![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
Scottish Court of Session Decisions |
||
You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> Macdonald Estates Plc, Re Review of a Decision of Gordon Murray [2009] ScotCS CSIH_72 (18 September 2009) URL: http://www.bailii.org/scot/cases/ScotCS/2009/2009CSIH72.html Cite as: [2009] ScotCS CSIH_72, [2009] CSIH 72 |
[New search] [Help]
EXTRA DIVISION, INNER HOUSE, COURT OF SESSION
|
|
Lady PatonLord WoolmanLady Cosgrove
|
[2009] CSIH 72
OPINION OF LADY PATON
in the Petition of
MACDONALD ESTATES PLC
Petitioners;
For a review of a decision of Gordon Murray, architect dated 27th August 2009
_______
|
Respondent: Clark QC, Davies; Harper McLeod LLP
18 September 2009
[1] In view of the shortage of time, I do not
propose to rehearse the background or to record the arguments presented on Thursday 17 September 2009.
[2] The petitioners seek interim orders
in terms of paragraphs (b) and (c) of Statement 3 of the Petition. There is no
dispute over paragraph (b). Accordingly we shall grant interim
suspension in terms of paragraph (b).
[3] In relation to paragraph (c), I acknowledge
that the clear and fully-reasoned opinion of the Lord Ordinary supports the
petitioners' contention that they have a prima facie case. In view of
the conflicting opinion known to have been provided by an experienced senior
counsel who advised Mr Murray, I am not minded to explore the strength of
that prima facie case. I am content simply to confirm that there is
indeed a prima facie case.
[4] I turn therefore to the balance of
convenience. First, it was submitted that the grant of the interim order
in terms of paragraph (c) would preserve matters entire pending the outcome of
the current reclaiming motion concerning Mr Murray's status and
obligations. I do not agree. In my opinion, on a proper construction of the
missives, the contracting parties' intention was that satisfactory planning
permission (unencumbered and unqualified by disagreements, disputes, referrals
to experts, arbitrations, or litigations) would be in place by 26 September 2009 as a prerequisite of the
continuance of the project, otherwise parties would be free to resile. The
significance of that contractual condition should not be underestimated in a
commercial project of this nature, as parties to the project have agreed a
precise timetable including dispute-resolution procedures. Were this court to
accede to the petitioners' motion and to grant the interim order sought
in terms of paragraph (c), far from preserving matters entire, the court would be
innovating upon the parties' contract by putting to one side the existing
fundamental dispute over planning permission, and ordering the production of a
final determination from Mr Murray which would result in the purification
of the suspensive condition such that neither party would be entitled to
resile. In my opinion, that approach would result in a major departure from
the parties' intention as evidenced by the missives.
[5] Secondly, it was contended on behalf of the
petitioners that any prejudice suffered by NCP as a result of the granting of
the interim order would be outweighed by the prejudice suffered by the
petitioners were the interim order not granted. Inter alia, the
following points were made:
[6] The project involved other parties, namely
SECC and another party who acted as both funder and developer. If the interim
order were granted and the final determination issued confirming that
satisfactory planning permission had been granted prior to 26 September
2009 such that the suspensive condition in the Macdonald/NCP missives was
purified, then those other parties would, in terms of their contracts, proceed
with the project. However if the interim order were not granted, and if
the suspensive condition in the Macdonald/NCP contract were not purified by
26 September 2009, the whole project would founder, as those other parties
would be contractually entitled to (and would be likely to) withdraw. That
would involve considerable prejudice to the petitioners.
[7] By contrast, it was contended that the
grant of the interim order would result in no prejudice to NCP. NCP
would simply be held bound by an agreement which they had entered into. NCP
would not have to carry out any works meantime. Even if NCP carried out some
work and incurred loss, they would be protected by their right to claim damages
from the petitioners, who sought the interim order periculo petentis.
