![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
Jersey Unreported Judgments |
||
You are here: BAILII >> Databases >> Jersey Unreported Judgments >> Urbania -v- Petrofac [2018] JRC 058 (14 March 2018) URL: http://www.bailii.org/je/cases/UR/2018/2018_058.html Cite as: [2018] JRC 58, [2018] JRC 058 |
[New search] [Help]
Arbitration - application by the plaintiff apply for a stay of proceedings.
(Samedi)
Before : |
T. J. le Cocq, Esq., Deputy Bailiff, and Jurats Blampied and Thomas |
|||
Between |
Urbania International Management Consultancy |
Plaintiff |
|
|
And |
Petrofac International Limited |
Defendant |
|
|
Advocate O. J. Passmore for the Plaintiff.
Advocate R. D. J. Holden for the Defendant.
judgment
the deputy bailiff:
1. On 11th August, 2017, Urbania International Management Consultancy ("Urbania") commenced proceedings against Petrofac International Limited ("Petrofac") for the sum of Arab Emirate Dirhams 71,375,496 plus interest and costs. The proceedings were started by a simple summons and the debt was said, in the summons, to arise out of a Services Agreement dated 29th June, 2011, (and varied in writing on 2nd February, 2014,) ("the Services Agreement"). Urbania asserts that it has provided advisory and other services under the Service Agreement for Petrofac and the value of those services is reflected in the sum claimed in the summons.
2. The Services Agreement, which is governed by English law, contains the following provisions:-
"29. All disputes between Consultant and Petrofac arising out of or in connection with this Agreement shall be referred to arbitration under the rules of the International Chamber of Commerce and the place of the arbitration shall be London, England. Arbitration proceedings shall be conducted in the English language.
30. This Agreement shall be deemed to have been executed and delivered in England and shall be interpreted and construed in accordance with the laws of England."
3. When the summons was first presented before this Court Petrofac sought to place the matter on the pending list. The basis on which it sought to do so were the provisions of Clause 29 of the Services Agreement. It was Petrofac's position that the proceedings against it in Jersey should not have been brought, that there was a dispute between it and Urbania and that dispute must, pursuant to Clause 29 set out above, be referred for arbitration. Accordingly Urbania's proceedings in Jersey should be stayed for that purpose.
4. Urbania does not accept that such a stay should be imposed and argues that the arbitration provision set out in Clause 29 above does not apply in the circumstances because of an exception within the applicable statute in Jersey.
5. The matter turns upon the interpretation of Article 5 of the Arbitration (Jersey) Law 1998 ("the Arbitration Law") which is in the following terms:-
I refer to the part underlined above as "the exception wording".
6. The first point to note from Article 5 is that there is no discretion involved and the requirement of the Court to make an order staying the proceedings is mandatory. Secondly, in this case, it is not argued before us that the arbitration agreement is null and void, inoperative or incapable of being performed. The sole argument before us is based on the exception wording, namely whether or not there is "in fact any dispute between the parties with regard to the matter agreed to be referred." In order to refuse to order a stay we must be satisfied that there is not in fact any dispute.
7. It is Urbania's case in brief that there is no real dispute. The obligation to pay those monies has never been challenged and Urbania's entitlement to them is not really in dispute. Petrofac, for its part, simply says that the arbitration clause is binding and the mere fact that it has not paid would be sufficient to establish that there is a dispute between it and Urbania and therefore there should be a stay for reference to arbitration.
8. Had this matter fallen to be resolved purely by reference to English law then there does not appear to be any challenge to Petrofac's assertion that it would inevitably have been stayed for arbitration. We have been shown an affidavit from leading counsel specialising in arbitration in England and Wales and in summary counsel informs us that under English law:-
(i) A claim which remains unpaid constitutes a dispute and is therefore to be resolved by the arbitral tribunal rather than the court;
(ii) Even if a defendant admits payment is owing there is still a dispute until payment is made. Non-payment amounts to a dispute irrespective of any admission;
(iii) It is not permissible under English law to disapply the arbitration agreement and take court proceedings instead, on grounds that a claim is or appears unanswerable;
(iv) Any defence and/or relevance to the SFO investigation (as explained hereunder) would be a matter for the arbitral tribunal.
