BAILII [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback]

Scottish Court of Session Decisions


You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> Boyack Homes Ltd v Fife Council [2009] ScotCS CSIH_7 (10 February 2009)
URL: http://www.bailii.org/scot/cases/ScotCS/2009/2009CSIH7.html
Cite as: [2009] ScotCS CSIH_7, 2009 GWD 7-128, 2009 SLT 406, [2009] CSIH 7

[New search] [Help]


FIRST DIVISION, INNER HOUSE, COURT OF SESSION

Lord Wheatley

Lord Carloway

Lord Hardie

[2009] CSIH 7

XA155/07

OPINION OF THE COURT

delivered by LORD WHEATLEY

in the cause

BOYACK HOMES LIMITED

Pursuers and Appellants;

against

FIFE COUNCIL

Defenders and Respondents:

_______

Act: Francis; Morton Fraser LLP

Alt: Clark Q.C.; HBJ Gateley Wareing (Scotland) LLP

10 February 2009


[1] The pursuers and appellants are a firm of house builders who in 2001 were engaged in a private housing development adjacent to
Holly Road, Leven, Fife. The development required the building of new roads which at one point linked up with the existing thoroughfare at Holly Road. The defenders and respondents are the relevant roads authority and the appellants required to obtain a construction consent from them to build the roads within the development.


[2]
Some time prior to July 2001 the appellants applied to the respondents for the necessary construction consent. By letter dated 27 July 2001 the respondents wrote to the design company which acted for the appellants intimating that one of the conditions of the construction consent would be that the appellants should provide the street lighting for the development to the standard required by the respondents. A copy of the respondents' requirements guidelines and specifications was enclosed with the letter. The respondents also offered at the same time to provide a design and supervision service for the installation of the lighting for a fee. The design drawings would show various details including the position of the lamp standards. The appellants, by letter of 9 October 2001, elected to use the design service offered by the respondents. The relevant design drawings were sent by the respondents to the appellants on 19 November 2001. The design drawings showed that three lamp standards on Holly Road at its junction with the development required to be removed, and replaced by five new lamp standards. It is agreed that the provision of the five new lamp standards was entirely a consequence of the appellants' development; it had become necessary to upgrade the lighting because of safety and amenity requirements at the junction. At all material times the respondents had a statutory obligation to provide and maintain lighting at Holly Road in terms of section 35(1) of the Roads (Scotland) Act 1984.


[3]
By letter dated 12 June 2002 the respondents told the appellants that they intended to grant construction consent with a condition that the appellants install the improved lighting on Holly Road. The respondents had been aware of this condition since October 2001 as part of the design contract and had already in fact installed the new lamp standards by 12 June 2002. The respondents' letter asked the appellants to advise them if they wished to be heard on the conditions of the consent within 21 days, but the appellants did not wish to be heard. By fax dated 19 June 2002 the appellants asked the respondents to confirm their agreement or otherwise to the conditions which were to be applied to the construction consent. The relevant condition referred to in the fax dated 19 June 2002 was in the following terms:

"1. The whole of the work shall be carried out at the Developer's own expense in a consistent and workman like manner and in accordance with:- '....

(b) the Council's "Transportation Development Guidelines" (details of which can be obtained from the Council's Head of Transportation) and, as regards road lighting, the design provided or approved by the Head of Transportation;'"

It is this condition, which was in fact repeated in the construction consent issued on 1 July 2002, that is said by the appellants to be ultra vires of the respondents. By letter dated 20 June 2002 the appellants expressly agreed to the conditions to be included in the construction consent including condition 1(b) quoted above and sought a prompt award of the consent. In terms of section 21(6) of the Roads (Scotland) Act 1984, the appellants had 28 days in which to appeal against any of the conditions to the Secretary of State but they did not do so. On 1 July 2002 the respondents issued to the appellants the relevant construction consent, including the condition that the respondents should be responsible for installing the upgraded lighting in Holly Road. Parties are agreed that this condition in the construction consent was in effect preceded in identical terms by a contract for lighting services between the respondents and the appellants in terms of the earlier letters and drawings exchanged in October 2001.


[4]
It is accepted that prior to 20 June 2002 all of the works referred to in condition 1(b) and the associated drawings had in fact been completed by the appellants. The construction consent, which incorporates condition 1(b), was granted to the appellants by the respondents on 1 July 2002. The appellants now maintain that the incorporation of the condition to provide the improved lighting in Holly Road at the junction which appears in the construction consent and in the original contract for the provision of lighting services was ultra vires of the respondents, and now seek recompense. Counsel for the appellants also argued that in terms of the contract for the design of the improved lighting at Holly Road, there must be an implied term that any specification in the design drawings to meet the respondents' requirements was a reference to lawful requirements and would not require the appellants to do anything that the respondents were in law bound to do.


