BAILII [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback]

High Court of Ireland Decisions


You are here: BAILII >> Databases >> High Court of Ireland Decisions >> Dekra Erin Teoranta v. Minister for the Environment and Local Government [2001] IEHC 154; [2002] 2 ILRM 30 (2nd November, 2001)
URL: http://www.bailii.org/ie/cases/IEHC/2001/154.html
Cite as: [2002] 2 ILRM 30, [2001] IEHC 154

[New search] [Printable RTF version] [Help]


Dekra Erin Teoranta v. Minister for the Environment and Local Government [2001] IEHC 154; [2002] 2 ILRM 30 (2nd November, 2001)

THE HIGH COURT
1999 No. 114 JR
IN THE MATTER OF THE EUROPEAN COMMUNITIES (REVIEW PROCEDURES FOR THE AWARD OF PUBLIC SUPPLY, PUBLIC WORKS AND PUBLIC SERVICE CONTRACTS) (2) REGULATIONS 1994
AND
IN THE MATTER OF ORDER 84 OF THE RULES OF THE SUPERIOR COURTS 1986 AS AMENDED
BETWEEN
DEKRA ERIN TEORANTA
APPLICANT
AND
THE MINISTER FOR THE ENVIRONMENT AND LOCAL GOVERNMENT
RESPONDENT
AND
S.G.S. IRELAND LIMITED
NOTICE PARTY
Judgment of Mr Justice O’Neill delivered the 2nd day of November 2001

1. By a Notice of Motion dated the 15th of June 1999, the Notice Party (hereinafter referred to as “S.G.S.”) seeks to have these Judicial Review proceedings struck out in limine due to the applicant’s failure to comply with the three month time limit prescribed in Order 84 A RSC 1986 or in the alternative due to the applicant’s inordinate and inexcusable delay in instituting these proceedings. These Judicial Review proceedings were initiated following on the respondents decision to award a contract to S.G.S. for the establishment and operation of a system for testing private cars in Ireland. The applicant (hereinafter referred to as “Dekra”), was an unsuccessful tenderer for this contract and had been informed by the respondent that it was ranked second to S.G.S. on the criteria set out in the invitation to tender.

THE PARTIES

2. Dekra is a joint venture vehicle of Dekra International S.A. C.I.E. and the Society of the Irish Motor Industry (“S.I.M.I.”) and was established to seek the National Car Testing contract. It was one of the parties that submitted a request for qualification to the respondent but did not succeed in winning the contract. The respondent awarded the contract to S.G.S. and supports S.G.S. in this Motion. S.G.S. also submitted a request for qualification to the respondent and was successful in winning the contract. S.G.S. is the moving party in this Motion.


BACKGROUND

3. E.U. Directive No. 96/96 O.J. No. L46, dated 17th of February 1996 requires Member States of the Union to introduce a system of periodic testing of the road worthiness of motor vehicles. In compliance with this Directive on the 31st of March 1998, the Irish Government launched the tendering process with the publication both in the Irish National Newspapers and in the Official Journal of the European Communities of a notice relating to the award of a contract to establish and operate such a system. On the 7th of July 1998, the applicant was one of the five undertakings invited by the respondent to submit tenders. This invitation, which stated that the target date for the award of the contract was the 11th of December 1998 was accepted by Dekra before the deadline of the 27th of September 1998.

4. On the 23rd of November 1998, following the submission of a report to the Minister, the respondent contends that a decision was made to award the contract to S.G.S.. The following day the 24th of November 1998, Dekra and the other unsuccessful tenderers were informed both verbally and in writing that “subject to contract” the tender of S.G.S. would be accepted. On the 8th of December 1998, a “debriefing” meeting was held between the representatives of Dekra and the respondent. On the 14th of December 1998, the respondent informed Dekra that the formal announcement of the award of the contract would take place the following day. Having learned from other sources that S.G.S.’s proposed re-test fee was substantially in excess of its own, Dekra through its solicitor wrote to the respondents raising this issue inter alia . Not being satisfied with the response of the respondent Dekra in another letter of the same date put the respondent on notice of its intention to seek injunctive relief unless the respondent refrained from awarding the contract to S.G.S.. A further meeting was held that evening between the representatives of Dekra and the respondent and it was agreed between these parties to meet again in order to provide a more comprehensive debriefing to Dekra. However the respondent subsequently by letter of the 5th of January 1999 informed Dekra that it did not consider further discussions on the subject appropriate.

5. On the 15th of December 1998, the award of the contract to S.G.S. was announced at a public ceremony and was signed by the respondent and a representative of S.G.S. Between then and the institution of these proceedings on the 25th of March 1999 there was an exchange of a number of letters between Dekra and the respondent. In this correspondence Dekra sought reasons for the respondent’s decision and clarification on a number of issues. Dekra contends that the responses received from the respondent were inadequate and did not deal with many of the queries raised.

6. On the 25th of March 1999 Dekra issued these Judicial Review proceedings.


Submissions of S.G.S.

7. S.G.S. identifies the following issues as necessarily arising on this Motion:


(a) Date on Which Time Begins to Run for the Purposes of Order 84(a) Rule 4

8. On the first of these issues namely the date from which time runs S.G.S. make the following submissions:-

  1. On the 24th of November 1998, the respondent made a decision to award the contract to S.G.S. and this decision was communicated to Dekra. This decision was a “decision to award” within the meaning of Order 84(a) Rule 4 and accordingly time started to run from that date.
  2. Even if it were to be accepted that as was averred to and contended by Dekra that a decision had been made to award the contract to S.G.S. Ireland on the 15th of December 1998, the time accordingly began to run from the 15th of December 1998 thus on any view S.G.S. submit that the time began to run for the purposes of Order 84(a) Rule 4 at the latest from the 15th of December 1998.

(b) Whether Proceedings Initiated Within the Three Month Time Limit

9. S.G.S. submitted that on any view of when time began to run, the time limits stipulated in Order 84(A) Rule 4 RSC 1986 had not been complied with by Dekra.


(c) Whether “Good Reason” for an Extension of Time Shown
  1. S.G.S. cites the case of O’Donnell v. Dun Laoghaire Corporation [1991] ILRM 301 and submits following the principles elucidated in the Judgment of Costello J. as he then was, in that case, that it was necessary for Dekra in order to obtain an extension of time to both explain and justify the delay and that the test to be applied was an objective one.
  2. S.G.S. point out that although (a) Dr Bogk admitted in his Affidavit of the 5th of July 1999 that he was aware of the decision to award the contract on the 24th of November 1998, (b) that various debriefing sessions took place and (c) a threat of immediate legal action was made on the 14th of December 1998, no satisfactory explanation has been given by Dekra as to why nothing was done to initiate proceedings until the 25th of March 1999. In particular S.G.S. contend that the explanations proffered by Dr Bogk, to the effect that Dekra did not know that the contract had been executed on the 15th of December, and that it required answers to the queries raised in the correspondence and the clarifications sought in that correspondence, do not satisfactorily explain why proceedings were not initiated promptly and in any event within the three month period. S.G.S. query why Dekra was sufficiently concerned to threaten immediate proceedings on the 14th of December 1998 but yet did nothing to initiate proceedings until the 25th of March 1999.
  3. S.G.S. submit that the delay could not be justified having regard to the substantial expense which necessarily would have to be and was incurred and the extensive obligations undertaken by S.G.S., all of which was known to Dekra. In this regard it cites the case of the State (Cussen) v. Brennan [1981] IR 181 to support its submission that there was a necessity for speed and expedition in circumstances as in this case where third parties such as S.G.S. had acquired rights as a result of the administrative decision taken by the respondent. Relying upon Cussen, S.G.S. submits that Dekra had “good reasons to believe” that it was not going to be awarded the contract as early as the 24th of November, that it is a factor which the court should have regard to even if it concludes that the time began to run from the 15th December 1998.
  4. S.G.S. submit, moreover, that the range of third party rights involved in this case is somewhat greater than arose in the Cussen case, having regard to the extent of expenditure, staff recruitment, site acquisition all of which had to be undertaken by S.G.S. in order to set up the network of test centres throughout Ireland.
  5. Acknowledging that Dekra has confined its claim to damages nonetheless S.G.S. submit that such a claim can only succeed if it is established that the award of the contract itself was invalid, and S.G.S. has a vital interest in establishing that the contract was not invalidly awarded and in this regard S.G.S. referred to a passage from the judgment of Buxton LJ in the case of Matra Communications SAS v. Home Office [1999] 3 All ER 562, 576 where the learned judge there describes the unsettling and disrupting effect of a claim even limited to damages and hence the necessity to ensure in the public interest that such claims are made promptly, a necessity underlined by the emphasis on speedy redress in E.U. Directive 89/665 itself.