9. It is not in our view necessary to go into a considerable amount of detail concerning the background of the matter.
10. The Services Agreement sets out the scope of services to be provided. It defines Urbania as the consultant and makes references to the provision by the consultant of certain services to Petrofac for the preparation of the tender and execution of bids submitted by Petrofac for a number of projects listed in the first paragraph of the Services Agreement.
11. The scope of services are more specifically defined and it is not necessary to recite them in detail. They may be characterised as providing assistance to identify a strategy to prequalify and develop a winning proposal to execute the project in question, to provide advice in respect of local requirements, to advise on local economic, political and social market conditions and existing and future laws applicable to the project in question and to provide other forms of advice and assistance.
12. The Services Agreement entitled Urbania to charge a fee of 1.25% of the value of the contract for the project. The fee fell to be determined by a calculation based on figures provided by Petrofac.
13. It is alleged, and we do not take there to be any dispute, that Urbania worked for a significant period with Petrofac until the project in question was successfully awarded to Petrofac. In order to enable Urbania to raise its fee Mr Bonucci who is the Group Head of Business Development at Petrofac, sent a breakdown of the contract value concerning the project so that Urbania's fee could be calculated.
14. Urbania then raised an invoice and submitted it to Petrofac and it has not been paid. We are aware of no argument which disputes the nature of the work undertaken by Urbania nor the correctness of the quantification of Urbania's fee.
15. On 12th May, 2017, the Serious Fraud Office ("SFO") announced publicly that it was investigating Petrofac in connection with the activities of a company called Unaoil. We are informed that Unaoil is not in any way connected with Urbania or the work they carried out for Petrofac.
16. A number of communications passed between Urbania and Petrofac. Communication often took place by text between a Mr Amir Samhoun ("Mr Samhoun") of Urbania and Mr Bonucci. On 10th May, 2017, Mr Bonucci confirmed that Urbania's invoice had been received and that he had "already started processing it".
17. We do not need to refer to the other messages passing between them save to say that on the 20th June, 2017, Mr Samhoun asked for an update on the question of the invoice and Mr Bonucci replied:-
"Amir, still chasing the compliance team. The situation is getting worse as everything is frozen... let's wait some more time if it gets better."
18. Mr Samhoun's response was an indication that he may need to take legal steps to protect Urbania's rights.
19. It is perhaps also worth noting the contents of Mr Samhoun's affidavit detailing two telephone calls between Mr Samhoun and Mr Bonucci. On 28th May, 2017, Mr Bonucci telephoned Mr Samhoun who enquired about the status of the invoice. Mr Bonucci said that all payments had been frozen and he could not provide an estimated payment date. Mr Samhoun indicated that Petrofac's issues with the SFO had nothing to do with Urbania and Mr Bonucci agreed with that. Mr Bonucci stated, in response to Mr Samhoun's point that Urbania could not wait indefinitely, to the effect that:-
"No Amir, you have a legal and legitimate agreement, our internal committee has approved the invoice, the company will pay it."
20. From the information that we have it does not appear, as we have said, that the invoice in terms of quantification and contractual entitlement is in dispute or, at least, no such dispute has been claimed or detailed. When Urbania eventually instructed English legal advisers to write to Petrofac those legal advisers received what could only be described as a holding response and, thereafter, on 7th August, 2017, Petrofac's legal advisers wrote indicating that it was not appropriate at that point for Petrofac to authorise payment to Urbania because of the ongoing investigation by the SFO in the United Kingdom. This was, so it was stated, because of allegations of bribery concerning Petrofac, its officers and agents.
21. The nature of the SFO's investigation and its existence was first notified to Urbania when the SFO issued a press release in the following terms:-
"The SFO is investigating the activities of Petrofac PLC, its subsidiaries and their officers, employees and agents for suspected bribery, corruption and money laundering.
This investigation is related to SFO's ongoing investigation into the activities of Unaoil."
22. The letter from Petrofac's legal advisers Freshfields of 7th August ,2017, states as follows:-
"On 12th May 2017 the Serious Fraud Office announced that it is investigating Petrofac, its subsidiaries (which includes PIL), and their officers, employees and agents for suspected bribery, corruption and money laundering.
In light of the SFO's investigation extending to Petrofac's agents, it is not considered appropriate, at this point in time, for Petrofac to authorise payment of Urbania's outstanding invoice. PIL will of course notify you if, and as soon as circumstances change.
