BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?

No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!



BAILII [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback]

Irish Court of Appeal


You are here: BAILII >> Databases >> Irish Court of Appeal >> Paulson Investments Ltd & Anor -v- Jons Civil Engineering Ltd & Anor [2016] IECA 169 (08 June 2016)
URL: http://www.bailii.org/ie/cases/IECA/2016/CA169.html
Cite as: [2016] IECA 169

[New search] [Help]



Judgment
Title:
Paulson Investments Ltd & Anor -v- Jons Civil Engineering Ltd & Ors
Supreme Court Record Number:
23/13 SC
Court of Appeal Record Number:
2014 728
Date of Delivery:
06/08/2016
Court:
Court of Appeal
Composition of Court:
Finlay Geoghegan J., Peart J., Hogan J.
Judgment by:
Hogan J.
Status:
Approved
Result:
Allow and set aside
Judgments by
Link to Judgment
Concurring
Finlay Geoghegan J.
Peart J.
Hogan J.
Peart J.



THE COURT OF APPEAL
2014 No. 728

[Article 64 Transfer]


Finlay Geoghegan J.
Peart J.
Hogan J.

BETWEEN/


PAULSON INVESTMENTS LTD. AND ALBERT ENTERPRISES LTD.
PLAINTIFFS/APPELLANTS
- AND -

JONS CIVIL ENGINEERING LTD. AND P.J. EDWARDS AND CO. LTD.

DEFENDANTS/RESPONDENTS


JUDGMENT of Ms. Justice Finlay Geoghegan on the 8th day of June 2016

1. This is an appeal against an order of the High Court (Birmingham J.) of the 6th December, 2012, that the plaintiff furnished security for costs to each of the defendants. The order was made pursuant to a judgment in writing delivered on the 2nd November, 2012.

2. The orders of the High Court were made pursuant to s. 390 of the Companies Act 1963. It remains the applicable provision to the determination of the appeal notwithstanding the enactment of the Companies Act 2014.

3. There has been one significant and material development in the litigation which whilst indicated in the course of the hearing of the appeal occurred subsequent to the hearing. The Court has been informed that the plaintiffs have lodged €500,000 with their solicitors to be held to the credit of the action to meet any costs orders made against the plaintiffs in the substantive action by which I understand is meant following the full hearing. At the appeal hearing, it had been indicated on behalf of the plaintiffs that this would be done and the court directed that it should be told if such a sum was provided to its solicitors.

4. It is appropriate to note at the commencement of this judgment that the parties were in agreement that the figures which had been estimated for the defence costs of trial namely, €784,983 plus VAT in the case of the first defendant and €769,000.73 plus VAT in the case of the second defendant calculated on the basis of a twenty day hearing were simply estimates agreed for the purposes of the application for security for costs. It is agreed that they were estimates of the entire costs and were not intended to form the basis of the amount for which security would be ordered in the event that the defendants’ applications were successful. The amount for which the order should be made was not in issue in the High Court and it appears that the parties had envisaged that if orders for security were made that the determination of the amount might be remitted to the Master.

5. In the course of the hearing I raised a question as to whether the amount had been estimated in accordance with the Supreme Court judgment in SEE Company Limited v. Public Lighting Services Limited [1987] ILRM 255, i.e. costs incurred after the demand for security was made. On the facts herein proceedings commenced on the 1st November, 2005 and the applications for security was made by the first defendant in April 2011 and by the second defendant in May 2011. Irrespective of the outcome of the substantive appeal, the parties, through their counsel at the hearing were in agreement that the part of the order made in the High Court which specifies the estimated amounts as the amounts payable would have to be vacated and in the event that the appeal against the order for security failed there would have to be a determination of the amount to be provided by reference to an estimate of costs after the date of demand for security.

Background to the proceedings
6. The first named plaintiff, Paulson Investments Limited (“Paulson”) is the owner of a site at Dyer Street, Drogheda, beside the river Boyne. In 2000 it was decided that the site would be developed and the development would take place through the second named plaintiff Albert Enterprises Limited (“Albert”). Both companies are part of the Mirella Group of which Mr. William Smyth is a director and principal shareholder.

7. In 2000 there were discussions with the first named defendant Jons Engineering Limited (“Jons”) in relation to a fixed price contract to construct the three storey basement of a proposed nine floor development on the site. Ultimately agreement was reached but no written contract entered into which contributes significantly to the complexity of the factual and legal issues in the proceedings. P.J. Edwards & Company Limited (“Edwards”) the second named defendant is a specialist piling contractor who in response to a tender agreed to carry out piling works on the site. The plaintiffs retained Consulting Engineers, Hendrick Ryan and Associates who issued drawing specifications and instructions for the construction of the basement and associated piling works. Jons retained AGL Consulting to provide geo-technical design consultancy works.

8. Work commenced without any contractual documents being entered into. The first element of the works was the construction of what is referred to a secant pile wall around the full perimeter of the development site. There is a dispute as to whether this wall forms part of the temporary works or the permanent works with potentially different consequences as to the persons responsible. Jons went on site in September 2000 and Edwards entered on site and commenced piling work in February 2001. Almost immediately, problems ensued. The piling operations gave rise to settlement which exceeded parameters specified by Hendrick Ryan and Associates. Piling work stopped in March 2001. Further investigations were carried out, other expert engineers engaged and ultimately the defendants left the site in September and November 2001. The plaintiffs subsequently constructed a modified development consisting of a seven storey over ground structure.

9. The initial proceedings relating to the works carried out on the site were plenary proceedings by Jons against Mr. William Smyth in 2001. Subsequently, in those proceedings, Jons applied to join Paulson and Albert as defendants and the proceedings appear to have reached the stage of delivery of an amended defence in 2009. In 2001, Edwards issued summary proceedings against Albert which were subsequently remitted to plenary hearing and the defence delivered by 2005. Neither of these proceedings has been set down for trial.

10. These proceedings commenced on the 1st November, 2005, with a contemporaneous delivery of a statement of claim. The claim against Jons is in contract and negligence. The claim against Edwards is in negligence alone. The total damages claimed are in the order of €25 million. Defences were delivered in 2007 and in 2008 voluntary discovery sought. There was either agreement or orders requiring the plaintiffs and Jons and Edwards to make discovery by different dates in 2008.

11. Edwards made its discovery by November 2008; the plaintiff completed its discovery by October 2010 and then in November 2010, brought a motion to strike out the defence of Jons for failure to make its discovery. Jons completed its initial discovery by February 2011.