(d) Whether Dekra Applied Promptly

10. S.G.S. submits that the obligation of Order 84(a) is to apply “at the earliest opportunity” and that this obligation arises independently of the three month time limit. S.G.S. submits that Dekra had such an opportunity in December 1998 but for reasons which have not been adequately explained this opportunity was not availed of and hence Dekra failed to comply with the requirement in Order 84(a) Rule 4 to make the review application “at the earliest opportunity”.


(e) Whether Order 84(a) Rule 4 RSC 1986 is Ultra Vires
  1. Here S.G.S. deals with Dekra’s claim that Order 84(a) Rule 4 is ultra vires the Superior Court Rules Committee on the basis that it infringes the principle that remedies available in Irish law including limitation periods must respect (a) the principle of equivalence and (b) the principle of effectiveness. In this regard S.G.S. refer to a passage from the judgments of the Court of Justice in the case Palmisani v. Instituto Nazionale Della Previdenza Socialiale (case C-261/95 [1997]) E.C.R.1-4025 where it is stated that time limits for reparation or loss for damage laid down by a national law must be not less favourable than those in relation to similar domestic claims (principle of equivalence) and must not be so framed as to make it virtually impossible or excessively difficult to obtain reparation. (Principle of effectiveness)
  2. S.G.S. submits that these principles apply only to Dekra’s claim for loss and damages arising out of a breach of a direct effective community law right i.e. Francovich damages. These principles do not apply to their claim which derives from domestic law i.e. claims for breach of statutory duty or in respect of constitutional rights.
  3. S.G.S. submits that the comparator cannot be with respect to claims for damages for breach of other directly effective community rights as it must be concerned with similar rights derived wholly from domestic law, and in this regard S.G.S. referred the case of the Levez v. TH Jennings (Harlowe Pools) Limited (case C326/96 [1999] All ER (E.C.)1, [1998] E.C.R. 1-7835).
  4. S.G.S. submitted that if there was no true domestic comparator then the national legal system was at liberty subject to the principle of effectiveness to set whatever limitation period seemed best for the claim in relation to community rights. In the Matra case the vires of a three month limitation period for applications for review of public service contracts was upheld, the court taking the view that there was no true comparator under English law. Specifically the Court of Appeal rejected a comparison with actions for breach of statutory duty as being “too wide”. Relying on this aspect of a judgment in the Matra case S.G.S. submitted that there was no appropriate comparison under Irish law that met the Palmisani test of equivalence and therefore there was no impediment to a three month limitation period.
  5. S.G.S. submitted that it was almost impossible to envisage how Order 84(a) Rule 4 RSC 1986 could be attacked on the basis that it infringed the principle of effectiveness. In this regard S.G.S. relies on the fact that the English Court of Appeal in the Matra case came to a similar view in respect of the relevant English Rule which is in almost identical terms to Order 84(a) Rule 4.

SUBMISSIONS OF THE RESPONDENT

11. The respondent fully supported the submissions of S.G.S. and made the following additional submissions:-

(a) Order 84(a)
  1. The respondent points to a number of special features of Order 84(A) RSC 1986 as follows:

(b) The Limitation Period
1. The respondent firstly noted the principle that limitation periods are in fact compatible with European Community Law and in this regard refers to the case of Fantask A/S v. Industriaminsteriet (case C-188/85 [1998] All ER (EC) 1, [1997] ECR I -6783.
2. The respondent submits that time began to run from the 24th of November 1998 when the applicant was informed of the decision to award the contract to S.G.S.. The respondent submits that the decision to award the contract as notified both verbally and in writing to the applicant on the 24th of November 1998 was a decision within the meaning of the Review Procedures Directives and Implementing Regulations.
3. Therefore, the respondent submits that the initiation of proceedings was in excess of four months from the decision to award a contract and in excess of three months from its signing. And referring to the case of Alcatel Austria AG v. Bundesministerium Fur Wissenschaft und Verkehr (case C-81/98 E.C.J. 28th October 1999), submitted that the point in time at which the award of a public contract is made is of decisive importance for the review procedure.
4. Moreover by virtue of the principle laid down in Finnerty v. The Western Health Board (Unreported High Court, Carroll J. 5th October 1998), the signing of the contract of December 1998 was a mere reiteration of the decision to award the contract on the 24th of November 1998.
5. The respondent observes that Dekra in its Notice of Motion and Grounding Statement acknowledged the delay and seeks an Order extending the time for the making of its application.

(c) Applicant “at the earliest opportunity”
  1. The respondent submits that when the applicant wrote to the Minister on the 14th of December 1998 he had an early opportunity to apply for review but nevertheless failed to avail of this opportunity and is thus disentitled from utilising the procedure.
  2. The respondent submits that Order 84(a) Rule 4 places on a person seeking a review pursuant to the Order an obligation to make the application “at the earliest opportunity”, and that the jurisdiction to extend the three month period only arises where “the earliest opportunity” arises after the expiration of the three month period from when the grounds for the application first arose. Thus only in circumstances where an applicant did not have an opportunity within the three month period, whether because of ignorance of the existence of grounds or for some other reason depriving the applicant of an opportunity to make application, can the three month period be extended were good reasons are shown. The converse of this is that where an applicant did have an opportunity to apply within the 3 months but failed to avail of it the respondent submits that the court in that circumstance cannot extend the time limit.
  3. The respondent points to the change of wording from “promptly” in Order 84 Rule 21 to “at the earliest opportunity” in Order 84(a) Rule 4 and submits that this change implies a more stringent obligation on the part of the applicant to act with greater speed.

(d) No Good Reason for Extending the Three Month Period
  1. The respondent submits that Order 84(a) while allowing for the extension of the three month period where “there is good reason” does not provide for an extension of time in relation to the requirement to “act at the earliest opportunity”. As the earliest opportunity was within the three month period the respondent submits that there is no justification for an extension.
  2. The respondent places reliance on the case of O’Donnell v. Dun Laoghaire Corporation (2) [1991] ILRM 301, and submits that Dekra has offered no reasonable explanation or justifiable excuse for the delay. The respondent submits that there was not any objective basis for the delay in the institution of proceedings after the preliminary step was taken on the 14th of December i.e. the threat to instigate such proceedings. The respondent submits that all material knowledge necessary to ground the application was available to the respondent in and around the time that the initial threat was made. The respondent points to the fact that Dekra’s grievance centred on three things namely the level of re-test fees, the location of test centres and alleged bias and the respondent points to paragraphs 11, 15 and 16 of the Affidavit of Dr Bogk dated the 22nd of March 1999 to support his contention that Dekra had all the necessary information at the material time and that there was therefore no lack of information which could justify delaying the institution of proceedings after the 15th or 16th of December 1998.
  3. The respondent further points out that any further information that was necessary could have been obtained in the context of discovery and interrogatories which are expressly provided for in Order 84(a). Dekra’s suggestion that it was not possible to start proceedings prior to the completion of full discovery would render the entire review procedure unworkable and run counter to the essential purpose of the E.C.’s Review Procedure Directives and the Implementing Regulations, that the award of public contracts be reviewed in as expeditious manner as possible.