Clearly, we reject your contention that proceedings to wind up PIL are in order. The current circumstances do not allow Urbania to take any such step."
23. The essence of Petrofac's argument is that there is a dispute between it and Urbania and consequently that dispute must be referred to arbitration. Petrofac asserts that it has not on the face of the invoice or the claim admitted that the sums are due and also asserts that the effect of the investigation by the Serious Fraud Office on the matter of payment is a matter that should be determined within the arbitration proceedings.
24. We were referred to a number of cases and texts in connection with the appropriate interpretation of Article 5 of the Arbitration Law. Many of the cases referred, not to statutory provisions, but to clauses in agreements providing for arbitration of 'disputes' or 'differences'.
25. The Arbitration Law was enacted in part, as appears from the long title, to "give effect to the New York Convention on the Recognition and Enforcement of Foreign Arbitral Aawards...".
26. Schedule 3 of the Arbitration Law contains the convention on the Recognition of Enforcement of Foreign Arbitral Awards done in New York on 10th June, 1958. Article II(1) states:-
27. And, at sub-paragraph (3):-
28. The exception wording is not contained in the New York Convention. The exception wording is, however, contained within the English Arbitration Act of 1975.
29. The origin of the wording of Article 1 of the Arbitration Act 1975 is to be found in the report of the Committee of the Law and Arbitration 1927 known as the McKinnon Committee Report which says this:-
"Our attention has been called to a point that arises under the Arbitration Clauses (Protocol) Act 1924. Section 1 of that Act in relation to a submission to which the protocol applies deprives the English court of any discretion with regards granting the stay of an action. It is said that cases have already not infrequently arisen, where (e.g.) a writ has been issued claiming the price of goods sold and delivered. The defendant has applied to stay the action on the ground that the contract of sale contains an arbitration clause, without being able, or condescending, to indicate any reason why he should not pay for the goods, or the existence of any dispute to be decided by arbitration. It seems absurd that in such a case the English court must stay the action, and we suggest the Act might at any rate provide that the court shall stay the action if satisfied there is a real dispute to be determined by arbitration."
30. There is a material distinction between the position in the United Kingdom at present and that which obtained in 1975. The Arbitration Act of 1996 does not contain the exception wording and accordingly the Courts there no longer need to consider the meaning and effect of that wording. That change, which of course has come about by an Act of Parliament, is not reflected in the Jersey position and the cases that concern the Arbitration Act 1975, which contained the exception wording, are prima facie more relevant to a consideration of the Arbitration Law than later cases under the Arbitration Act of 1996.
31. In Mustil and Boyd (The Law and Practice of Commercial Arbitration) (2nd Edition) under the heading Clauses requiring a "dispute" or "difference", the learned authors say this:-
32. In Redfern and Hunter on International Arbitration (Fifth Edition) at 1.59 and 1.60 under the heading "The need for a dispute" the learned authors say this:-
33. It appears clear that the English courts gave meaning to the exception wording within the Arbitration Act of 1975. The courts took the view that they were able to refuse to grant a stay for arbitration if there was no real dispute. This appears to have been interpreted, as a claim not being genuinely disputable if it would justify, for example, an application for summary judgment. In other words, if it is clear that any such "dispute" was not a real dispute because, if pleaded, it would give rise to the summary judgment then the court was satisfied that it had a basis not to grant a stay for arbitration but instead to enter summary judgment.
34. We will set out some of the authorities which have been put before us which appear to us to support the proposition that the English courts, whilst taking a fairly robust view of the requirement for a dispute within arbitration clauses (in other words that there was a dispute even when, for example, there was nothing more than a refusal to pay without any kind of justification), nonetheless construed the exception wording in the Arbitration Act 1975 as producing a basis to refuse a stay.
35. As we have said, the provisions of the Arbitration Law reflect not the current English statutory position but that which existed under the Arbitration Act of 1975 (under which Section 1(i) contains the exception wording in the same terms as Article 5 of the Arbitration Law).
36. There can be no doubt and we do not think it in dispute that raising an account pursuant to the Services Agreement and submitting that account for payment are matters that fall squarely within the Services Agreement and any dispute with regard to those matters are also themselves matters that fall within the Services Agreement and therefore are subject to the arbitration provisions.