12. In early 2011, the defendants became aware that the plaintiffs had entered NAMA and in February 2011, Jons requested security for costs and in May 2011 Edwards did likewise and both refused. Motions were issued in April and December 2011, respectively. Hearing of the two motions for security for costs and the plaintiffs motion to strike out Jons’s defence for failure to make discovery, commenced on the 21st February, 2012 and adjourned on the fourth day, as counsel for Jons informed the High Court that certain missing records for the “Casa Grande Rig 26” which had been the subject of much discussion and comment had been found. Thereafter the hearing of the motions was adjourned to June 2012, further discovery made and affidavits sworn. The trial judge permitted cross examination of Mr. Pentony of Jons and Mr. Gogarty its solicitor on the application of counsel for the plaintiff. The hearing of the motions lasted a further four days. The trial judge delivered on the 6th December, 2012, a single judgment on both the applications for security for costs and on the application to strike out the defence of Jons. He refused the application to strike out and he made orders for security for costs.

13. This judgment is only concerned with the appeal against the decision to grant security for costs. Nevertheless it is of relevance to this appeal that the trial judge decided the application for security for costs contemporaneously with the motion to strike our for failure to make discovery and heard the matter in total over eight days based upon a significant number of affidavits and exhibits thereto including expert reports.

High Court judgment
14. The application was made pursuant to s. 390 of the Act of 1963 which provides:-

      “Where a limited company is plaintiff in any action or other legal proceeding, any judge having jurisdiction in the matter, may, if it appears by credible testimony that there is reason to believe that the company will be unable to pay the costs of the defendant if successful in his defence, require sufficient security to be given for those costs and may stay all proceedings until the security is given.”
15. As noted by the trial judge the applicable principles were not seriously in dispute. The applicant must establish by credible evidence that the respondent will not be able to meet an order for costs. It was agreed that on the estimate of costs for each of the defendants and the available financial information in relation to the plaintiffs, that the defendants had each discharged the onus of so establishing.

16. The defendants, as applicants then must show that each has a prima facie defence to the plaintiffs' claim. If a bona fide defence is established then unless the plaintiff can establish the existence of some special circumstances which would justify the refusal of an order for security for costs the order pursuant to s. 390 will be made.

17. In the High Court each defendant contended that it had a prima facie defence or as has been sometimes put, a sustainable defence to the plaintiffs' claim against it. That was hotly disputed by the plaintiffs.

18. The plaintiffs submitted that, in any event, there were special circumstances and in the High Court identified those as:-

      (a) "Inordinate delay on the part of the defendants in seeking security for costs, during which period of delay the plaintiffs incurred considerable costs particularly in relation to discovery"; and

      (b) "That there has been default on the part of the first named defendant in complying with the agreement in relation discovery. This contention was made as an alternative to the application to strike out. The default is such that it is contended that the defence of the first named defendant should be struck out, but if that is not done, then in any event the order for security for costs should be refused."

19. The trial judge concluded that each of the defendants had made out in accordance with the applicable legal principles a prima facie defence to the plaintiffs’ claim. He then considered the special circumstances contended for by the plaintiff and rejected both the delay and the failures of the first named defendant in relation to discovery as constituting special circumstances which would justify the refusal of the order sought.

Appeal
20. The plaintiffs in their appeal submit that the decision of the trial judge both on bona fide defences and the absence of special circumstances should not stand.

21. In pursuing the appeal against the determination of the trial judge that each of the defendants had made out a prima facie defence it is not contended that the trial judge erred in the legal approach to the consideration of the issues save that it is submitted that he failed to engage with certain of the evidence adduced and in particular certain of the expert evidence adduced by the plaintiffs.

22. The trial judge in a very careful judgment identified the standard required to be met by each defendant in accordance with what I had stated in an ex tempore judgment in Tribune Newspapers v. Associated Newspapers Ireland t/a The Irish Mail on Sunday (Unreported, High Court, Finlay Geoghegan J., 25th March, 2011):-

      “. . . in my judgment, what is required for a defendant seeking to establish a prima facie defence is to objectively demonstrate the existence of admissible evidence and relevant arguable legal submissions applicable thereto which, if accepted by a trial judge, provide a defence to the plaintiff’s claim.”
23. The trial judge also referred to a number of other authorities which indicate that once the court is satisfied that the defendant has made out a prima facie defence it is not the function of the court to assess the strengths or weaknesses of the parties’ respective cases. He also expressly considered the plaintiffs’ submission that the defendants had failed to deal with what was termed “critical evidence” from a Mr. Luby of SLR Global Environment Solutions and his conclusion that ground conditions on site were not unforeseen in the context of the Supreme Court decision in Hidden Ireland Heritage Holidays Limited t/a The Hidden Ireland Association v. Indigo Services Limited and Others
[2005] IESC 38, [2005] 2 IR 115.

24. The trial judge having considered the prima facie defences of each of the defendants contended for concluded that on the evidence adduced by the defendants on the motions and the legal arguments relied upon, notwithstanding the evidence and submissions of the plaintiff that they did meet the threshold of a prima facie defence in accordance with the relevant authorities.

25. The trial judge whilst he reached that conclusion expressly at para. 42 recognised that he may not have referred to all the issues canvassed by the defendants which they relied upon as establishing a bona fide defence at this stage and then stated:-

      “42. . . . For my part, I find myself in a position very similar to that described by Clarke J. in Parolen Limited v. Doherty & Lindat Limited (Unreported, High Court, Clarke J. 12th March, 2010). In the course of his judgment, Clarke J. had this to say:-

        ‘There are very many issues both of law and fact which will need to be resolved before the case can come to a proper conclusion. It does not seem to me appropriate to enter into anymore detailed analysis of the legal principles at this stage for the trial is the best place to come to a fair conclusion on these matters. Suffice it to say that I am satisfied that there is a possibility that Mr. Doherty may succeed in persuading the court that, both on the law and on the facts, circumstances are such that he is not obliged to account to Parolen for the option agreement which he has entered into with the purchaser. In these circumstances, I am satisfied that Mr. Doherty has made out an arguable case or prima facie defence.’

      43. As Clarke J. was, I am of the view that there are very many issues both of law and fact which will need to be resolved before the case can come to a proper conclusion. Like him, I am of the view that it is not appropriate to enter into any more detailed analysis of the legal principles at this stage for the trial is the best place to come to a fair conclusion on these matters. It is possible that the defendants will succeed on the law and the facts and possible that the plaintiff’s claim will fail. In the circumstances, I am satisfied that both defendants have made out an arguable case and accordingly, it is necessary to consider whether the plaintiffs have established special circumstances by virtue of which they ought not to be required to provide security for costs.”
26. Whilst the trial judge used the term “arguable case” in para. 43 it is clear from the authority of the judgment that he was using the term in the sense of a prima facie defence of a standard required by the authorities.

27. Counsel for the plaintiffs on appeal accepted, as he must do on the authorities, that the court cannot consider the strengths or weaknesses of the respective positions of the parties if the defendant meets the prima facie threshold. Nevertheless in able and detailed submissions, but more appropriate in my view to the trial of the proceedings he sought in essence to persuade the court of the inability of the defendants to succeed in their defence, principally by reference to evidence to be adduced on behalf of the plaintiffs and the strength of the plaintiffs’ case.