(2) Acquired Rights and Prejudice to Notice Party

12. The respondent points to the fact that upon the signing of the contract that S.G.S. would have acquired rights and obligations and undertaken investment and expenditure which would have been well known to Dekra and in delaying instituting proceedings Dekra created a situation in which S.G.S. potentially acted to its detriment in perhaps incurring great losses.


(3) Public Interest and Prejudice to the respondent
  1. The respondent submits that to allow an application for the review of public contract outside the specified time period will prejudice the orderly administration of public tenders and lead to a bureaucratic nightmare for the respondent and other government departments and public bodies implementing public tenders and would not be in accordance with the principle of legal certainty. In this regard it was pointed out that there are several hundred of these contracts ongoing and that to permit reviews of these contracts outside of the three month time limit would place an impossible burden on government departments and other public bodies and lead to wholly undesirable uncertainty over the status of contracts awarded and lead to long delays in carrying out public projects all of which is contrary to the public interest. The respondent further submits that the public interest is a matter which should be taken into account.
  2. The respondent rejects Dekra’s contention that as it is not seeking to set aside the contract no prejudice results to the respondent. The respondent submits that in order for damages to be awarded to Dekra it would first be necessary to declare the decision awarding the contract to be unlawful. This in turn the respondent submits, would render the contract between the respondent and S.G.S. unenforceable or at the very least create uncertainty as to the status of this contract as a consequence of which the respondent and S.G.S. would be prejudiced. The respondents point out that a situation such as this would lead to a serious loss of public confidence in the system for car testing and in particular, that S.G.S. would properly carry out this function and this in turn would lead to considerable problems for both S.G.S. and the respondent.
  3. The respondent contends that they would be doubly prejudiced were an extension of time granted as both the validity of the decision to award a contract would be an issue and the claim for damages also maintained.
  4. The respondent submits that in delaying instituting their proceedings Dekra deprived the respondent of the opportunity to take an alternative course such as by suspending the award of the contract and having the issue sought to be raised in these proceedings litigated before either the respondent or S.G.S. were committed to the obligations of the contract.
  5. The respondent points to the fact that Ireland has already been the subject of infringement proceedings brought by the European Commission for the non-transposition of E.U. Directive 91/328/E.C. consolidated in E.U. Directive 96/96/E.C.. The respondent is anxious to implement these provisions in order to avoid further proceedings and incurring further damage to Ireland reputation in relation to the implementation of E.U. Directives.
  6. The applicant further submits that as a result in his institution of the proceedings and the ambiguity in Dekra’s Notice of Motion commencing the proceedings as to the reliefs sought, that the respondent was unable to proceed as had been planned to select a supervisor/agent to assist the respondent in monitoring and evaluating the N.C.T.’s service against a range of specified standards as is required under Article 2 of E.U. Directive 96/96/E.C. The respondent’s submission in this regard is to the effect that the competition to appoint a permanent supervisor could not begin until Dekra decided not to seek a setting aside of the contract, a fact which was not communicated to the respondents until the 23rd of June 1999, as until then it could not be assumed with safety that the contract would be held to be valid. The respondent acknowledges that whilst Dekra’s Notice of Motion did not expressly seek annulment of the contract, the respondent believed that due to the ambiguity in the Notice of Motion particularly in relation to the reliefs that would be sought, were it to be found that the application was brought in time, that the contract was thus in jeopardy. The respondent submits that the time period for the submission of tenders was such that the respondent could not appoint a supervisor within the designated time and thus it was necessary to appoint a short term supervisor to serve from September 1999 until June 2000. The ultimate effect of Dekra’s delay, the respondent submits, was that the respondent could not with confidence appoint a supervisor/agent sufficiently early to make the optimum contribution to the successful mobilisation of the N.C.T.’s, and that the respondent incurred extra cost by being forced to run two separate procurement competitions.

(4) The applicant contends that Dekra acquiesced in the signing and implementation of the contract by failing to act with due expedition in the initiation of these proceedings knowing that the respondent and S.G.S. were on the 15th of December going to execute the contract. The respondent thus submits that the applicant is now estopped from seeking an extension of time.

13. The respondent submits that there are no constitutional issues arising which would justify an extension of time and it submits that the delay on the part of Dekra in initiating the proceedings was in all the circumstances unconscionable and hence there is no good reason to extend the time.


(c) The applicant’s failure to make full disclosure in its Statement and Grounding Affidavit
  1. In the Grounding Affidavit Dr Bogk states inter alia :-
“The respondent decided to award the contract to S.G.S. Ireland Ltd. (S.G.S. Ireland) on the 15th of December 1998. The applicant is unaware of the date of execution of the contract between the respondent and S.G.S. Ireland which it submits is the date of the award of the contract. Dekra International S.A., the principle shareholder in the applicant has requested this information from the respondent.”
  1. The respondent submits that these averments are materially deficient, misleading and in breach of the principle of good faith for the following reasons:
(a) the applicant was informed of the decision to award the contract to the Notice Party on the 24th of November 1998.
(b) the applicant was informed of the date of signing or execution of the contract on the 15th of December 1998.
(c) the provisions of the terms of the contract were available to all tenderers in the invitation to tender document and draft contract which clearly specifies that the car testing system had to be put in place by 4th of January 2000 and that measures had to be put in place in 1999 to ensure that this start-up date for testing would be achieved.

14. The respondent therefore submits that there was no ambiguity as to the date of the decision to award the contract, the date of its signing or the provisions for its implementation.

  1. The respondent points to paragraphs 17 and 18 of the Grounding Affidavit of Dr Bogk sworn on the 22nd of March 1999 in which it is alleged that the contract would not have been executed until January 1999 at the earliest, that the grounds for this application would have arisen only then and that the respondent had been aware of the applicant’s concerns since the correspondence of the 14th of December 1998.
  2. This Affidavit of Dr Bogk, the Minister submits, is less than a full and frank disclosure of the information available to the applicant at the material time, is intentionally selective, designed to obfuscate the facts and mislead the court as to the true knowledge of the applicant concerning the date of the decision to award the contract to the Notice Party and the date of execution of the contract. In particular the Minister submits that there was a failure on the part of Dekra to:
(a) disclose the notification by telephone to it by Mr Des Coppens for the respondent on the 24th of November 1998 of the decision to award the contract.
(b) exhibit the letter of the 24th of November 1998 notifying the decision to Dekra. This however Dekra did acknowledge, in Dr Bogk’s second Affidavit sworn on the 5th of July 1999.
(c) mention the debriefing meeting which took place on the 8th of December 1998, in the body of the Affidavit notwithstanding that exhibit “D.B. 7” of the said Affidavit i.e. a letter from the respondent, clearly reveals that this meeting took place and that the respondent had at that meeting not only informed the applicant of the decision to award the contract to the Notice Party but also to disclose the reason why such a decision was made.
(d) exhibit the full set of correspondence of the 14th of December 1998 exchanged between Dekra and the respondent.
  1. Moreover it is submitted by the respondent that Dekra has not complied with Order 84(a) Rule 3(x) of the R.S.C. 1986 which requires Dekra to specify the date of notification of the alleged infringement. Dekra failed to specify the 14th of December 1998 notwithstanding that it had sent a letter to the respondent on that date threatening legal proceedings.

(f) Abuse of Process

15. The respondent submits that in commencing the review procedure by a letter of the 14th of December 1998 threatening legal proceedings yet failing to “prosecute” the action for an excess of three months is an abuse of process. The respondent submits that this is especially so having regard to the applicant’s knowledge at all material times of the date of the decision to award the contract, of his rights and remedies and of the inevitable resulting prejudice to S.G.S. and the respondent. As the tardy prosecution induced the respondent and S.G.S. to act to their detriment the court is asked that the applicant do not benefit from such abuse of process and for this reason alone the proceedings should be dismissed in limine .