If NCP were ultimately successful in their contention that Mr Murray was
an arbiter, then matters would revert back to the stage when Mr Murray was
requested to state a case for the court. Mr Murray's final determination
(issued in compliance with this court's interim order) could be
reduced. Few difficulties were envisaged in such a reduction, as (a) it would
be procedurally competent within the judicial review process (Rule of Court
58.4(b), the Answers being amended if necessary); (b) the other contracting
parties would have no locus to enter the process to oppose reduction;
and (c) counsel for the petitioners ultimately gave an undertaking that if NCP
were successful in their argument that Mr Murray was an arbiter who was
required to state a case, the petitioners would not oppose the reduction.
Matters would then revert to the stage when Mr Murray was about to state a
case, as if the final determination had never existed: cf Lord Pearson at page
397 of Miller & Son v Oliver & Boyd (1906) 8F 390
(although the Inner House in that case expressly reserved its opinion on the
matter); Russell on Arbitration (23rd ed) para 8-068; Hussman
(Europe) Limited v Pharaon [2003] 1 All ER (Comm) 879 at paras [81]
to [83]; and Lord Hope's article on Arbitration in the Stair Encyclopaedia (reissue)
paragraph 75. It was contended that the concern which arose in Fairlie
Yacht Slip Limited v Lumsden 1977 SLT (Notes) 41 did not arise.
[8] In my opinion, however, the issuing of the
final determination prior to 26 September 2009 in compliance with an interim
order of this court would result in a substantial risk of prejudice to NCP
which might be irreversible and might not be curable by any future award of
damages against the petitioners. The issuing of the final determination (a)
rules that the planning permission granted is satisfactory (a matter disputed
by NCP); and (b) by purifying the suspensive condition, removes NCP's right to
resile from the missives on the basis of dissatisfaction with the planning
permission granted. Thus in the future, if for any reason the final
determination were not reduced despite NCP's success in their reclaiming
motion, NCP would find themselves contractually bound to a project governed by
planning permission which was unacceptable to them. That situation would be
highly prejudicial to NCP, bearing in mind the parties' intention as recorded
in the missives that NCP should have the right to resile in the event that
satisfactory planning permission were not in place by 26 September 2009.
In view of the uncertainties of litigation, arbitration, and other
dispute-resolution procedures, in respect of the passage of time, arguments
presented, and decisions issued, and also in view of the fact that the project
would presumably be proceeding over the years on the basis (albeit subject to
challenge) that the planning permission granted was satisfactory, it cannot in
my view be said with any certainty that even if NCP were successful in their
reclaiming motion, the final determination would at some future time be reduced
by a court with the effect that matters should proceed as if that final
determination had never existed. Thus the interim order sought by the
petitioners would in my view give rise to a substantial risk of major prejudice
to NCP, a prejudice which would be in direct conflict with the express terms of
the parties' contract. By contrast, the possibility that the project might not
survive beyond 26 September 2009 was envisaged and provided for by the
contracting parties, on one view on the basis that if a fundamental
prerequisite (namely satisfactory planning permission) was not in place by that
date, unchallenged by disagreements, disputes, referrals to experts,
arbitrations or litigations, then parties should be entitled to withdraw from
the project.
[9] In the result, for all the above reasons, I
am of the opinion that the balance of convenience favours NCP, and that this
court should refuse to make the interim order sought in terms of
paragraph (c).
EXTRA DIVISION, INNER HOUSE, COURT OF SESSION
|
|
Lady PatonLord WoolmanLady Cosgrove
|
[2009] CSIH 72
OPINION OF LORD WOOLMAN
in the Petition of
MACDONALD ESTATES PLC
Petitioner;
For a review of a decision of Gordon Murray, architect dated 27th August 2009
_______
|
Respondent: Clark QC, Davies; Harper McLeod LLP
18 September 2009
[10] National Car Parks Limited ("NCP") has
marked a reclaiming motion against the decision of the Lord Ordinary dated 15 September 2009. Although the case has
been listed for early disposal, no date for the hearing in the Inner House has
yet been fixed. It is almost certain that no decision will be issued prior to 26 September 2009, which is the Longstop
Date set out in the missives.