28. With the exception of one issue to which I will refer, I have concluded that there is no basis upon which this Court should interfere with the conclusion reached by the trial judge in accordance with the correct legal principles and on a consideration, in some detail, of the issues relating to different aspects of the prima facie defences relied upon by each of the defendants. The absence of any written contractual provisions between the parties; a significant factual disputed issue as to whether the secant piles form part of the permanent or temporary works; disputes as to the responsibilities of different parties for different aspects of the work and the significant factual disputes in relation to the site investigations and alleged unforeseen ground conditions make the resolution of the plaintiffs’ claims and the defences of each defendant thereto complex both in the determination of many disputed factual issues and the consequent legal responsibilities for the failure of the piling works and the damage caused thereby to the site.

29. The one issue in which it appears that the trial judge may have been in error in concluding that Jons had established a prima facie defence related to the contention which it sought to make that it contracted with Mr. Smyth personally and not with the second named plaintiff. The Court at the appeal hearing drew the parties’ attention to the fact that Jons had not pleaded in its defence that it had contracted with Mr. Smyth rather than with either of the plaintiffs. Counsel for both parties admitted that no one had had adverted to this in the High Court. In the absence of such a defence being pleaded it does not appear that it ought to have been considered as available to the defendants on the application for security for costs as a prima facie defence. Nevertheless my conclusion on that issue does not alter my overall view that there is no basis on appeal to interfere with the conclusion reached by the trial judge that the first named defendant, Jons, had made out a prima facie defence. Certain of the other prima facie defences of Jons identified by the trial judge also relate to the entirety of the claim. In particular the defence in reliance upon the contention that the piling work should properly be considered as forming part of the permanent or temporary works for the purposes of the IEI standard form of contract which provisions are contended to apply to the relationship between the plaintiffs and the first defendant.

Special circumstances
30. The applicable legal principles are not in dispute. What constitutes a special circumstance is not a closed class: West Donegal Land League Ltd. v. Údarás Na Gaeltachta and Others [2006] IESC 29, [2007] 1 ILRM 1. The onus of establishing special circumstances is on the plaintiff. Special circumstances must be considered by the court in the context of the particular facts of the individual case.

31. In an application to which s. 390 applies, the court is not bound to make an order for security once the prima facie defence and inability of the plaintiff to meet the costs of the defendant if successful is established: SEE Company v. Public Lighting Services [1987] ILRM 255. It may refuse to do so if special circumstances are made out. However the discretion given the court to refuse an order for security is one which must be exercised in the interests of justice. On the one hand as has been repeatedly stated the requirement for the provision of security for costs by a limited company serves a legitimate aim and purpose both to protect against the potential abuse of the privilege of limited liability and also to protect defendants against litigation costs would be irrecoverable where they can establish that they may succeed in their defence. However, such an order also risks impeding the constitutional right of access to the courts if the security fixed results in a limited company being incapable of pursuing its claim.

32. It is relevant to the exercise of the discretion in this case that in accordance with the decision of the Supreme Court in Lismore Homes Limited (In Receivership) v. Bank of Ireland Finance Limited [1992] 2 I.R. 57, it is agreed between the parties that any order for security made pursuant to s. 390 of the 1963 Act, must be for the full amount of the estimated or probable costs of the defendant after the date upon which the application for security was made. The court does not have a discretion to make an order for security of a lesser amount.

33. In the High Court the plaintiff only contended for two grounds of special circumstances, delay and the first named defendant’s failures in its obligations in relation to discovery. Delay applied to both defendants. The period of delay identified by the plaintiffs was only between January or early February 2010 and February 2011, in the case of the first named defendant. The plaintiffs submitted that accounts for the year ended 31st March, 2009, had been filed in the company’s registration office on the 26th January, 2010, and that those accounts which showed a combined net asset position of €1.23 million should have given rise to concern for the defendants and been further investigated. Even if those accounts ought to have been considered and the defendants should be considered as having been in a position to bring an application in 2010 the trial judge concluded that the period of approximately one year’s delay was not such as to justify the refusal of an order for security for costs. He took into account that in that period the plaintiffs had completed its discovery in October 2010 and expended €125,000 on preparing its discovery.

34. On the second special circumstance whilst the trial judge held that the first defendant had been in breach of its obligations nevertheless he also found as a fact that there was “no element of deliberate suppression of documentation or any deliberate attempt to disadvantage the plaintiffs by withholding documents until late in the day. What occurred happened as a result of human error, culpable error certainly, but not as a result of the pursuit of an intentional strategy”. The first defendant’s discovery which had wrongly not included these documents was completed in February 2011. The trial judge concluded that the punishing of the first named defendant by withholding an order for security for costs would be “an entirely disproportionate response”.

35. The special circumstances relied upon on appeal now include a very significant additional matter namely, the fact that there has been lodged with the solicitors for the plaintiffs €500,000 to be held to the credit of the proceedings for the purpose of discharging any order for costs of the substantive trial (I understand this not to include interlocutory orders already granted) award in favour of either defendant against either of the plaintiffs.

36. The lodgement of a sum of money in such a way as to make it exclusively available for the purpose of discharging orders for costs in favour of the defendants if successful in the defence of these proceedings is, in my view, a special circumstances which it is permissible for this Court on the hearing of the appeal to take into account. I recognise that the amount is as a matter of probability less than the full amount of the probable amount of security if the High Court order were upheld and the amount was to be determined upon the basis of the estimated twenty day trial but only costs incurred after the respective dates of application for security. The work on discovery by each defendant was or ought to have to have been completed prior to that date which will have involved substantive costs. Nevertheless €500,000 is a considerable sum.

37. The circumstances of these proceedings which the Court must now take into account include that they are proceedings which commenced in 2005 and which relate to events in 2001 in respect of which there are also plenary debt proceedings. These proceedings are at an advanced stage as pleadings are closed and significant and expensive discovery completed. Whilst they are not in the commercial list, nevertheless they are proceedings which would be appropriate for case management and an application to that effect can be made by any of the parties to the High Court.

Conclusion
38. I have concluded that the plaintiffs in lodging €500,000 with their solicitors have discharged the burden of establishing that there are now special circumstances which when viewed in the context of the stage reached in the proceedings in the High Court is such that it is in the interests of justice between the plaintiffs and the defendants in these proceedings that the Court should allow the appeal and vacate the order for security for costs made in the High Court.