Principle of Equivalence

16. The respondent adopts the arguments and submissions of S.G.S. on this issue


SUBMISSIONS OF DEKRA

17. Dekra’s submissions raise a number of issues as follow:-

(a) Locus standi
(b) the date of the impugned decision
(c) extension of the three month time limit
(d) Teleological Approach to interpretation of Order 84 A Rule 4 (e), three month time limit contrary to European Community Law.
(a) Locus Standi .

18. Dekra submits that S.G.S. has no standing to make the present application as no relief is being sought against it and as a consequence these proceedings cannot cause it to suffer any injury or prejudice. S.G.S. has no interest which a court could recognise which is injured or affected by these proceedings.

19. Moreover the applicant relies on the dicta of O’Higgins C. J. in Norris v. The Attorney General [1984] IR 36, 58 for the purpose of submitting that S.G.S. is relying on a jus tertii as it seeks to rely on the rights of the respondent.

(b) The date of the impugned decision.
1 Dekra concedes that the grounds giving rise to the application arose on the 15th December 1998, the date of the signing of the contract which it claims is the date of the award of the contract for the purposes of Order 84 A. Dekra concedes that time ran from the 15th December 1998 and expired on the 15th March 1999, for the purposes of Order 84 A Rule 4.
2 Dekra refutes the contention of both S.G.S. and the respondent that the operative date from which time ran was the 24th November 1998, on the grounds that the decision notified as of that date was “subject to contract”, and having regard to the fact that the contract was already included with the tender documents and was not open to negotiation, hence none of its terms was yet to be settled, thus the phrase “subject to contract” in this context could only have been reasonably understood as meaning that there had been no final decision to award the contract to S.G.S..
(c) Extension of the three month time limit
1 Dekra draws attention to the similar phrasing used in Order 84 A and that in Order 84 Rule 21 (1) R.S.C. 1986. While noting that to date there has been no case law regarding Order 84 A the matter allows for a similar extension of time for good reason and that there has been a number of cases dealing with this in Order 84 Rule 21(1). Here Dekra refers to O’Donnell v. Dun Laoghaire Corporation [1991] ILRM 301 and O'Flynn v. Midwestern Health Board [1991] 2 IR 223.
2 Dekra also placed reliance on the English case of Keymed (Medical) and Industrial Equipment Ltd. v. Forest Health Care NHS Trust unreported High Court Queen’s Bench Division, Langley J. 17th November 1997. Dekra submitted that this court should apply the principles which were set out in this case. Specifically that the relevant considerations for the exercise of the court’s discretion as to whether or not to extend time were as follows:-
(i) The length of and reasons for any delay;
(ii) The extent to which the plaintiff was to blame for any delay;
(iii) The extent to which the defendant might have induced or contributed to the delay;
(iv) Whether the defendant had been or would be prejudiced by the delay or the grant of an extension.

20. Adopting the foregoing criteria Dekra made the following submissions.

(1) Length of Delay

21. Dekra accepted that the date of the award of the contract was the 15th December 1998 and for the purposes of Order 84 A Rule 4 that time began to run from the 15th December 1998 and thus the three months expired by the 15th March 1999. On this basis Dekra contends that the delay was only of ten days duration. Even if the earlier date contended for by S.G.S. and the respondent were to be accepted as the date upon which the grounds for the application arose the delay was still only one month and one day.

(2) Reasons for delay - extent to which the respondent responsible for the delay.

22. Dekra identified the following factors as being a contribution by the respondents to the delay;

(a) The respondent’s statement of the award of the contract was “subject to contract” induced in Dekra a belief that no final decision to award the contract to S.G.S. had been made;
(b) At the “debriefing” meeting of the 8th December 1998 no information was given as to the respective prices of the tenders;
(c) The respondents reply to Dekra’s letter of 14th December 1998 that the level of re-test fees was incomplete as it did not inform the applicant as to what level the fee was set at or as to how it was calculated;
(d) The cancellation of a meeting to be held on the 12th January 1999 the purpose of which was to give a more detailed debriefing;
(e) The respondent’s failure in his correspondence to deal with specific queries raised;
(f) The failure of the respondent to respond to Dekra’s query as to when the contract was signed.
(3) Prejudice caused by the delay
1. Dekra submits that the rights of the respondent are not prejudiced in that the proceedings will not lead to any further delay in the discharging of its E.C. law obligations to introduce the system of car testing. Dekra points out that Ireland has already been in breach of those obligations and indeed the tendering process was not commenced by the respondent until after Ireland was in default of its obligations in this regard. Dekra also submits that having regard to the fact that in these proceedings it seeks only damages and does not seek to set aside the award of the contract, that there is no inhibition on the respondent or S.G.S. getting on with the implementation of the car testing system.
2. Dekra rejects the respondent’s claim that there will be a resultant delay in the carrying out of a consequential E. U. wide public procurement process for its supervision contract for the mobilisation and operational stages of the N.C.T.’s Dekra affirms that it makes no claim with respect to the consequential contract and submits that the respondent is obliged to comply with these obligations regardless of whether proceedings challenging the award of the main contract are held to be statute barred.
3. Dekra rejects the respondent’s contention that it was further prejudiced by the delay in that it could not adopt a different course of action which might have minimised the potential claim for damages, for example by suspending the signing of the contract. Dekra contends that the respondent had no such intention as;
(i) The respondent was on the 14th December 1998 put on notice of the threat of injunctive relief ;
(ii) There was contact between the parties between January and March 1999 in which Dekra revealed grave dissatisfaction;
(iii) At no stage did the respondent make any attempt to suspend the contract, on the contrary at all times evinced a determination to proceed with the contract;
(iv) Dekra submits that the respondent could easily have suspended the contract after the institution of proceedings as for example towards the end of the three month time limit;
(v) The respondent’s ability to defend the proceedings could not be said to have suffered any prejudice by reason of the proceedings having been instituted ten days or one month and a day outside the time limit;
(vi) As Dekra did not seek to overturn the award of the contract it submits that S.G.S.’s claims that it has incurred significant expenditure, undertaking significant legal obligations, and being allowed to act to its detriment through the expenditure of time energy and resources, the entering into legally binding agreements, are irrelevant.
(4) The respondent’s delay in sending its award notice for publication.
1. The respondent sent its post contract award notice for publication on the 4th February 1999, fifty-one days after the award of the contract. Under Articles 16 and 17 (2) of Council Directive 92/50/EEC as amended this notice should have been sent forty eight days at the latest after the award of the contract.
2. Dekra acknowledges that no prejudice was caused to it by this delay but adds that it would be inequitable to reject its claim on the grounds of delay when the respondent itself is guilty of delay.
(5) Teleological Approach to Interpretation of Order 84 A Rule 4.
1. Dekra submits the court should exercise its discretion in favour of extending the time limit to ensure that an effective remedy can take place and that appropriate compensation can be awarded. It bases this submission on the well established principle that where domestic law is enacted in order to implement a community measure , a national court applying the domestic legislation should interpret and apply it in conformity with the requirements of E.U. law where possible. In this regard Dekra refers to the case of Van Colson v. Land Nordrheim-Westfalen [Case 14/83] [1984] ECR 1891.
2. Dekra points to the recitals in E.U. Directive 89/665/EEC, the “Remedies Directive”, which Order 84 A was introduced to implement. These recitals note that existing National and E.C. remedies for ensuring the application of Public Procurement Law were not always sufficient to ensure compliance and that it was necessary to ensure that adequate procedures existed in Member States to allow compensation of persons harmed by an infringement. Moreover Article 1 of the Remedies Directive requires Member States to take measures to ensure that decisions of contracting authorities be reviewed effectively.
(6) The three month time limit contrary to European Community Law.
1. Dekra submits that the three month time limit in Order 84 A Rule 4 RSC 1986 is contrary to the principle of equivalence. In this regard they referred to the case of Francovich v. Italy (joint cases of C-6/90 and C-9/90 [1991] E.C.R. 1-5357, in which the E.C.J. stated that the procedural rules for actions to safeguard E.C. Law rights should be designated by National Law. However, the substantial and procedural conditions for reparation of loss and damage must not be less favourable than those relating to similar domestic claims (“principle of equivalence”) and must not be framed so as to make it virtually impossible or excessively difficult to obtain reparation (“the principle of effectiveness”) . It was submitted by Dekra that Order 84 A Rule 4 failed to comply with the principle of equivalence but conceded that there was no infringement of the principle of effectiveness.
2. Dekra submitted that in comparison with a number of similar domestic actions the time limit in the relevant rule is unduly restrictive. They point out that in particular that before the entry into force of this Order an applicant had up to six years to begin seeking damages for breach of E.C. Procurement Law. Dekra submit relying on the Judgment of Carroll J. In Tate v. The Minister for Social Welfare [1995] 1 ILRM 507, that an action seeking damages for breach of statutory duty is a tort therefore the time limit is six years pursuant to Section 11(1) (E) of the Statute of Limitations 1957.
3. Dekra submitted that the domestic character of these proceedings is in the nature of a claim for breach of statutory duty and that therefore claims in respect of breach of statutory duty are a correct comparator.