[5]
In his judgment against which the present appeal is taken, the sheriff at Kirkcaldy concluded that the pursuers' case rested on the proposition that section 35(1) of the 1984 Act imposed an absolute duty on the defenders as the road authority. Section 35(1) provides:

"A local roads authority shall provide and maintain lighting for roads, or proposed roads, which are, or will be, maintainable by them and which in their opinion ought to be lit."

The sheriff was of the view that the pursuers' contention imposed too high a duty on the defenders and he could see no equitable reason why the pursuers should not be liable for the re-siting of the lighting in Holly Road, which was caused solely by the requirements of the pursuers' development. Further, the sheriff thought that the pursuers' interpretation of section 35 as imposing an absolute duty on the defenders meant that section 48 of the Act, which allows a roads authority to enter into an agreement with any person willing to contribute to the construction or improvement of a road, would have no meaning. Further, the sheriff could find no reason or basis for concluding that any implied term as argued for by the pursuers should be incorporated into the contract.


[6]
The principal question in the appeal came to be whether the incorporation of the condition that the appellant should provide and pay for the improved lighting on Holly Road was unlawful and improper, and ultra vires of the respondents. Both parties relied on passages from Stewart v Perth & Kinross Council 2004 S.C. (H.L.) 71 for support for their respective positions.


[7]
In that case, a local authority had established a licensing scheme for second hand car dealers in terms of the Civic Government (Scotland) Act 1982. Section 24 of that Act provides that an authority may attach conditions to a licence requiring the keeping of records relating to the dealer's stock in trade. Paragraph 5 of schedule 1 to the Act allowed the authority to grant or renew licences subject to "such reasonable conditions as it thinks fit". The purpose of the scheme was to deter, and assist in the detection of, stolen cars in the second hand market. The local authority imposed conditions on the licences issued by them requiring the dealer to provide prospective customers with a report on each car on display for sale, containing detailed information about the condition of the car and other matters. It was held (in terms of the rubric of the report) that the effect of this condition would have a considerable impact on contracts between the dealer and his customers, that the principal mischief to which the legislation was directed was the handling of stolen property, and that the licensing system was not designed for the purpose of consumer protection, as other legislation existed for that purpose. In these circumstances the particular conditions imposed on licence holders by the local authority in respect of the reports were ultra vires.


[8]
However, the reasoning behind the decision in Stewart v Perth & Kinross Council is more developed in the speeches delivered in the case, and was variously referred to by counsel in their submissions. The passages principally relied on by the appellants are found in the speech of Lord Hope of Craighead:

"
[27]
The opening words of para. (5.2) of Sched 1 to the 1982 Act give power to the licensing authority to attach 'such reasonable conditions' to the licence as it may think fit. As I said earlier, it is to those words that one must go if one is to discover whether those parts of condition 2.5(a) which require information to be given to the purchaser are within the power to attach conditions that is given by the 1982 Act to the licensing authority. At first sight they give a wide discretion to the licensing authority. It requires a very strong case to interfere with the discretion which has been vested in a body of that kind, which legislates in the interests of the community (Nicol v Magistrates of Aberdeen, per Lord President Inglis at p.308; Da Prato v Magistrates of Partick, per Lord Loreburn L.C.). As Lord Russell of Killowen C.J. said in Kruse v Johnson (p.99), legislation of this kind ought to be supported if possible, looking to the character of the body which is legislating, the subject-matter and the nature and extent of the authority which is given to the body to legislate in matters of this kind.


[28]
But it is clear that the discretion which is vested in the licensing authority is not unlimited. The authority is not at liberty to use it for an ulterior object, however desirable that object may seem to it to be in the public interest (Pyx Granite Co Ltd v Ministry of Housing and Local Government, per Lord Denning at p.572; Newbury District Council v Secretary of State for the Environment, per Viscount Dilhorne at p.599). The scope which is to be given to the words 'such reasonable conditions' must be ascertained from their context."

In a passage relied on by the respondents, Lord Rodger of Earlsferry said:

"
[55]
The critical question is the extent of this power in the case of dealers carrying on their business as dealers in second hand motorvehicles. The test is not in dispute. Guidance can be found in the approach that Viscount Dilhorne summarised for conditions attached to planning permissions in Newbury District Council v Secretary of State for the Environment (p.599):

'It follows that the conditions imposed must be for a planning purpose and not for any ulterior one, and that they must fairly and reasonably relate to the development permitted. Also they must not be so unreasonable that no reasonable planning authority could have imposed them.'