39. As the notification to the court that the monies had been lodged with the solicitor for the plaintiffs occurred subsequent to the date of hearing, I have also concluded that the Court should hear the parties as to any particular requirements in terms of undertakings or acknowledgements by the solicitor for the plaintiff in relation to the terms upon which they now hold the monies to satisfy the intention that those monies be exclusively available for the purpose of discharging any orders for costs in favour of either defendant against either plaintiff following the determination of these proceedings in the High Court.


JUDGMENT of Mr. Justice Gerard Hogan delivered on the 8th day of June 2016

1. This is an appeal brought by the plaintiff companies against the decision of the High Court (Birmingham J.) directing that they provide security for costs in favour of the defendants pursuant to s. 390 of the Companies Act 1963 (“the 1963 Act”): see Paulson Investments Ltd. v. Jons Civil Engineering Ltd. [2012] IEHC 541. As it happens, the security for costs rules in respect of companies have subsequently been altered by the new s. 52 of the Companies Act 2014 which came into force on 1st June 2015. It is, however, agreed that as this litigation and, indeed, the judgment under appeal ante-dates the coming into force of this provision, the applicable law for the purposes of this appeal remains that contained in s. 390 of the 1963 Act.

2. Section 390 of the 1963 Act provides:

      “Where a limited company is plaintiff in any action or other legal proceeding, any judge having jurisdiction in the matter, may, if it appears by credible testimony that there is reason to believe that the company will be unable to pay the costs of the defendant if successful in his defence, require sufficient security to be given for those costs and may stay all proceedings until the security is given.”
3. There has been one development since the date of the High Court judgment in that shortly after this appeal was heard in November 2015 the plaintiffs lodged some €500,000 in court to the credit of the action, as indeed they had indicated that they would do during the course of the appeal. The defendants and the Court were later notified of this development. This sum, as we shall presently see, is approximately one third of the estimated combined costs which the defendants will incur in defending this action.

4. The present litigation arises from developments which took place at a site in Dyer Street, Drogheda, Co. Louth as far back as 2000. The plaintiffs are related companies involved in property development. Both companies form part of what is known as the Mirella Group and each is a wholly owned subsidiary of Mirella Investment Ltd. Mr. Willie Smyth is a director and is the principal shareholder of both plaintiff companies and also of Mirella Investments Ltd.

5. The first named plaintiff, Paulson Investments Limited (“Paulson”) is the owner of a site at Dyer Street, Drogheda, which is bounded to the south by the River Boyne. In 2000, it was decided that the site would be developed and that the development would take place through the second named plaintiff, Albert Enterprises Limited (“AEL”). It was intended that the development would consist of a three storey basement, with six floors above ground, offering office, retail, commercial and residential elements. The first named defendant, Jons Engineering Ltd. (“Jons”), carried on a civil engineering business, while the second named defendant, P.J. Edwards & Company Limited (“Edwards”), is a specialist piling contractor.

6. At some stage in 2000 Mr. Willie Smyth entered into discussions with a view to entering into a fixed price contract with Jons to construct the three storey basement element of the development. Somewhat unusually, however, at no point was a written contract actually entered into by the plaintiffs or, indeed, by Mr. Willie Smyth with the first defendant, Jons. It is agreed that the plaintiffs and Edwards had no contract with each other.

7. There is, in fact, some dispute about whether at particular stages, Jons was dealing with the plaintiff companies or whether it was dealing with Mr. Willie Smyth personally. Indeed, at one point Jons issued summary proceedings in 2001 against Mr. Smyth claiming the payment of invoices in the sum of €600,000 arising out of this dispute. It is only fair to record that the defence of Mr. Smyth was to the effect that the contract was with the plaintiff companies. As will presently be seen, one of the defences advanced by Jons is to the effect that its contract was with Mr. Smyth personally and not with the plaintiff companies.

8. Jons was engaged as the main contractor to excavate the basement. It was also to design and construct the temporary and permanent works required for the three basement floors. Jons engaged the services of AGL Consultancy to prepare this design. Jons were also responsible for monitoring these works.

9. The plaintiffs retained consulting engineers, Hendrick Ryan and Associates (“Hendrick Ryan”), to advise in relation to the construction of the development. Hendrick Ryan issued drawings, specifications and instructions for the construction of the basement and the piling and ground works associated with this. In preparing its specifications Hendrick Ryan contemplated the use of what is known as secant piles in constructing the basement retaining wall. (Secant piles are a series of interlocking piles forming a structure around the building site below ground level.)

10. This procedure is described as involving bored and case in situ piles which would be constructed using rotary bored piling techniques and, if necessary, would use support fluids to support collapsing or unstable boring ground. In essence, the Hendrick Ryan specifications contemplated the use of conventional or traditional methods involving as it did large diameter bored cast in place piles, using temporary casing and a support fluid to maintain the stability of the bore if necessary.

11. The tender documentation was furnished to Edwards, which responded and ultimately took on the task of piling. It is, however, a matter of some controversy as to who actually engaged Edwards to carry out the pile driving. The plaintiffs contend that Edwards was engaged by the Jons to carry out the piling works. This is disputed by Jons who maintain that the appointment of Edwards was made by the plaintiffs and/or by Mr. Smith personally.

12. As it happens, Edwards had previously worked on a site in close proximity to the Dyer Street site. On that occasion they had not used the traditional secant pile method of piling but, rather, an alternative method of constructing a secant piled wall which has the capacity to be quicker and more economical known as “continuous flight augering” (“CFA”). (The secant piled wall itself can be used either as a retaining wall or as a temporary support structure during construction work).

13. In broad terms, CFA piling is a replacement piling technique where the boring operation removes matter and replaces it with concrete. The concrete is injected under pressure through the hollow stem of the auger. Once the pumping of the concrete has commenced, the auger is then progressively withdrawn, bringing with it extracted soils from the bore up to the surface. After the auger is removed, reinforcement is then inserted. The advantage of CFA is that it can be used to construct a continuous bore without ever leaving an open hole.

14. By tender dated 5th July, 2000, which was accompanied by a letter dated the 17th July, 2000, Edwards tendered for the piling aspect of the contract at a price of €1,082,700 plus VAT. This tender was premised on the use of the CFA piling method. Edwards qualified its tender in the following manner:-

      “We have based our tender on being able to use CFA bored piles which has never been a problem in Drogheda where we have worked literally less than 50 metres from the site. However, we do note the very long chiselling times recorded below 11 metres which would cast some doubt on the use of CFA methods. It would be prudent, therefore, to qualify our tender which would be subject to test boring, which we would carry out at our own expense.”
15. This tender was subsequently accepted by Henricks Ryan. In doing so it specified by letter dated 8th November 2000 that the concrete CFA secant piling should be carried out within indicated limits of “settlement” or ground movement.

16. Jons entered upon the site in September 2000, in apparent anticipation of the execution of a written contract incorporating the terms and conditions of the Institute of Engineers of Ireland (“IEI”) standard contract. In passing it might be observed that the parties are agreed - at least for the purposes of this motion - that the relationship between the plaintiffs and Jons is indeed governed by the IEI standard contract.