23. Dekra admitted that there were a number of over-riding considerations which should govern the exercise of the court’s discretion as follows:-

1. Relying upon O'Flynn v. Midwestern Health Board and the dictum from the judgment of McCarthy J. at page 239, Dekra submits that where there is no prejudice to third parties that time should be extended. Dekra submits that a serious wrong would be done to them if they are not permitted to litigate their claim, and if they are correct in their contention they would be entitled to an award of damages. They submit that they should not be prevented from litigating their claim at the behest of S.G.S. who are not prejudiced at all by these proceedings or not prejudiced in a manner which can be recognised by a court.
2. Dekra submits that as a matter of principle or public policy as it effects the administration of justice, parties should not be forced at the first moment to issue a writ. They say that it was right and proper that Dekra attempted to ascertain precisely why the contract was awarded to S.G.S., why a re-test fee double Dekras could have been accepted, to ascertain why and if there was an innocent explanation which Dekra had missed or failed to understand. They contend that had there been a convincing explanation, proceedings would not have been warranted. They submit that parties should be encouraged to resolve disputes. They contend that the concept of “earliest opportunity” contained in Order 84 A Rule 4 must be construed as meaning in the circumstances of each case having regard to the obligation to put the contracting authority on notice of the infringement, and they submit that this is indeed contemplated in Order 84 A in that there is an obligation to exhibit this notice and the response thereto in the Affidavit of Verification required by Rule 3 of the Order.
3. Dekra submits that it is nonsense to suggest that an identical approach should be adopted where only damages are sought. They contend that there is a qualitative and quantitative difference where a ten day extension of time in circumstances where only damages are claimed as distinct from the setting aside of the award. Dekra submit that it was clear from the issuing of proceedings in March that setting aside of the award was not sought in these proceedings. They submit that the courts in this jurisdiction should not follow the judgments of the Court of Appeal in the Matra case in this regard and they further submit that the judgments in the Matra case are inconsistent with the approach taken in O'Flynn v. Midwestern Health Board and in O’Donnell v. Dun Laoghaire Corporation and they further submit that a more harmonious approach is to be found in the Keymed case .
4. They point out that the rationale of the Remedies Directive is to assist those who wish to challenge awards, to ensure that one arm of the State i.e. the contracting authority cannot award contracts which cannot be speedily challenged and suspended if necessary in the courts. They contend that the Directive is there to ensure that there are effective remedies available throughout the European Union. They point out, that the fact that you are required to bring an application within three months does not mean you will get a hearing in timely fashion and they say that the short time limit of three months is designed to ensure that parties don’t come after the time limit to set aside contracts, where the successful tenderer might be several months into the contract. They say that the three month period is explicable in the context of a suspension or setting aside of a contract , and that urgency doesn’t apply where only damage is claimed. They point out that it was difficult for S.G.S. to set out a prejudice to them and they say that after the 15th December 1998 the respondent and S.G.S. were contractually bound and that they were left to get on with their contract unhindered and indeed did in fact set up a car testing system from the 1st January 2000. They say that nothing in these proceedings will prevent S.G.S. testing any car over the ten year period of the contract. Dekra contend that S.G.S. or the respondents are unable to point to any recognisable prejudice or any prejudice which the law could countenance.
5. Dekra submits that the court must have regard to the balance of prejudice as between all of the parties . They say that any prejudice alleged by S.G.S. or their respondents is so indefinite and of potential that it does not compare with the real and actual prejudice that Dekra would suffer if it was shut out from making its claim.

DECISION
The Locus Standi Issue

24. Dekra raised this issue contending that S.G.S. have no locus standi to bring the Motion seeking the striking out of the proceedings in limine , on the grounds that no relief is sought in the proceedings against S.G.S. and having regard to the fact that Dekra seek only damages and not the setting aside of the award of the contract, the proceedings do not threaten any prejudice to S.G.S..

25. S.G.S. say that in order to get damages Dekra must prove that the award of the contract was illegal and obtain a declaration from the court to that effect. They say the granting of such a relief would place in jeopardy the contractual arrangements between S.G.S. and the respondents, perhaps rendering that contract unenforceable.

26. Whether or not the effect of such a declaration would go so far as to render the contract between the respondents and S.G.S. unenforceable is not a question which I have to decide on this Motion. I am satisfied however, that whatever be the ultimate legal effect of such a declaration on that contract, that a pursuit of such a declaration in these proceedings, and if it were obtained would undoubtedly have in the words of Buxton L.J. in the Matra case “an unsettling and disruptive effect on that process”. It would seem to me that at the very least such a declaration would give rise to uncertainty as to the status of the contract and the obligations thereunder of the parties, and would inevitably lead to damage to public confidence in the car testing system. I am of the view that these would be real prejudices to both S.G.S. and the respondents and hence in my view, S.G.S. have a real interest in the outcome of these proceedings and have in my view a locus standi to bring this Motion.


Construction Order 84 A Rule 4 of the RSC 1986

27. A number of issues were raised concerning the construction of various parts of this rule which reads as follows:-

“An application for the review of a decision to award or the award of a public contract shall be made at the earliest opportunity and in any event within three months from the date when grounds for the application first arose unless the court considers that there is good reason for extending such period.”

28. The respondents submitted that where the “earliest opportunity” occurred within the three months period, that the rule does not permit or create a jurisdiction to extend the three month time limit. Conversely, they said it was only when the earliest opportunity arose outside of the three month time limit that the court could extend that time limit.

29. I cannot agree with this submission. It would seem to me that the phrase “unless the court considers that there is good reason for extending such period”, as it comes after the conjoined events, namely, at the earliest opportunity and within three months, and there being no distinction made between them, must in my view be construed as including both of these eventualities. The rule seems designed to confer upon the court a discretion to extend time. If the respondents submission were correct there would in effect be no discretion; as where the “earliest opportunity” occurred within the three months, the time period could not be extended, and where the “earliest opportunity” occurred outside of the three month period an extension of time would be inevitable. Accordingly therefore I am of the view that the rule permits an extension of time whether or not the “earliest opportunity” occurs within or outside the three month time limit.

30. Dekra submitted that the “earliest opportunity” would have to be construed as only arising after the notification to the contracting authority of the infringement alleged and of its intention to seek a review and the response on the contracting authority thereto. In this case Dekra, by a letter of the 14th December 1998, gave the notification required and the respondent gave his response to that notification also in a letter of the 14th December 1998. Thus Dekra were in a position to comply with Order 84 A Rule 3 from the 15th December 1998 onwards, and hence insofar as their obligation under this rule could have effected the “earliest opportunity”, their obligation under Order 84 A Rule 3 could not have postponed the “earliest opportunity” past the 15th December 1998 or within a day or two later as may have been necessary in order to prepare the necessary papers for the purposes of the application.