[11] As the reclaiming motion suspends the Lord
Ordinary's interlocutor, Mr Murray cannot presently issue his final
determination. That means that the suspensive condition in the missives will
not be purified before the Longstop Date. NCP has, however, provided an
undertaking that it will not resile prior to the issue of the final
determination.
[12] Macdonald Estates Plc ("Macdonald") does not
accept that the undertaking sufficiently protects its position. Pending the
resolution of these proceedings, it seeks interim orders to regulate the
position. They are in the following terms:
"On behalf of the petitioners (1) to grant interim suspension of the decision of the first respondent dated 27 August that in determining the dispute between the parties he is acting as an Arbiter; and (2) for decree ad interim in terms of section 47 (2) of the Court of Session Act 1988 ordaining the first respondent to issue a determination in terms of his draft findings dated 6 August 2009 on a business day following that on which judgment is given prior to 10 am."
[13] NCP does not oppose the first order and
interim suspension can therefore be granted.
[14] With regard to the second order, the parties
directed their respective submissions toward the balance of convenience. In my
view, there are three factors to take into account.
[15] First, there is the question of prima
facie case. While Mr Clark accepted that there is one, he invited the
court not to look at its strength in determining the balance of convenience.
He pointed out that Mr Murray had acted on the opinion he had received
from experienced senior counsel. In my view, however, as the Lord Ordinary has
found in Macdonald's favour after hearing detailed argument over the course of
three days, it is in a stronger position than the normal litigant seeking interim
orders. It has a judicial determination in its favour. That is therefore a
factor which points toward the granting of the order.
[16] Secondly, Mr Lake stated that if the
order is not granted, the transaction will fall. He explained that three
further contracts have been entered into relative to the development. They are
also conditional upon the purification of the suspensive condition prior to the
Longstop Date. In two of the contracts, the third party will not agree to an
extension of time beyond 26 September 2009. I regard this as a very important
factor to take into account. By refusing to grant the order, the practical
effect would be to bring the development and the missives to an end. In that
event, Macdonald would suffer very great prejudice.
[17] Thirdly, there is the question of the
prejudice to NCP. If the reclaiming motion is refused, the contract will
simply proceed in accordance with the timetable set out in missives. If it is
granted, then the order will be recalled and NCP will have a claim against
Macdonald for any loss arising from its grant.
[18] Mr Clark submitted that if NCP succeeds
in the reclaiming motion , there could be uncertainty about setting aside any
determination issued in terms of the interim order. He pointed out that
reduction is an equitable remedy and that third party interests might be
involved. In response, Mr Lake gave an undertaking at the bar that in
such circumstances, Macdonald would not oppose the reduction of the
determination. In respect of third parties, Mr Lake pointed out that they
would have no locus to oppose reduction. He also informed the court that they
had been kept fully aware of the current proceedings.
[19] Having regard to all these factors, in my
view the balance tips decisively in favour of Macdonald. If the interim order
is not granted, the practical consequence will be very significant: the
transaction will fall. The grant of the order will keep matters entire. Any
detriment suffered by NCP is outweighed by the prejudice to Macdonald. I would
therefore be prepared to make the order sought in terms of section 47 (2).
EXTRA DIVISION, INNER HOUSE, COURT OF SESSION
|
|
Lady PatonLord WoolmanLady Cosgrove
|
[2009] CSIH 72
OPINION OF LADY COSGROVE
in the Petition of
MACDONALD ESTATES PLC
Petitioner;
For a review of a decision of Gordon Murray, architect dated 27th August 2009
_______
|
Respondent: Clark QC, Davies; Harper McLeod LLP
18 September 2009
[20] I agree with your Ladyship in the chair for
the reasons given. I have nothing to add.