17. In February 2001 Edwards entered on site and commenced piling work without, however, having carried out the test boring to which they had referred in their letter of 17th July 2000. A new rig (a Llamada P90TT) was used in the first instance. It would seem that the on-board computerised instrumentation on the Llamada rig was not functioning properly, at least not initially.

18. Two piles were bored on the first day, but problems quickly emerged as during the concreting process, concrete from the first borehole “slumped” into the adjoining one. Further secant and loadbearing piles were installed and bored and these initial problems were addressed at a meeting between Jons, (and its consultants, AGL Consultancy), and Edwards on 9th February 2001. (Neither Henricks Ryan nor the plaintiffs were present at this meeting.)

19. Shortly after the commencement of piling operations, the ground in the vicinity of the piling became unstable. This resulted in ground movement or settlement which exceeded the stipulated maxima. On the 10th/11th February 2001 Edwards replaced the Llamada rig with a Casagrande CFA 26 rig. Considerable problems nonetheless persisted and the piling records showed multiple cases of auger rotation with minimal penetration as well as auger withdrawal using forward rotation without back screwing. There were, it would seem, up to thirty open boreholes. It does not appear to be in doubt that these practices are highly undesirable: the plaintiffs’ expert, Mr. Wasilewski, described the conduct of Edwards as “folly”. He further stated that in his opinion the latter’s “incorrect choice of pile type and defective workmanship had caused the [ground] movement.” It is only fair to observe that there is, nevertheless, considerable debate among the various experts as to whether these difficulties were caused or exacerbated by unsuitable ground conditions.

20. On the 2nd March, 2001, Hendrick Ryan instructed that piling should cease. Edwards maintained that the piling difficulties which had been encountered were due to unforeseen ground conditions which were not suitable for the CFA piling techniques. The experts retained by Edwards were very critical of the soil evaluations that had been carried out prior to its involvement. Following discussions, there followed attempts at site improvements involving, in particular, engaging in a process known as “grouting” in an effort to stiffen the ground. However, these efforts to keep settlement within the specified parameters ultimately failed. Hendrick Ryan were not prepared to relax the parameters or tolerances and work was then suspended in September 2001 at which stage the defendants were requested to leave the site.

21. The plaintiffs ultimately proceeded with a modified development consisting of a seven storey over ground structure, thus omitting the basement which had been proposed.

22. The present proceedings were commenced by the plaintiffs in November 2005. The claim against Jons involves allegations of breach of contract and also involves claims in tort, whereas the claim against Edwards is brought entirely in tort. The plaintiffs claim sums of approximately €2m. for wasted professional fees. There is, additionally, a claim for approximately €22m. in respect of the reduced capital value of what was actually constructed as compared with what had been originally intended.

23. For the purposes of the application for security for costs the parties reached agreement on a number of factual matters. First, the defence costs of trial can be estimated at €784,983 plus VAT in the case of Jons and €769,000.73 plus VAT in the case of Edwards calculated on the basis of a twenty day hearing. These sums amount in total to €1,553,983.73 plus VAT. Second, the aggregate value of the plaintiffs by reference to the accounts filed by them for year ending the 31st March, 2010, amounts to €830,579, while the accounts for year ended the 31st March, 2011, show aggregate net asset values of €158,859.

24. It is, accordingly, not in dispute that the plaintiffs will be unable to pay the costs of either defendant if both defendants are successful in their defence. The principal issues, therefore, both in the High Court and, on appeal, in this Court are whether:-

      (i) the defendants could establish a prima facie defence

      and

      (ii) whether there are other special circumstances which would justify the Court in not making any such order for security for costs.

25. The plaintiffs also argue that the defendants unduly delayed applying to the High Court for security for costs. In view of the conclusions I am about to reach in respect of this application, it is unnecessary to express any view on this latter issue.

The judgment in the High Court
26. In a characteristically thorough and careful judgment Birmingham J. concluded (albeit with some hesitation, it would appear) that the defendants had each established a prima facie defence under the various headings I am about separately to consider. He also concluded that the defendants were justified in delaying making their application for security for costs in view of the fact that the financial position of the plaintiffs had deteriorated in the period after 2009. He accordingly concluded that it was appropriate to make the requisite order for security for costs.

Has Jons established a prima facie defence?
27. Turning first to the question of whether a prima facie defence case has been established by Jons, the recent case-law shows that the mere assertion of such a defence is not enough (Tribune Newspapers v. Associated Newspapers (Ire.) Ltd., High Court, 25th March 2011). A defendant wishing to advance a prima facie defence must also go further than demonstrating that such a defence is simply arguable (Pagnell Ltd. v. OCE (Ire.) Ltd. [2015] IECA 25). Such a defendant must also show that there is an evidential basis for the suggested prima facie defence (see, e.g., Tribune Newspapers and Pagnell).

28. As Charleton J. stated in Oltech (Systems) Ltd. v. Olivetti UK Ltd. [2012] IEHC 512, this means that the defendant has a “reasonably sustainable defence”. This did not mean:

      “…a barely arguable defence, since experience demonstrates that there is little that cannot be argued. It has to be demonstrated, rather, that if there is a legal defence that it is potentially sustainable on a practical view of the law or, if the defence is one of fact, that if what the defendant alleges in answer to the plaintiff is proven in court that it will defeat the plaintiff’s claim.”
29. In Oltech the defendant could point to the fact that the plaintiff had acknowledged the existence of a debt due to the defendant. In these circumstances the existence of a reasonably sustainable defence could be simply and quickly established. The complexity of the present case is in stark contrast to the relatively straightforward nature of the defence in Oltech.

30. It would have to be acknowledged, however, that in complex litigation of the kind presented by this case, the prima facie defence requirement gives rise to some difficulties. While this Court has stressed that the courts must avoid, where possible, delving “unduly deeply into complex matters which constitute the subject matter of the litigation” (see CMC Medical Operations Ltd. v. Voluntary Health Insurance Board [2015] IECA 69, per Mahon J.), there are times when, in order to ascertain whether there is such a defence, this seems unavoidable.

31. Where, as here, nearly all of the issues are highly - even unusually - complex, both in terms of law and fact, the prima facie test becomes extremely difficult to apply, at least without a detailed evaluation of the claim and the defence of the kind that the courts have traditionally avoided in interlocutory applications of this kind. The defendants can certainly advance arguable defences in respect of every single point. If, however, the higher standard of “reasonably sustainable defence” suggested in Oltech is to be applied, then on the particular facts of this case it would in truth be necessary to have a detailed analysis of these substantive points in the manner almost suggestive of a mini-trial in order to do justice to the parties.

