Further meetings with Rockfire they are now stating that the only option they would accept is for the cable circuits to be replaced. They have agreed that the Solar Park would make a contribution towards the enhanced scheme with a view that SSEN would recover the reaming costs from Modus.
…
It has been suggested that a Rechargeable job should be set up to enable the solar Park to pay their contribution toward the project. We would then look to recoup the remaining costs from Modus. There is no guarantee that we would be successful in recouping all the remaining costs.'
'As stated previously it is imperative to us that the solar park is not out of action for long periods during the summer months and as such the agreement will be that SSE will lay a new cable next to the existing one as soon as possible in Quarter 2 2018, with the work expecting to last up to 4 months and outage times minimised. A guarantee will be provided at the end of the works that the cable is now fit for purpose with an expected life cycle to match the solar park.'
'I think It was the pressure from the solar farm and, obviously, the experts reports backing up with some concerns, so there was obviously an unknown risk of how long this circuit would last.'
'3. SEPD and the Customer agree that the cables referred to in the Adoption Agreement are defective and do not meet the standards required pursuant to the Adoption Agreement.
4. SEPD's preferred method for resolving the defective cables will result in the electricity supply to the Customer's Property being interrupted.
5. The Customer has a different preferred method for resolving the defective cables which reduces the length of time of the interruption albeit at a higher cost.
6. In consideration of SEPD undertaking the Customers preferred method of resolving the defective cables, the Customer is willing to contribute to the additional costs incurred by SEPD.'
E. The Expert Evidence
Nature and Extent of Defects
(1) Lack of EPR tape over the force spring. This can cause moisture ingress and potential mechanical instability caused by the constant force spring. Without the constant force spring being securely in place sharp edges of the copper wires and mesh may damage the insulation of the cable.
(2) Application of tape on the copper braid. Braids of copper wire are used as armour in XLPE cables providing protection to the insulation and other parts of the cable. Application of the tape directly onto the braid of copper wires prevents the braids from being embedded directly into the mastic applied as part of the cable joint. This in turn leads to gaps in the layers that could allow the ingress of water into the joint.
(3) Temporary Binder Left in Place. Temporary binders are typically used during the cable preparation process to keep the components together while assembling the joint. However, they are intended to be removed once the final components are in place. Leaving the temporary wire binder in the cable joint poses a risk to the sheath used to provide protection to the joint as it creates an uneven surface and creates gaps within the joint. Sharp edges of the wire binder can also cause mechanical damage to the inner surface of the sheath.
(4) Uneven cutting of semi-conducting screen. The screen was not removed evenly, creating uneven distribution of electrical fields which can lead to damage to the insulation and can lead to premature failure.
(5) Poor Abrasion of Cable Sheath. Poor abrasion will subsequently lead to poor or reduced adhesion between the cable sheath and either the resin or repair sleave. The risks associated with the deviation of poor abrasion to the HV cables outer sheath is that it will reduce the adhesion between cable sheath and the resin or repair sleave. This can lead to water ingress which ultimately will lead to catastrophic cable failure.
(6) Impact Damage to Outer joint cold shrink. Damage in the outer jacket of the joint cold shrink, can compromise the protection that the cold shrink is intended to provide to the components of the cable joint. In the case of the photograph presented in the EA Report, the damage has caused the exposure of the copper braid. The impact damage to the cable sheath increases the risk of electrical stress concentration at the screen edges which could lead to breakdown of dielectric strength of the insulation.
(7) Cable sheath not cleaned under repair sleeve. The presence of dirt can lead to bad adhesion between the cable sheath and the repair sleaves. This can create voids and electric treeing in the insulation which will lead to electrical faults through the insulation.
(8) Copper wire braid too long. When either the copper mesh or braid are too long and not as per specification of the joint cut position, this can lead to damage to the outer sheath of the cable. It is for this reason that is considered a defect as damage to the outer cable sheath of the cable results in potential moisture ingress as well as reduced sheath resistance.
(9) Poor shrinkage on repair sleeve. The risks from this deviation include that the damaged HV cables outer sheath has not been fully sealed by the repair sleeve and as such could lead to potential water ingress and electrical faults. The failure could manifest due to a potential insulation breakdown.