37. Many of the authorities deployed before us dealt with the question of whether or not a matter is in dispute for the purposes of a clause containing such a provision within the relevant arbitration agreement. They are not, in general, cases which touch upon the interpretation of the meaning of "dispute" within the Arbitration Act of 1975 and, by extension, Article 5 of the Arbitration Law. There is authority to the effect that the English courts have taken a different approach in construing the meaning of the term "dispute" within the Arbitration Act of 1975.
38. The concern of the English courts under the Arbitration Act 1975 appears to be the belief that, by strict application of an arbitration provision, arbitration could be used to slow down the recovery of a claim in respect of which no reasonable dispute could be raised. There was concern expressed that arbitration could take a long time and that it would be in effect an injustice to require a contracting party to go to arbitration when their claim was not capable of any serious dispute. It is also clear that this approach of the English courts was not without criticism and did not reflect, perhaps, the approach to modern arbitration.
39. In Associated Bulk Carriers Limited-v-Coch Shipping Inc (The Fuohsan Maru) [1978] 2 All ER 254 the Court of Appeal dealt with a dispute relating to a charter party. The plaintiffs lent a motor vessel to the defendants for a number of years during the course of which the defendants used a number of devices to get out of the charter. They purported to terminate the charter party and redeliver the vessel and the plaintiffs treated the defendants conduct as a repudiation. They accordingly brought a claim in damages. The defendants had admitted liability but denied the plaintiffs were entitled to the amounts of damages claimed. They applied for an order under the Arbitration Act of 1975 that the proceedings should be stayed and the dispute referred to arbitration in accordance with the charterparty. The court found whereas undoubtedly the plaintiffs were entitled to a substantial sum in damages there was in fact a dispute between the parties with regard to the matter agreed to be referred and the matter must be stayed under the Arbitration Act of 1975. The judgment of Lord Justice Browne at paragraph 263 of the judgment contains these words:-
40. And at paragraph 264 of the judgment Geoffrey Lane LJ said this:-
41. The case of Tradax Internacional SA-v-Cerrahogullari TAS (The M Eregli) [1981] 3 All ER page 344 was cited by Petrofac to support the argument that the claim that is not positively admitted it is in dispute. In that case Kerr J was dealing with an arbitration clause which contained a time limit of nine months within which any claims under the relevant contract need be made. At page 349 of the judgment the court said, at J:-
42. In the case of Ellerine Bros (Pty) Limited and another-v-Klinger [1982] 2 All ER page 737 the English Court of Appeal in the judgment of Templeman LJ (page 741) said this:-
43. In Hayter-v-Nelson [1990] Lloyds Law Reports Vol. 2 page 265 Saville J had to consider the meaning of dispute in an arbitration clause within the context of a reference to arbitration. He cited at page 268 the judgment of Templeman LJ in Ellerine -v- Klinger (cited above) and then went on in the following terms:-
44. He then goes on to reject the assumption that arbitrations are necessarily slow processes, secondly that the parties have made an agreement that in the place of the courts their dispute should be resolved by arbitration, and then says:-
45. In Mayer Newman & Co Limited-v-A1 Farrow Commodities Corporation SA (The John C Helmsing) [1990] Lloyds Law Reports Vol. 2 at page 290 the court characterised the argument before them on an arbitration clause in the following way:-
46. At page 296 in his judgment Bingham LJ stated as follows:-
47. It appears from the above quote that Bingham LJ felt constrained by authority placed before him although he did not need to resolve the issue as he addressed the matter by reference to different argument.
48. There is an interesting extract from the case of Exfin Fishing India Limited Mumbai and Telanhi Shipping Co Mumbai [2006] EWHC 1090 (Com) in which at paragraph 9 Langley J said this:-
49. In Pledream Properties Limited-v-5 Felix Avenue London Limited [2011] L and TR 20 at page 291 Lewinson J, at paragraph 18, said this:-
50. In Channel Group-v-Balfour Beatty Limited [1993] AC 334 at 356 Lord Mustil states:-
51. In Hume-v-AA Mutual International Insurance Co. Limited [1996] LRLR 19 at 27 Clarke J said this:-
52. Although considerable authority has been deployed before us, and we have referred to a part only, it seems to us the matter can be simply stated. The Royal Court, at present, pursuant to the express terms of Article 5 of the Arbitration Law has the discretion if satisfied that there is no real dispute between the parties, to decline to stay a matter for arbitration. That is no longer the position in the United Kingdom because the express provisions which had enabled it under the Arbitration Act of 1975 to do so have not appeared in the Arbitration Act 1996. In determining whether or not there is a real dispute the Court should resolve any doubt in favour of a stay and should only decline to order a stay for the purposes of arbitration if satisfied to the standard necessary for a summary judgment that there can be no real argument or dispute put forward to defeat the claim.