32. In this vein, Jons has advanced four potential defences. First, it is suggested that the contract was with Mr. Smyth personally and not with the plaintiff companies. Second, that it bore no responsibility for Edwards under the IEI contract. Third, and related to the second, that Edwards was in the nature of a nominated contractor and it relies on the Supreme Court’s decision in Norta Wallpapers v. John Sisk & Sons [1978] I.R. 114 for this purpose. Fourth, it is said that any damage was caused by the unforeseen nature of the ground soil or its unsuitability for CFA piling. These arguments may now be considered in turn.

The Smyth contract point
33. In the High Court, Birmingham J. considered that Jons had established a prima facie defence on this point:

      “So far as the defences raised by the first named defendant are concerned, perhaps the most straightforward is the contention that any contract it had was with Mr. Willie Smyth personally and not with either of the companies named as plaintiffs. Ordinarily, one has to say, a defence based on a contention that a plaintiff has sued the wrong party or in this instance that the wrong parties are plaintiffs is one that would be greeted with scepticism or a lack of enthusiasm. It is most frequently encountered when an individual defendant says that he is not responsible for a debt but that responsibility rests with a limited company. However, there are some factors present that might suggest that on this occasion, the point may have some substance. It is a matter of interest, if no more than that, that the first shot in this litigation was fired by the first named defendant issuing proceedings by way of summary summons for an amount of approximately €600,000 in 2001 against Mr. William Smyth. These proceedings were issued at a time when the Mirella Group was a strong one and when there was no doubts about any of the companies within it, so there would have been no particular tactical advantage in pursuing Mr. Smyth personally. Now, it is the case that Mr. Smyth’s response to the proceedings was to say, inter alia, that the proper defendants in those proceedings were Paulson and AEL and that the response of the plaintiff in those proceedings was to join those companies. Nevertheless, the fact that the first instincts of the plaintiffs in those proceedings was that they had been dealing with Mr. Smyth is of interest. Counsel for the plaintiff is dismissive of the suggested defence and points to the fact that invoices were issued to AEL. However, in turn, counsel for the defendants’ points to the summary summons proceedings and the contention there, that after work had been carried out that the plaintiffs in those proceedings were asked to issue invoices to a particular company and complied with the request that was made of them. It seems to me that the point raised, while manifestly by no means guaranteed to succeed, cannot be dismissed.”
34. For my part, in assessing the question of whether Jons has established a prima facie defence that the relevant contracting party was Mr. Smyth, I consider that the identity of the person sued by Jons in the 2001 summary proceedings is at best of limited relevance. It shows at most that Jons believed that it was dealing with Mr. Smyth, rather than the plaintiff companies. The question, however, of the identity of the parties to a contract is, however, fundamentally an objective question of fact and the subjective beliefs of the parties where such matters are in dispute is rarely dispositive of the matter.

35. It must also be noted that in a replying affidavit filed in those 2001 proceedings Mr. Smyth immediately denied he was the proper defendant. If, however, an inference is nonetheless to be drawn from the fact that Jons issued proceedings against Mr. Smith on this basis - even though Mr. Smyth subsequently denied that he was the appropriate defendant - it would amount in the circumstances to a breach of the rule against narrative or, as the rule is sometimes described, the rule against self-corroboration: see McGrath, Evidence (2nd ed.) at 139.

36. Subject to certain defined exceptions, the rule against narrative prevents witnesses referring to earlier consistent statements in order to re-inforce their own credibility. In this context, the claim made by Jons in the 2001 proceedings amounts to an earlier statement that it believed that Mr. Smyth was the contracting party. In these circumstances, Jons cannot point to its earlier consistent statement with a view to bolstering its present claim that the Mr. Smyth was the appropriate defendant.

37. I think, however, that Jons can place more weight on the letter of October 2011 from McCann FitzGerald, the solicitors for the plaintiffs, which accepted the termination of the agreement between the parties. It may well be significant that this letter refers to the client as Mr. Smyth, especially as there was no written contract in the first place. The statement in this letter must, however, be viewed against the fact:

      (i) that the second plaintiff, Albert Enterprises Ltd., discharged the invoices

      and

      (ii) there was no unequivocal plea in the defence denying that the plaintiffs were the proper plaintiffs.

38. There is no doubt but that the Smyth defence point is arguable, even if it was not specifically pleaded in the defence. It is clear, however, that from the case-law that this in itself is not enough to establish a prima facie defence, since in the words of Charleton J. in Oltech, a “reasonably sustainable defence” is required for this purpose.

39. I do not think that, for the reasons just stated, the fact that Jons elected to sue Mr. Smyth (rather than the plaintiffs) is sufficient in itself to demonstrate the existence of a reasonably sustainable defence. I do think, however, the reference to Mr. Smyth as the client in the October 2011 correspondence is sufficient to establish a prima facie defence for this purpose, even if there are also powerful arguments - such as the fact that Albert Enterprises discharged the invoices - which point in the opposite direction.

40. Given the finely balanced nature of the competing arguments, I propose to return to this issue at a later stage in this judgment.

Whether Jons is responsible for the conduct of Edwards under the IEI contract
41. Clause 8(1) of the IEI contract provides that the contractor is responsible for the “methods of construction”, even it is not for design and specifications. On this basis, therefore, Jons would in principle be liable for the faulty workmanship of Edwards.

42. There is considerable evidence from the records and the report prepared by Mr. Wasilewski (on behalf of the plaintiffs) that, as I have already described, inappropriate auger withdrawals occurred. It would also appear that there were auger withdrawals on a number of occasions without back screwing. It is further accepted that this practice is inherently dangerous and so much is not really disputed by Mr. Turner, the expert retained by Jons.

43. While it is most assuredly not my wish to pronounce on the substantive merits of this complex dispute in the context of an interlocutory application of this kind save to the extent that I am perforce obliged to do so, I find it nonetheless difficult to accept that there is a prima facie defence to the claim of defective workmanship. On that basis, therefore, Jons might well be exposed to liability by virtue of Clause 8(2) of the IEI contract, even if difficult question of causation remain.

The Norta Wallpapers defence
44. So far as any defective workmanship on the part of Edwards is concerned, Jons has indicated that it proposes to rely on what might be termed the Norta Wallpapers defence.

45. In that case the Supreme Court accepted that normally a term would be implied in a building contract as between between a builder and employer making the builder liable to the employer for loss and damage suffered as a result of goods, materials or work supplied or constructed by a subcontractor not being fit for purpose. The Court nevertheless held that such a term would not be implied in that case in relation to the fitness of the design of particular roof lights in a situation where, as Henchy J. put it ([1978] I.R. 114, 125-126), Sisks (the defendant builders) were put “…in the position of being little more than ordering agents for a roof that had already been vetted and passed by Norta’s engineer.”