That approach was approved by Lord Keith of Kinkel in Grampian Regional Council v Secretary of State and Aberdeen District Council (p.66). Here, therefore, the conditions attached to the licence must be for a licensing purpose and not for any ulterior purpose. They must also fairly and reasonably relate to the business that the licence holder is permitted to carry on as a dealer in second hand cars. In addition, they must not be so unreasonable that no reasonable licensing authority would have imposed them."

Further, in this respect, counsel for the respondents quoted from Lawrence Building Co. Ltd. v Lanark County Council 1978 SC 30, where Lord President Emslie (at p.47) quoted with approval what was said by Lord Selborne L.C. in the Great Eastern Railway Co. case, to the effect that the doctrine of ultra vires:

"... should be reasonably, and not unreasonably, understood and applied and that whatever may fairly be regarded as incidental to, or consequential upon, those things which the legislature has authorised ought not (unless expressly prohibited) to be held, by judicial construction, to be ultra vires."

and noted that this proposition had also been cited with approval in the cases of Glasgow Corporation v Flint 1966 S.C. 108 at 119, and Graham v Glasgow Corporation 1936 S.C. 108 per Lord Justice Clerk Aitchison at p.125.


[9] Against that background, counsel for the appellants maintained that the contract between the parties could not properly ask the appellants to do more than the respondents could legally require, and this applied both to the contract for the design services in relation to the improved lighting on Holly Road and to the construction consent in which the significant condition exactly matched the one which it was designed to anticipate. Section 35(1) of the 1984 Act imposed a prima facie duty on the respondents irrespective of the cause or occasion to provide and maintain lighting on roads within their area as required. Section 21(3)(a) of the Act allows the roads authority a wide discretion to impose conditions on any construction consent, but as Lord Hope said in Stewart v Perth & Kinross Council, the freedom to impose such conditions is not unlimited and any conditions sought to be introduced must be examined in the context of the contract. In the present case the form and substance of the contract meant that the respondents could only impose conditions on the appellants in respect of a new road within the development undertaken by the appellants, and the power to include conditions into the contract or the consent could not extend to their prima facie duty to maintain and improve the existing road network lighting for which they had already a statutory responsibility. This approach, counsel argued, was borne out by the provisions of the 1984 Act (such as sections 16, 21(5), 22, 35(5) and 151), all of which in effect drew clear distinctions between new and existing roads. The condition in the design contract requiring the appellants to provide new lighting was not related to the new roads within the development, but to the existing road network, and was therefore ultra vires. A roads authority could require developers to pay for unrelated matters, but this was normally achieved by other means and measures, such as section 48 of the 1984 Act and section 75 of the Town and Country Planning (
Scotland) Act 1997.


[10]
In reply, counsel for the respondents submitted that the condition introduced into the design contract to the effect that the appellants should improve the lighting at Holly Road, and repeated in the construction consent, was not ultra vires. Section 23(1)(a) allowed the roads authority to impose conditions as they saw fit. There were no restrictions in law on how they set about doing this. The only qualification on the appropriateness of having such conditions is that the services required of the appellants should arise reasonably and fairly out of the development and its associated construction consent. The respondents have a general responsibility to provide and maintain lighting on roads under their control in terms of Section 35(1) of the Act, but there was no qualification or restriction on how they should discharge that responsibility. There was no justification for saying that any such conditions incorporated into the contract or the consent could only relate to the new roads in a development, and could not extend to cover the existing road network. In terms of section 48 of the Act, the roads authority has wide powers to enter agreements with anyone to assist with the provision of lighting.


[11]
The secondary argument for the appellants was that there had to be an implied term in any contract, having regard to the need for business efficacy, to the effect that the respondents' requirements referred to must mean the council's lawful requirements, and as such would not call for the appellants doing work which the respondents themselves were bound to perform in terms of section 35(1). The contract could not stipulate that the appellants performed work in excess of what was required for the development. The appellants were entitled to expect the design contained in the agreement to be legally correct. The respondents could not, for example, propose a contract which led to the result that the appellants had to upgrade the existing road lighting network in Leven. The only rational conclusion was that the contract had to have an implied term that the appellants could not be asked to carry out what were the legal requirements incumbent upon the respondents. Counsel accepted that if his argument on ultra vires failed, then this argument could also not succeed.