53. In the Guernsey case of The States-v-Miller and Baird CI Limited Guernsey Law Reports 2005-2006 GLR 295, the Court of Appeal, Rokison JA delivering the judgment of the court, applied Section 4 of the Arbitration Guernsey Law 1982 which is, in effect, in identical terms to Article 5 of the Law. The learned judge confirmed that the common practice in the English courts endorsed by Lord Mustill in the Channel Tunnel case should generally be followed unless and until Guernsey law is brought into line with the English Arbitration Act 1996 which, in his words, has considerably reduced the circumstances in which a court may decline to grant a stay in the face of a valid and effective arbitration agreement, in particular by removing the discretion of the court to refuse a stay if there is no real dispute. At paragraph 43 the learned judge went on, in reference to the judgment of Saville J in Hayter-v-Nelson that:-
54. And, at paragraph 47, in referring to the judgment of Kerr LJ in SL Safia Liners Limited-v-State of India Limited [1985] 1 WLR at 1401 the Court of Appeal went on to say:-
55. And at paragraph 55, the court said:-
56. On the facts of that case the Court of Appeal did not consider that the matter was so clear that the defendant should be denied its prima facie right to have the dispute referred to arbitration. It, in allowing the appeal, ordered that the action was stayed pursuant to Section 4 of the Arbitration Guernsey Law 1982.
57. Of course the context of this present application comes from the attempt on the part of Petrofac to place the matter on the pending list and then apply for a stay. It is of course well understood that the terms of Rule 6/6(1) of the Royal Court Rules 2004 whilst apparently mandatory in its terms nonetheless were still subject to an inherent power in the court to protect litigants from an abuse of its process.
58. In its decision in Powell-v-Acorn Finance [2016] (1) JLR Note 10 the Court of Appeal said this:-
59. Article 6 of the European Convention on Human Rights, which provides that in the determination of his civil rights and obligations everyone was entitled to a fair and public hearing within a reasonable time by an independent and impartial tribunal established by law, was not inconsistent with the Royal Court's inherent power to refuse to place an action on the pending list if the defendant had no defence, with the result that summary judgment was given in favour of the plaintiff.
60. The States of Jersey has not seen fit to enact any changes to the Arbitration Law to reflect the alteration in the statutory position in the United Kingdom - we do not think that it is open to us to do so judicially. The Court retains a power to refuse to stay in the event that it determines that there is no real dispute between the parties. The policy behind what is termed as the exception provisions is to filter out cases where the defendant may be simply playing for time or not acting in a bona fide manner in asserting that there is a dispute or where there is in reality no dispute.
61. The argument put before us by Petrofac does not raise a substantial defence to the contractual obligation or the qualification exercise on which the claim is founded.
62. The Plaintiff refers to the Defendant's position as set out in paragraph 4.1 of the affidavit of Mr Roger Harwood which is in the following terms:-
"4.1 The defendant has not paid the invoice which is exhibited by the plaintiff .... It is the defendant's position that a dispute therefore arises and that arbitration is the agreed dispute resolution forum."
63. It can readily be seen that this offers no explanation as to what any substantive defence to the claim may be. It relies purely on the absence of payment as creating a valid dispute which should be referred to arbitration.
64. We have of course taken into account the references to the SFO investigation which in the letter from Freshfields of 7th August, 2017, referred to above simply states that repayment of the invoice, in the light of the SFO's investigation was "not considered appropriate". It may conceivably be that there is some kind of argument that could be advanced but our difficulty lies in the fact that Petrofac has not condescended to provide the slightest detail as to what the basis for that assertion may be. Absent that argument it is simply impossible for us to assess whether or not there is any force in it at all. It is not, prima facie, readily apparent to us that the mere fact of an SFO investigation provides any real dispute as to the liability of Petrofac to pay Urbania on its invoice.
65. Accordingly we decline to stay Urbania's proceedings for reference to arbitration.