46. For my part, I doubt that the Norta Wallpapers defence is available to Jons having regard to the facts of this case. Norta Wallpapers was a case where the defects related to the designs in the roof lights which had been prepared by specialist sub-contractors nominated by Norta and actually approved by the employer’s engineer. There was no evidence by which it might be inferred that Norta relied on Sisks to detect any flaw in the design of the roof lights. But even here Henchy J. suggested that the general contractor remains responsible to the employer for the poor workmanship of the specialist sub-contractor: see [1978] I.R. 114, 126.

47. One may accept that Jons probably knew nothing about CFA methods and were simply passive onlookers so far as the choice of specialist piling techniques employed by Edwards were concerned. But Jons nonetheless accepted the contract knowing that there would be a specialist contractor using such methods. In contrast to the position in Norta Wallpapers, there is no evidence to suggest that either the plaintiffs or its engineer, Hendricks Ryan, had ever actively approved the use of the CFA piling technique. This, after all, had been first suggested by Edwards in their cover letter of 17th July 2000 when they had qualified their tender by saying that they proposed to use CFA bored piles, subject only to test boring.

48. In any event, it is clear from Norta Wallpapers that the builder remains responsible to the employer for the poor workmanship of the sub-contractor. As I think that there is clear evidence of such poor workmanship on the part of Edwards (a topic dealt with elsewhere in this judgment), I do not think that it can be said that Jons has established a prima facie defence qua builder under this heading.

The unanticipated grounds defence
49. Jons maintains that it was not guilty of negligence or breach of contract, contending that it carried out the relevant works in accordance with the specifications of Hendricks Ryan (the plaintiffs’ engineer). It argues that in accordance with Clause 8(1) of the IEI contract, Hendricks Ryan were responsible for the design and specification of any such permanent works. There is, indeed, an issue as to whether the works at issue - namely, the secant pile wall - were intended to be permanent within the meaning of that clause and whether they would have remained part of the permanent structures.

50. Jons further contends that some of the piles on the secant pile wall were intended to be load-bearing (and, hence, permanent structures), whereas the support structure utilised following the construction of the secant wall were simply the temporary works. Jons then maintains that the defendants encountered ground conditions which were not reasonably foreseeable. These unfavourable ground conditions produced an unexpected degree of settlement and neither the plaintiffs nor Hendricks Ryan instructed it as to how the physical conditions of the site were to be dealt with such that the piling could be carried on with the meaning of Clause 12(1) of the IEI contract.

51. It thus summarises its case by saying that these adverse physical conditions rendered it physically impossible (within the meaning of Clause 13 of the IEI contract) for Jons to carry the works in accordance with the specifications of the plaintiffs’ engineers and that in accordance with Clause 13 it stands discharged of any liability: the settlement and the consequent damage were caused by the unforeseen grounds conditions.

52. In this respect it should be noted that the plaintiffs have placed great significance on one aspect of the report of Mr. Luby of SLR Global Environment Solutions (“SLR”). Mr. Luby concluded that the ground conditions on site were not unforeseen and the plaintiffs contend that that conclusion has not been contradicted. Accordingly, the plaintiffs say that the entire substructure of the defendants’ defence falls away in its entirety. In his report, Mr. Luby stated:

      “The construction of the bored pile foundations for the existing mixed use scheme in late 2002 and early 2003 did not encounter or reveal any unexpected characteristics of the natural ground. The ground conditions encountered during the piling contract were similar to those described in the original ground Investigation reports. The weight of available evidence therefore indicates that there is no basis for any contractual claims in relation to unforeseen ground conditions at this site.”
53. While it is true that the defendants did not, in terms, produce evidence which contradicted Mr. Luby’s report, they did nonetheless challenge the weight which these observations should carry. They argued that Mr. Luby’s conclusions were based on what was subsequently encountered during the work on a very different development which omitted the three basement floors. It is true that Mr. Luby was present for the second development and offered geotechnical advice in relation to it, but he was not present at the time when Jons first took possession of the site in September 2000 or when Edwards commenced piling in February 2001.

54. In this respect the question of the ground conditions actually encountered by Edwards and how that compared with what had been expected having regard to site investigations carried out on behalf of the plaintiffs before the involvement of either of the defendants remains central. The defendants’ case is that the initial specifications stipulated by Hendrick Ryan, and the relaxed tolerances to which they were prepared to agree, could not have been achieved having regard to the prevailing ground conditions which they actually encountered.

55. It might further be noted that the reports prepared by Jons’ expert, Mr. Turner, are critical of the site investigations carried out between September and November 2009 by Site Investigations Ltd. (“SIL”). These investigations were carried out by SIL on the instructions of Hendrick Ryan. Mr. Turner concluded that it was likely that the alluvial sandy soil found on the site was denser and more compact than the site investigations reports prepared by SIL suggested. Mr. Turner pointed out that site investigations on a nearby site at Laurence Street, Drogheda, recorded the presence of what he describes as dense conditions. If this were correct, then it would follow that such denser conditions would require more effort to drill than had been anticipated.

56. This is another example of a hugely complex issue in respect of which Jons can establish a reasonably sustainable defence. But the matter is finely balanced, because it could equally be said that the plaintiffs have by the same token established a reasonably sustainable cause of action. After all, the plaintiffs can argue with some force that if Jons wanted to advance this unforeseen ground conditions defence, there would have to be evidence of a notice under clause 12(1) of the IEI contract passing the responsibility on to the plaintiffs’ nominated engineer, namely, Hendricks Ryan.

57. As Birmingham J. recognised:

      “Insofar as there is disagreement between the experts, this is a matter that requires to be explored through oral evidence and cross-examination. It is not a matter that can be resolved by identifying selected extracts from reports.”
58. Just as with the Smyth defence argument, I propose to return later to this issue.

The position of Edwards
59. As I mentioned already, there is a good deal of evidence of poor workmanship on the part of Edwards. By its own admission it did not conduct the test boring which it had previously suggested might be necessary. It would also appear that the computerised on-board instrumentation on the Llamada rig was either not functioning or was not used properly on the first day of boring on 6th February 2001. No report sheets were kept in respect of the “slumping” of one of the secant piles. Within a few days of commencing boring Edwards notified Jons, Hendricks Ryan and the plaintiff companies on 12th February 2001 of the existence of an open borehole. It now appears that there were apparently in total over 30 such open boreholes.

60. In these circumstances, it would be hard to accept that Edwards has established a prima facie case that it was not negligent. Independently of that question, however, it has argued that if it was negligent, any losses suffered by the plaintiffs amounted to pure economic loss in that there was no damage to person or property. It contends, however, that it owed no duty of care to avoid pure economic loss based on decisions such as that of the English Court of Appeal in Robinson v. PE Jones (Contractors) Ltd. [2011] EWCA Civ 9, [2011] 3 WLR 815. There are also questions of causation.