(10) Incorrect size mastic tape used for repair sleeve. Failure as a result of using the incorrect width mastic tape manifests due to loss of adhesion area which would then allow water ingress that can degrade the insulation of the cable and lead to electrical failure.
(11) Uneven application of mastic patch seal. When the mastic seal does not fully cover the cable components within, it leaves exposed spots in the joint which are not completely sealed and as such can limit the protection offered to the copper mesh and wires. Subsequent failure would manifest due to a potential insulation breakdown due to water ingress, corrosion of wire mesh and potential mechanical instability of the joint.
Risk of Future Failure
Remedial Options
(1) Partial replacement of the faulty and/or defective joints in each circuit.
(2) Replacement of both circuits in their entirety through replacement of one circuit at a time, using the same trench already excavated.
(3) Replacement of both circuits in their entirety in a newly excavated trench.
F. Causation, Reasonableness, Mitigation and Remoteness
Pleadings
Summary of Key Facts drawn from Sections D and E
(1) Modus was not prepared to carry out or fund any technical solution acceptable to SEPD.
(2) Modus also expressed concerns as to its ability to fund, or repay, the cost of carrying out even Option 1 (which was approximately 33% of the Option 2 estimated costs and 25% of those for Option 4);
(3) SEPP were entitled to conclude, at least at the time they were making their decisions, that the prospect of recovering any or any substantial sum from Modus was (at the very least) risky;
(4) SEPD had a statutory obligation to connect SSF to the grid;
(5) carrying out the works in such a way as to require a significant downtime of the existing circuits would cause very significant financial losses to SSF (whether the daily losses are £23,000, £28,000 or £50,000);
(6) SEPD had no legal liability to compensate SSF for those financial losses;
(7) SSF/Rockfire placed pressure on SEPD to agree a solution which did not involve any significant downtime to the connection, including explaining why there was a 'large public interest' in maintaining generation.
(8) SSF/Rockfire also offered a financial contribution in order that the remediation take place without causing an outage (subject to that contribution being repaid if any recovery was made in relation to the costs of remediation against any third party).
(9) SEPD agreed to carry out the works in the way they did ('the Adopted Solution') under an agreement by which SEPD received £700k for doing so. It is not possible, on the evidence, to say for certain whether this contribution was more, less or the same as the then perceived additional cost of carrying out the works in the way requested by SSF. On the basis of figures within the options report spreadsheet, at least, it exceeded the delta between Option 2 (in-line replacement with significant outage) and Options 4 and/or 5. The Remedial Agreement would, on these figures at least, have represented a net contribution to SEPD's anticipated costs irrespective of the maintenance of the connection during the works.
(a) was it reasonable for SEPD to replace the circuits by the Adopted Solution?
(b) if it was reasonable, are the actual costs of doing so properly attributable to the defendant's wrong rather than a consequence of the claimant's choice?
(c) if so, are the actual costs of doing so themselves reasonable?
(1) it was objectively reasonable to reject in-line replacement (Option 2) as not being equally technically efficacious, in light of the contemporaneous concerns over ducting. However, in light of SEPD's own view that this was its preferred method at the time of entering the Remedial Agreement, I approach the remainder of the analysis on the basis that SEPD did not regard the advantages of complete replacement over in-line replacement as sufficient to justify as reasonable the additional costs;
(2) it was objectively reasonable to reject any replacement methodology, including in-line replacement, which required personnel to work in close proximity to a live circuit. I accept Mr Alyah's technical evidence that there were significant risks, which could not be fully mitigated, in carrying out the installation of the replacement circuits in the same or an adjacent trench whilst one or both existing circuits remained live;
(3) this conclusion leads to two possible approaches in practice: (1) replacing both circuits, whether in-line or by way of complete replacement in the same or adjacent trenches within the same easement, but in so doing, ensuring that the existing cable was disconnected so it presented no risk. This would mean that, inherent in any of these solutions, there would be a long period during which SEPD would provide no method by which SSF could generate revenue from the solar plant; or (2) replacing both circuits in a different route, which would mean no risk of interference with the existing circuits and which could therefore leave the live circuits in place until the installation of the new circuits was complete i.e. the Adopted Solution;