The date upon which time begins to run for the purposes of Order 84 A Rule 4 .

31. S.G.S. and the respondent contend that time began to run from the 24th November 1998 when Dekra were notified both verbally and by letter that a decision to award the contract to S.G.S. had been made. Dekra concedes that the contract was awarded on the 15th December 1998 and that therefore grounds for the application existed from that date and hence the three month time limit ran from that date. They contend that because of the use of the phrase “subject to contract” in the letter of the 24th November 1998 that it was reasonable for them to take the view that a final or firm decision had not been made to award the contract to S.G.S. at that time.

32. Order 84 A Rule 4 deals with two stages of the process of the awarding of a public contract. The first is the “decision to award” and the second is the “award of a public contract”. The facts as deposed on Affidavit convince me that by the 23rd November 1998 the respondents had made a “decision to award” the contract to S.G.S.. There is no doubt that they communicated their decision in that regard to Dekra and other unsuccessful tenderers both verbally and by the letter of the 24th November 1998. It seems to me that the terms of the letter are quite clear and unequivocally convey the fact that a decision had been made to give the contract to S.G.S.. While I would accept that the inclusion of the phrase “subject to contract” may have given rise to some reflection as to what it precisely meant in the context in which it was used, its inclusion, in this letter does not in my view, at all diminish the clear intent expressed in the letter namely to award the contract to S.G.S. and does not negate the knowledge that a decision to that effect had been made by the respondent.

33. Hence I reject Dekra’s contention that it was reasonable for them to understand this phrase as a meaning that no final decision to award the contract had been made. It would seem to me that the most obvious meaning of the phrase in the context in which it was used was, that the decision to award, was subject only to the formal execution of the contract itself, in the light of the fact that as Dekra points out, there were no terms of the contract which were opened to negotiation. While it might very well be the case that in that context the phrase “subject to contract” could be equated as it was submitted by Dekra with “the existence of the contract being denied”, that of course could not amount to a negation of the facts that “the decision to award” the contract had been made. Thus while the phrase “subject to contract” could be said to have conveyed to Dekra that the contract was not yet formally awarded to S.G.S., it could not have conveyed to them an understanding that a decision to award the contract to S.G.S. had not been made. However I would accept that Dekra did not know of grounds for dissatisfaction with that decision until some time later. Between then and the 14th of December, they learned, of the S.G.S.’s re-test fee, from “other sources”. Thus it can be said that notwithstanding the fact that “grounds for the application first arose” on 24th November 1998, that the “earliest opportunity” to apply for review occurred later.

34. I am therefore of the view that time for the purposes of Order 84 A Rule 4, ran from the 24th November 1998. Thus when Dekra initiated these proceedings on the 25th March 1993 they were one month and one day outside of the three month time limit.


Whether time limit was different where only damage is sought

35. It is clear from Directive 89/665/E.C. and, indeed, from Order 84 A Rule 4 that no distinction is made between claims for damages or other reliefs such as suspension or the setting aside of the award, and that being so, I agree with the following passage from the judgment of Buxton L.J. in the case of Matra Communication v. Home Office (1999) 3 All E.R. at 570:-

“Second, however, and more fundamentally, Matra’s argument is inconsistent both with the normal English practice and with the scheme of Directive 89/665. As to the former, questions of limitations are determined, as Regulation 32(4) says, according to when the proceedings are brought; it is unheard of to have a single limitation period which however commences at different dates according to the nature of the remedy sought. As to Directive 89/665, I have pointed out above that the whole range of remedies envisaged by Directive 89/665 is required to be provided rapidly and no distinction is made in that respect between damages and other remedies. Although the present issue is one of construction of the regulations, the approach of the regulations in submitting all remedies to the same rules is consistent with the approach of the directive.”

36. Were it the case that a different time limit were to apply in respect of a damages claim, the question would then arise as to what that time limit was, there clearly being no express provision for it in either the Directive or Order 84 A. It would seem to me that a differentiation in the treatment of damages as distinct from other reliefs sought, arises not in the context of the time limit, but in the context of whether or not the courts discretion to extend the time limit should be exercised in favour of an extension.


Whether “good reason” for an extension of time shown

37. Both S.G.S. and the respondent rely upon a case of O’Donnell v. Dun Laoghaire Corporation (1991) I.L.R.M. 301 and say that Dekra, in order to obtain an extension of the time limit must both explain and justify the delay and that the test in this regard is an objective one.

38. Dekra submits that in exercising its discretion, the court must have regard to the well known dictum of McCarthy J. in the case O’Flynn v. The Midwestern Health Board, quoted above and also that the court should be guided by the principles set out in the English case of Kaymed (Medical) and Industrial Equipment Limited v. Forest Health Care NHS Trust.

39. It would seem to me that there are no irreconcilable differences between the approaches taken in these various cases. There is a primary onus on Dekra who seeks an extension of the time limit to demonstrate on an objective basis that there is an explanation for the delay and a justifiable reason for it. Of relevance to a conclusion as to whether or not there is such an explanation and such a justifiable reason are the factors set out in the Kaymed case. The respondent submits and I agree with him in this regard, that a factor which must be taken into account is the public interest. This was clearly envisaged by Costello J., as he then was, in the O’Donnell case. However, it would seem, to me that applying the dictum of McCarthy J. in the O’Flynn case must result in tilting the balance in favour of extension of time where that extension of time does not prejudice either the respondent or third parties.


Explanation of and justification of delay on the part of Dekra .

40. Dekra contend that the fact that the letter informing him of the decision to award the contract was expressed to be “subject to contract” led them to believe that a final decision to award a contract had not yet been made. Although aware of the public ceremony on the 15th December, it was their belief that this was merely for the purpose of announcing the award of the contract and not the execution of the contract and they contend that they were unaware of the execution of the contract and believed that it would not take place until January 1999. They say that in the days following the 8th December 1998 when a “debriefing” meeting took place, they learned from “other sources” that S.G.S.’s re-test fee was substantially in excess of Dekras. As a consequence of this Dekra’s Solicitors Messrs. Lee McEvoy wrote to the respondents on the 14th December 1998 raising Dekra’s concerns in relation to the level of re-test fees. Dekra contend that following upon a further lengthy meeting on the 14th December 1998 it was agreed between Dekra and the respondents that a further meeting would take place on the 12th January where the matters concerning Dekra and in particular the question of the re-test fees would be fully explored. Dekra say that the respondent reneged on his promise to attend this meeting in his letter of the 5th January 1999. Dekra say that in their letter to the respondents of the 24th February 1999 they raise the question of re-test fees and other matters including the location of test centres and the issue of bias or conflict of interest arising out of the engagement of Messrs. Coopers & Lybrand as consultant to the respondent in relation to the tendering procedure. They say that their specific queries raised in this letter were not addressed in the reply of the respondent dated the 11th March 1999.

41. Dekra contended that it was reasonable for them to seek answers to their queries before launching the proceedings and when it was apparent that their endeavours in this regard were not going to be successful following the letter of the 11th March 1999, they promptly thereafter commenced the proceedings. They say that as a matter of principle and public policy, litigants should not be forced to issue a writ or otherwise commence proceedings without first taking steps to establish that the proceedings are warranted. Specifically they say that they were entitled to pursue their enquiries with the respondents as there was always the prospect that there might have been a reasonable and convincing explanation as to why the tender of S.G.S. was preferred, and in which circumstance proceedings would not be warranted, and the expense thereof could be avoided.