61. It is long been settled law that a builder owes a duty of care by reference to the law of negligence to protect the owner (and other persons who either acquire the property or who use it) from suffering personal injury or damage to other property. The extent to which (if at all) the builder owes a wider duty is a more complex issue. Specifically, does the builder owe a duty of care to avoid building defects which do not cause either personal injury or damage to other property?

62. There is no doubt but that the Supreme Court has previously decided that there are cases where such liability in tort might be imposed: see, e.g., Siney v. Dublin Corporation [1980] I.R. 400 and Ward v. McMaster [1988] IESC 3, [1988] I.R. 337. These decisions were clearly influenced by earlier parallel developments in the UK in leading cases such as Anns v. Merton L.B.C. [1978] AC 728 and Junior Books Ltd. v. Veitchi Co. Ltd. [1983] 1 AC 520.

63. There then began in the UK a long retreat from the decisions in Anns and Junior Books, beginning with the House of Lords decision in Murphy v. Brentwood District Council [1991] 1 AC 398 to the point where these earlier decisions permitting recovery in negligence for pure economic loss in a building context are now regarded, in the words of Stanley Burnton L.J. in Robinson, as “aberrant” and “heretical”. In the course of that retreat, the English judges have stressed the distinct and different nature of contractual obligations (which are consensually assumed) as compared with those obligations which are imposed by the law of tort (i.e., independently of contract or consent). On that basis, as both Jackson L.J. and Stanley Burnton L.J. stressed in their respective judgments in Robinson, the English courts now take the view that while these obligations overlap, there is a difference as to the extent of the obligations in both tort and contract.

64. It was precisely for those reasons that the English Court of Appeal concluded in Robinson that a homeowner could not recover in tort against the builder in respect of defective chimney flues as these defects had caused neither damage to person or to other property.

65. As matters stand in this jurisdiction it is not clear whether a property owner can recover for pure economic loss of this kind, the decisions in Siney and Ward v. McMaster notwithstanding. This was the very issue which the Supreme Court left open in Glencar Exploration plc v. Mayo County Council [2002] IESC 64, [2002] 1 IR 112, although it must be said that in his judgment, Keane C.J. (with whom the other members of the Court agreed) appeared to doubt the correctness of the expansive approach which had been taken in cases such as Siney and Ward.

66. The extent to which the duty of care imposed by the law of tort imposes a duty on builders to avoid pure economic loss is, as least so far as the law in this jurisdiction is concerned, a difficult one. As Birmingham J. himself recognised, it would not be appropriate to resolve this issue in the context of assessing whether a particular defendant has established a prima facie case. There is, in any event, the question of whether the “slumping” of one of the concrete piles amounts to damage to other property within the meaning of the test articulated in cases such as Robinson and, if so, whether this was causative of the losses suffered by the plaintiffs.

67. In my view, I am not persuaded on the evidence presently available to the court that, for the reasons already set out elsewhere in this judgment, Edwards have established a prima facie defence so far as the question of workmanship is concerned. I do think, however, that the legal issues arising under this heading (namely, the extent of the duty of care and whether there was, in any event, damage to other property and associated questions of causation) are open and finely-balanced.

Overall conclusions
68. I accept that a good deal of the case-law to date has approached the question of whether security for costs should be ordered has been approached almost on a binary basis (namely, whether the defendant has established a prima facie defence or otherwise). Given the special features of the present litigation, however, I do not think the interests of justice would be best served by adopting this approach in the context of complex multi-party litigation such as this which presents intricate issues of fact and law where in respect of many (albeit not all) of these issues the plaintiffs and defendants alike have presented what at least on a superficial analysis appear to be prima facie claims and defences to those claims.

69. Pulling all of these different threads together, it can be said that in some instances the disparate issues arising in this appeal are so complex (both in terms of fact and, in some instances, law) that it would really be well nigh impossible to assess fairly whether there was in truth a prima facie defence without the kind of detailed examination and analysis of the merits of these defences against which the courts have traditionally set their face in applications of this kind: see, e.g., the comments of Mahon J. in CMC Medical (already referred to) and those of Clarke J. in Parolen Ltd. v. Doherty, High Court, 12th March 2010.

70. In addition, however, there have also been important issues resolved adversely to the defendants. Contrary to the views expressed (albeit with apparent hesitation) by Birmingham J. in the High Court, I think, for example, that the undisputed weight of evidence is such that there is really no prima facie defence to the claim of poor workmanship on the part of Edwards, even if it does not follow from that conclusion that the plaintiffs’ claim in negligence against that defendant will necessarily succeed in view of the issues of recovery and pure economic loss and causation which will also arise. For the reasons already stated, I do not think that Jons can accordingly raise the Norta Wallpapers defence qua builder.

71. The Court is also entitled to have regard to the fact that the plaintiffs have already lodged the sum of €500,000 to the credit of the action. While this sum is less than the estimated costs of the defendants, it is nonetheless a significant sum which will help to provide some comfort to the defendants.

72. In my view, it is the very complex nature of the litigation which makes an assessment of whether there is in fact a prima facie defence so difficult without a detailed, merits-analysis of each claim of the kind normally avoided in applications of this kind is itself a special circumstance for the purposes of s. 390 of the 1963 Act. Even then, in some instances, I have found myself obliged to conclude that no prima facie defence has been established, e.g., in relation to the poor workmanship in respect of the auger withdrawals on the part of Edwards with the consequent implications for Jons in respect of its Norta Wallpapers defence.

73. For this purpose, the categories of special circumstances are not closed: see the judgments of Denham and Geoghegan JJ. to this effect in West Donegal Land League v. Údarás na Gaeltachta [2006] IESC 26, [2007] 1 ILRM 1.

74. In my view, the unusual circumstances of this case in themselves constitute special circumstances. These features are:

      (i) that the defendants have failed to establish a prima facie defence in respect of key defences (or aspects of such defences) advanced by them;

      (ii) the unusual complexity of the legal and factual issues in the case which makes the ascertainment in an interlocutory application of whether there is in fact a prima facie defence in respect of the remaining defences very difficult and all but impossible;

      (iii) the lodgement of a substantial sum (€500,000) by the plaintiffs (representing perhaps one third of the combined costs of the defendants).

75. In the light of these conclusions it is unnecessary for me to express any view on the inter-action of the right to order security under s. 390 of the 1963 Act and the plaintiff companies’ constitutional right of access to the courts. I nevertheless adhere to the views I have already expressed on this topic in my judgment in CMC Medical Operations.

76. In these circumstances, I would accordingly allow the appeal and I refuse to make an order for costs pursuant to s. 390 of the 1963 Act.


BAILII: Copyright Policy | Disclaimers | Privacy Policy | Feedback | Donate to BAILII
URL: http://www.bailii.org/ie/cases/IECA/2016/CA169.html