(4) although Mr Phillipps' evidence was that there were reasons independent of the outage issue which meant that routing the replacement cable in a different route had advantages in terms of landowner relationships/access, I do not accept that this of itself was likely to be a weighty issue in the decision to undertake the Adopted Solution. This is because the importance of these issues is inconsistent with the Agreement with SSF which identified SEPD's 'preferred method' which, I have found, was 'Option 2' – i.e in-line replacement;
(5) it is plain on the evidence that the motivation for choosing the Adopted Solution was the desire to accede to SSF's request that the remedial work did not give rise to any or any significant outage. It is clear that a long outage would cause SSF significant losses in revenue. Whilst I take account of the fact that there was no legal liability on SEPD's part to compensate that loss in revenue, that did not mean that it was unreasonable to accede to SSF's request, or that so doing did not flow naturally from the requirement to remedy Modus' breaches. This is because:
(a) SEPD's business is (at least in part) providing infrastructure to solar generation plants allowing them to export electricity and generate revenue. It had a statutory obligation to provide that connection. On any view, SEPD had a legitimate business interest in maintaining that which, by statute and by the Connection Agreement with the SSF, it was (to put it at its lowest) expected to provide. The fact that consequential loss for a failure to provide an effective export mechanism was minimised or excluded does not detract from the wider business and reputational interest in maintaining the connection. Put another way, whilst, as Mr Dickson said, SEPD could have (legally) said 'tough luck' without direct pecuniary implications, it does not follow that it is unreasonable, or a failure to mitigate loss, to decide not to do so;
(b) pressure was being exerted by SSF on SEPD to keep the connection live during the remedial works by reference to the wider impacts on the local community if electricity generation from the solar farm ceased. In particular, SEPD was being told that, 'Swindon project is a very public one with some very big public backers that relies on the income we generate each year to in the main assist with the provision of front line services to the residents in their areas, the funds are used in a variety of ways ranging from adult and social care to innovative projects to help people in fuel poverty so in simple terms this is a large public interest project'. There is no suggestion that this was not true. Mr Smith fairly accepted that this was a legitimate factor to consider: it plainly was. The legitimate interest in maintaining the connection in a large public project would be an important consideration in its own right, in addition to the related self-interested reputational issues which SEPD was entitled to take account of. Moreover, SSF had earlier threatened to consult with SEPD's regulator during the initial period during which the circuits were disconnected, and it is a reasonable inference that they may have done so again had the Remedial Agreement not been reached. It is therefore unsurprising that SEPD felt 'pressure' from SSF, as described by Mr Dickson, even if there was no direct financial leverage in the sense of a liability to pay compensation;
(c) SSF offered a financial contribution to the solution, in circumstances where on the basis of Modus' communications, SEPD was entitled to conclude that any recovery against Modus in practical terms was, at best, risky. Acceding to its customer's wishes, and acting, in circumstances where the customer was willing to finance, subject to recovery, some, all or indeed potentially more than additional costs involved in carrying out the works to keep the ability to generate electricity was objectively reasonable.
(6) It is not possible to say with any certainty what the additional cost was for carrying out the works in such a way as to keep the existing circuit alive. The highest it could possibly be put is the delta between the estimate for Option 2 at £1.4m and the outturn costs of the new route at £2.4m, but this is plainly not a safe comparison. A closer, but definitely not an entirely satisfactory guide, is the difference between £1.4m and Option 4 (£1.9m) i.e. about £500,000. It may have been lower. The burden is on Modus to prove the failure to mitigate, and to do so it is for Modus to establish how much cheaper it may have been to carry out the work in the way they contend SEPD should have: they have not done so. However, putting the burden of proof to one side, when weighed against the very legitimate interest in minimising as far as possible any downtime to the connection to the solar park, I conclude that whether the additional cost was £500,000 or £1m, the Adopted Solution was objectively reasonable;
(7) in circumstances where, by reason of Modus' defective work, it was reasonably necessary to replace the circuit, it was readily foreseeable that, SEPD would seek to carry out repairs without, insofar as they reasonably could, interrupting the existing connection to their customer. The decision to carry out the remedial works in this way was both reasonable, and caused in law by the underlying breaches and defective circuits;
(8) there is no evidence that the actual cost of carrying out the work was itself unreasonable, once it has been determined that the decision to replace the circuits was reasonable, and the decision to use the Adopted Solution was reasonable.