42. Both S.G.S. and the respondent in contending that Dekra have not offered either a reasonable explanation or a justifiable reason for the delay, point to the fact that they were informed of the decision to award the contract on the 24th November, by the 14th November as a result of the debriefing meeting on the 8th December and their own enquiries, they were aware of the three issues which caused them concern, namely the level of the re-test fee proposed by S.G.S., the conflict of interest issue involving Coopers & Lybrand, and the location of the test centres proposed by S.G.S.. They say that they were informed of the ceremony for the execution of the contract and invited to attend and they say that as a result of what transpired at that ceremony together with the press releases issued and the attendant publicity about it in the media on the 16th December 1998 that Dekra were fully aware of the issues which are subject matter of the substantive proceedings herein. They point to the correspondence of the 14th December 1998 where they raise these concerns and in particular the re-test issue and in which they give the notification as required by the relevant E.U. Directive of their intention to seek injunctive and other relief. They query as to why having taken that step and having regard to the knowledge which they had at the time, they did not promptly, then institute the proceedings and they say that no reasonable explanation has been advanced for this failure nor has there been any justification for the delay in initiating the proceedings up to the 25th March 1999.

43. In addition, the respondent contends that Dekra, in its Affidavits and in particular its statement grounding the proceedings and Affidavit of Verification have failed to make a full disclosure and indeed, that the statements and averments made in these documents are materially deficient, misleading and in breach of the principle of good faith and designed to obfuscate the facts and misled the court as to its true knowledge concerning the date of the decision to award the contract to S.G.S.

44. For the reasons already given, I do not accept that their reliance on the phrase “subject to contract” is an acceptable explanation of any delay from the 24th September 1998 to the 15th December 1998. By the 16th December 1998 in my view, Dekra were aware of the three issues which became of concern to them, namely the re-test fee, the location of tests centres and the conflict of interest issue.

45. I would be prepared to hold that the issues which were of concern to Dekra were complex in particular the issue of the re-test fees and that they may indeed have been baffled by the appellant discrepancy between the proposed re-test fee of S.G.S. and their own proposed re-test fee and that they strove for an explanation of this. To fully understand the difference between the two, I would readily be prepared to accept, would involve an exploration of the unlying data relevant to the concepts of variable cost and profit. Clearly discussion took place on these issues in the debriefing meeting of the 8th December 1998 and in the further meeting on the evening of the 14th December 1998 but, I would infer from the fact that a further meeting was arranged for the 12th January, that the parties involved in that meeting did not arrive at any kind of agreed conclusion or outcome.

46. The fact that Dekra did not initiate these proceedings pending the meeting on the 12th January 1999 is not surprising and I am inclined to view that their explanation of delay up to the point at which they were notified of the cancellation of that meeting is reasonable and justifiable. However, nothing was done from the receipt by them of notification of the cancellation of that meeting until their letter of the 24th February 1999, a full six weeks. There is no explanation whatsoever offered of this six week delay, a delay which formed a very significant part of the period of three months in Order 84 A Rule 4. At that point, namely 24th February 1999, they re-engaged in the same enquiries but obviously with greater elaboration. Having regard to the fact that the respondents had cancelled the meeting on the 5th January, they thereby intimated an end so far as they were concerned, to the discursive process related to the outcome of the tendering procedure.

47. In my view having regard to the essential urgency which was undoubtedly required having regard to the terms of the E.U. Directive 89/665 and Order 84 A Rule 4 the recommencement of correspondence of this kind on the 24th February 1999 was not justified.

48. Having regard to the foregoing I am of opinion that the “earliest opportunity” for the purposes of Order 84 A Rule 4 occurred in the week or so after the cancellation or the receipt by Dekra of notice of the cancellation of the meeting of the 12th January 1999.

49. While I would readily agree with Dekra’s submission that in general as a matter of public policy, litigants should not be forced to issue proceedings before they have a reasonable opportunity to satisfy themselves that the proceedings are warranted, having regard to the cancellation of the meeting on the 12th January 1999, any belief that they may have had that they would quickly reach a full understanding of the problem and fully inform their conclusion as to whether proceedings were warranted, must have been shattered by the cancellation of that meeting, leaving them under no doubt but that proceedings would be necessary if they were to progress their complaint.

50. The statement of Dekra grounding the proceedings together with the Affidavit of Verification could be said to have the appearance of a lack of candour, particularly in the light of the contents of the letter of the 14th December 1998 from Lee McEvoy Solicitors for Dekra where they say “we would be very grateful if you would respond to us in relation to this concern prior to the formal execution of the contract on Tuesday”.

51. It was submitted on behalf of Dekra that whatever deficiencies were there, they could not and did not mislead the court in the sense of getting the court to do something it might otherwise not have done because there was no application for leave and no application for interim relief. Undoubtedly this is so, but nevertheless the grounding statement and verifying Affidavit present an unhappy incompleteness. However without the benefit of the full hearing I would not be prepared to allow the exercise of my discretion on the issue raised in this Motion be swayed against Dekra on this ground alone.


Who contributed to the delay

52. Having regard to the foregoing, in my opinion, both the respondent and Dekra contributed to the delay up to the cancellation of the meeting on the 12th January 1999, thereafter the delay was entirely the responsibility of Dekra.


The issue of prejudice

53. Both the respondent and S.G.S. claim that they are prejudiced by Dekra’s delay in instituting these proceedings. Both say that notwithstanding the fact that Dekra does not seek to set aside the contract between them but merely seeks damages, that nonetheless in order to obtain damages Dekra will have to obtain a declaration to the effect that the award of the contract to S.G.S. was an infringement of the relevant Directives and hence unlawful, and they point to the declaratory reliefs that are claimed in the originating Notice of Motion of Dekra. Both S.G.S. and the respondent contend that the granting of a relief of this kind would, perhaps, render the contract between S.G.S. and the respondent unenforceable or at the very least cast a doubt over the status of the contract and that this uncertainty would be prejudicial to them both. They both also point to the fact that S.G.S. has invested a great deal of money and other resources in the setting up of the N.C.T.’s and that all of this may be placed in jeopardy.

54. The respondent additionally contends that he was prejudiced in been unable to precede in timely fashion to conduct a competition to select the independent supervisor for the implementation of the N.C.T.'s and as a result of the delay ended up having to pay for two competitions, the first to engage a temporary supervisor and the second a permanent supervisor.

55. It is readily to be appreciated that the existence of these proceedings and the reliefs claimed would have an “unsettling” effect on the relationship between S.G.S. and the respondent. While it is the case that the setting aside of their contract is not sought, nevertheless if Dekra succeeds in obtaining the declarations that are sought in its originating Notice of Motion and its statement grounding the proceedings, some doubt will be cast on the contractual relations between S.G.S. and the respondent giving rise to uncertainty. However, although it is unnecessary for me to decide the matter in these proceedings, it would seem that there is a clear distinction to be drawn between an infringement or illegality in the process whereby the contract was awarded, and the existence and status of the contract itself. No issue at all arises in these proceedings concerning the terms or obligations of the contract between S.G.S. and the respondent and given that Dekra does not seek to have it set aside, it is hard to see how it is in reality threatened by the reliefs that are sought by Dekra in these proceedings.

56. Nevertheless I could envisage a situation where if those reliefs sought by Dekra were granted that there would be an undermining of public confidence in the N.C.T.'s which could create a variety of problems for and pressures on both S.G.S. and the respondent, emanating from a disgruntled public.

57. However, that is a consequence which would flow from the nature of the reliefs themselves, were they to be granted, and do not appear to me to flow from the delay of Dekra in initiating these proceedings. The only relevance of that delay to these consequences is that it is clearly in the interest of all concerned including the public that proceedings of this kind involving claims for the reliefs that are claimed in these proceedings should be deposed of as speedily as possible. In this context it could be said that the delay on Dekra’s part could make a marginal contribution to any prejudice in this regard that S.G.S. and the respondent might suffer. However having regard to the time involved in the prosecution of the proceedings to a final determination I would be of the view that the contribution of Dekra’s delay in initiating the proceedings is insignificant in terms of that prejudice.