[12]
In reply, counsel for the respondents argued that the appellants had come nowhere near to meeting the test of necessity which has to be met before a condition can be imported into a contract. This test meant simply that the contract could not be carried out unless the conditions were implemented. In the present case, the work referred to in the condition had been fully completed before the contract was in place. It could not therefore be said that the term was necessary for the contract to be efficacious. Reference was made to Gloag on Contract, 2nd Ed. p.288. Counsel also submitted that because the work had been completed before the contract was signed, the basis for any claim for recompense had fallen away. Finally, counsel for the respondents submitted that even if he was wrong on all of the arguments he had submitted up to this point, the condition complained of by the appellants was not truly a condition imposed on the contract by the respondents, but an agreement between the appellants and respondents as to who would do the work. The appellants had not done the work as a condition of the contract but as a separate agreement between the appellants and the respondents, which they had now completed.


[13]
We are satisfied that the appellants' submissions in the present case must fail. On the assumption that what the appellants complain of is a condition imposed into the contract at the instance of the respondents, the appropriate test for deciding whether a particular condition has been competently included into a contract, and is not ultra vires of the local authority responsible for introducing it, can most conveniently be found in the case of Stewart v Perth & Kinross Council. From the speech of Lord Rodger (at para. 55), it is clear that any such conditions attached to an arrangement proposed by a local authority must for present purposes have three attributes. Firstly, the conditions imposed must be for a purpose connected to the subject matter of the agreement or proposed agreement in question, and not for any ulterior purpose. An ulterior purpose, as we understand it, would be something which went beyond the remit or subject matter of what was agreed between the parties. Thus, to use the example cited in argument by counsel for the appellants, if the roads authority had required as a condition of the construction consent that the appellants should be responsible for upgrading the lighting on the existing road network in Leven, then that condition would have been properly described as having an ulterior purpose, and it would be ultra vires of the authority to require such a condition to be part of the contract. However, in the present case, it was a matter of concession that the provision of extra lighting in Holly Road was a direct consequence of, and indeed necessary for, the purposes of the appellant's housing development, and although counsel for the appellant was careful to qualify his concession (so that it did not go to the extent of allowing the respondents to impose an illegal condition), that does not assist the appellant's position. As the sheriff has found, and as the appellants have conceded, the need for extra lighting was an essential part of both the design contract and the construction consent, and cannot be described as ulterior to those documents.


[14]
The second requirement is that the condition in question must fairly and reasonably relate to the subject matter of the agreement. The considerations in this respect are in many ways broadly similar to those relating to the first question. Again, standing the sheriff's findings in the pleadings and the appellants' concession, it is impossible to maintain that the provision of the additional lighting on Holly Road was not fairly and reasonably related to the construction consent required for the development. In respect of these first two grounds the critical distinction in our view is not whether the consequences of the condition affect the old road network rather than the new, but whether the consequences themselves, whatever they are, can properly be said to be for a purpose connected to the agreement, or which may be fairly regarded as incidental to or consequential upon the agreement, and which must fairly and reasonably relate to that agreement. Finally, it cannot be said, and it was not argued, that the condition was so unreasonable that no reasonable authority would have imposed it. In these circumstances, we are not satisfied that it has been shown that the inclusion of this condition into the contractual arrangements between the parties was ultra vires of the respondents.


[15]
We found equally unconvincing the appellants' submission that there should be a term necessarily implicit in the contract to the effect that the requirements therein referred to should be the respondents' lawful requirements. As counsel submitted, such terms are to be implied necessarily for the business efficacy of the contract. But here the contract was completed by 30 June 2002, before the construction consent was signed. It could hardly in those circumstances be described as a term that had to be implied for business efficacy. Further, the appellants would seem to be arguing that a term should be implied into a contract in terms exactly the opposite of the condition complained of, and specifically agreed to. It would be a remarkable position if a party to a contract could argue that, after the work had been successfully completed, it was a matter of necessity that a condition in the contract specifically agreed to should be held not to apply, and the converse of that condition imposed in its place. In these circumstances we can see no reason for holding that the implied condition contended for by the appellants should be incorporated into the contract.


[16]
Further, although this is not a matter directly for our decision, we are of the view that the condition complained of by the appellants is simply part of a straightforward contract between the parties. There is no qualification, within the terms of the statute or elsewhere, on the right of a roads authority to discharge their statutory lighting responsibilities by delegating performance to someone else. Section 48 of the 1984 Act seems specifically to allow such a course.


[17]
We therefore refuse the appeal and sustain the judgment of the sheriff.


BAILII:
Copyright Policy | Disclaimers | Privacy Policy | Feedback | Donate to BAILII
URL: http://www.bailii.org/scot/cases/ScotCS/2009/2009CSIH7.html