58. In the light of the fact that the setting aside of the contract is not sought by Dekra, it would seem to me that the undoubted fact that S.G.S. has invested heavily both in terms of money and other resources in the setting up of the N.C.T.'s is irrelevant.

59. Having carefully considered the evidence on Affidavit concerning the delay in the holding of the competitions for the independent supervisor, I am left unconvinced that the delay on Dekras part in initiating these proceedings should be blamed for the difficulties that the respondent encountered in engaging the supervisor. From the 24th November 1998 the respondent had made a decision to award the contract to S.G.S.. A full four months elapsed between then and the initiation of these proceedings on the 25th March 1999. No explanation is offered by the respondent as to why the competition to engage the supervisor was not held in this period, when it is clear from the time scale involved in holding such a competition, that it could easily have been done within that period.

60. The respondents say that they were deterred from holding the competition because of ambiguity in the Notice of Motion, statement grounding the proceedings and verifying Affidavit concerning the reliefs to be sought and that this was not finally cleared up until the letter of the 25th June 1999 from Dekra stating unequivocally that it did not seek the setting aside of the contract.

61. It is quite clear that the Notice of Motion dated the 15th March 1999 does not seek an Order setting aside the contract or suspending it. In the Statement of Grounds likewise in the paragraph headed “Relief Sought”, a setting aside is not sought.

62. In the paragraph headed “Relief Sought” at paragraph (x) (g) at sub paragraph 6 the following is stated:-

If the said three month period has expired, which is denied, the applicant’s claim is limited to damages and to ancillary declaratory relief. Specifically the applicant does not seek to set aside the award of the contract of S.G.S. Ireland. In the circumstances, there is no prejudice to any Third Parties arising from any delay.”

63. Paragraph 18 of the Affidavit of Dietnar Bogk sworn the 22nd March 1999 says the following:-

In the events that the three month period has expired, which is denied, I say and believe that this is an appropriate case for an extension of the time period, in particular, the applicant seeks damages from the respondent and does not seek to reopen the tendering procedure for the contract...”

64. While I would except that one can perceive an element of ambiguity in these documents relative to the relief claimed, it would seem to me that the overwhelming thrust or sense of the documents indicates to the contrary and I must confess to some surprise that the respondent would at the end of March or during April or May 1999 been deterred from an obviously necessary course, namely the holding of the appropriate competition to engage an independent supervisor, because of this alleged ambiguity.

65. On balance therefore, I am left unconvinced from the evidence that either the delay of Dekra or any alleged ambiguity in relation to a reliefs claimed in its Notice of Motion could be fairly blamed for whatever difficulties the respondent had in preceding with that competition up to June 1999.

66. Dekra contends that if these proceedings are struck out in limine as is sought, a grave injustice will be done to it because, what it contends is a valid claim will be defeated without ever being heard and that nothing that is advanced by either S.G.S. or the respondent as prejudice to them could be said in any serious way to outweigh the gross prejudice to it, that would result from these proceedings being struck out at this stage.


The Public Interest .

67. The respondents submit that the court must have regard to the public interest in exercising its discretion. The particular public interest that is advanced for consideration is the orderly administration of public contracts and tenders for public contracts. The respondents submit that were it the case that applications for review of awards of public contract were to be entertained outside the three month time limit, that this would lead to an administrative nightmare for various government departments and public bodies charged with the carrying out of these contracts, and that it would lead to great legal uncertainty affecting a great many parties if the status of these contracts was to be subject to uncertainty over a protracted period of time. In this regard the respondents point out that at any time there are several hundred of these contracts on going and that extensions of the three month time limits in relation to reviews of them would place an impossible burden on government departments and other public bodies.

68. I would readily accept that if the setting aside relief were to be sought in reviews of the decision to award or the award of public contracts initiated outside the three month limit, that this clearly could lead to kind of “administrative nightmare” that the respondents apprehend. Clearly in that situation a great many valuable public projects could be held up for lengthy periods of time and this would cause considerable prejudice to a great many people namely the contractors and all of the professionals involved, the departments of the State or other public bodies charged with dealing with these matters and last but not least, the publics enjoyment of the benefit of these contracts would be delayed for the duration of the completion of the litigation.

69. Where however, the setting aside of one of these contracts is not sought as in this case, an entirely different situation pertains. In this circumstance, all the public body or in this case the respondent is faced with is the task of defending the litigation. The project itself can and indeed has gone ahead. In this regard the litigation is in reality no different in terms of prejudice to the respondents than any other of the myriad proceedings that are directed against the state in general and this respondent in particular, on a daily basis and for which the State has ample resources, save that there is this difference, that under the relevant Directive 89/665 and under Order 84 A Rule 4 there is undoubtedly enjoined upon an Applicant for a review of the decision to award or the award of a public contract an onerous obligation to move with urgency and speed. On balance I do not see these proceedings as imposing any unusual or oppressive burden on the respondent.

70. The respondents also made the case that they are anxious to comply with their obligations under E.U. Law to implement the car testing system and point to the fact that they have heretofore been in breach of that obligation. This is rightly a concern of the respondent. The fact that Dekra do not seek the setting aside of the contract or a suspension of it means that these proceedings do not inhibit the respondent in proceeding to effect compliance with its obligations under E.U. Law. In fact the car testing system has been set up since January of the year 2000 without any apparent effect from these proceedings.


CONCLUSION

71. I have come to the conclusion that neither S.G.S. nor the respondent will suffer a significant prejudice that can be fairly attributable to the delay on the part of Dekra. Such prejudice as is decernable is of a potential or indefinite kind and would be the result of the proceedings themselves and the relief sought therein rather than the result of any delay on the part of Dekra in initiating these proceedings.

72. On the other hand if these proceedings are to be struck out now without been heard, a grave injustice may be done to Dekra. Balancing that prejudice against any potential prejudice to S.G.S. or the respondent, I have come to the conclusion that the balance must lie in favour of Dekra. I am mindful of the fact that Dekra have been in delay and as I have found earlier, have not explained a significant portion of that delay. Nevertheless the relief sought in this Motion by S.G.S. is of the most drastic kind and in my view is such that should only be granted in the clearest of cases where the default is gross or the prejudice caused by it is real and substantial and immediate. In this case the delay is short in terms of time, the extension of time required a matter of some one month. While urgency is clearly required in applications for reviews of the decision to award or the award of a public contract, nevertheless the conduct of these reviews are not a new departure in our jurisprudence such that a wholly different approach to the question of delay should be adopted. The courts are there to administer justice and only in the most extreme case should a party be repelled from the seat of justice unheard. No doubt the award of public contracts is a matter of great public importance involving potentially very serious obligations on the part of the State and where wrong doing occurs remedies which may place a heavy burden on the public purse. Be that as it may, the validity or the relevance to these reviews of the time honoured maxim Fiat Justitia Ruat Coelum remains undiminished.

73. For the foregoing reasons therefore, I have decided to exercise my discretion in favour of extending the time limit in Order 84 A Rule 4 to the 26th March 1999. In the light of this, it is unnecessary for me to express an opinion on Dekra’s submission, that the three month time limit in Order 84 A Rule 4 is ultra vires on the grounds that it offers the principle of equivalence. However, for the sake of completeness and in deference to the very erudite submission made by S.G.S. and Dekra on the topic I am prepared to say that, I am satisfied, that there is no comparator in our domestic law, breach of statutory duty being far to wide and diffuse to be a valid comparator. Hence, I would adopt the reasoning of Buxton L.J. in the Metra case and conclude that Order 84 A Rule 4 does not fall foul of the principle of equivalence.


© 2001 Irish High Court


BAILII: Copyright Policy | Disclaimers | Privacy Policy | Feedback | Donate to BAILII
URL: http://www.bailii.org/ie/cases/IEHC/2001/154.html