BAILII is celebrating 24 years of free online access to the law! Would you consider making a contribution?

No donation is too small. If every visitor before 31 December gives just £1, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!



BAILII [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback]

Scottish Court of Session Decisions


You are here: BAILII >> Databases >> Scottish Court of Session Decisions >> LEONARDO HOTEL MANAGEMENT (UK) LTD AGAINST GALLIFORD TRY BUILDING 2014 LTD AND ANOTHER [2024] ScotCS CSOH_43 (19 April 2024)
URL: http://www.bailii.org/scot/cases/ScotCS/2024/2024_CSOH_43.html
Cite as: [2024] ScotCS CSOH_43, [2024] CSOH 43

[New search] [Printable PDF version] [Help]


OUTER HOUSE, COURT OF SESSION
[2024] CSOH 43
CA41/23
OPINION OF LORD RICHARDSON
In the cause
LEONARDO HOTEL MANAGEMENT (UK) LIMITED
Pursuer
against
GALLIFORD TRY BUILDING 2014 LIMITED
First Defender
BUILDING DESIGN PARTNERSHIP LIMITED
Second Defender
Pursuer: T Young; MacRoberts LLP
First Defender: MacColl KC; Clyde & Co LLP
Second Defender: D Thomson KC, Hamilton; Kennedys
19 April 2024
Introduction
[1]
This case concerns a claim by the proprietor of the Leonardo Inn Hotel, Union
Square, Aberdeen. It is a claim for alleged defects arising at the hotel.
[2]
The pursuer is the current tenant of the property. The first defender was the design
and build contractor that was instructed by the landlord of the property, Union Square
Developments Limited, in connection with its development. The second defender was the
landlord's architect.
2
[3]
I heard the case at debate. Both defenders advanced two separate arguments. First,
the defenders argued that the pursuer's case against each of them had prescribed in terms of
sections 6 and 11 of the Prescription and Limitation (Scotland) Act 1973. Second, each of the
defenders challenged the relevancy and specification of the case that the pursuer had plead
against them.
Background
[4]
The landlord and the first defender entered into a building contract on 19 December
2006. The building contract was subsequently the subject of certain Minutes of Variation.
The works undertaken by the first defender in terms of the building contract included the
design and construction of a bus and railway station re-development together with a retail
and leisure development. The latter included the design and construction of the hotel
including, in particular for present purposes, the design and construction of the cladding of
the various elevations of the property.
[5]
On 11 January 2007, the landlord entered into a memorandum of agreement in
relation to the appointment of the second defender. In terms of that agreement, the second
defender undertook various obligations to the landlord including to provide architectural
services in respect of the Union Square development and to carry out those services using:
"...the reasonable skill, care and diligence expected of an appropriately qualified and
competent architect who is experienced in the provision of services of a similar size,
scope and complexity [in relation to developments equivalent to the present
development]..."
On 22 July 2007, the landlord and the first and second defenders entered into a novation
agreement in terms of which the first defender took over the second defender's appointment
from the landlord.
3
[6]
Subsequently, on 16 July 2008, the first defender granted a collateral warranty in
favour of the pursuer. In terms of that warranty, the first defender undertook, among other
things, to carry out and complete the development in conformity with the building contract.
On 22 July 2008, the second defender also granted a collateral warranty in favour of the
pursuer. In terms of that warranty, the second defender undertook to the pursuer that it had
duly performed and would continue so to perform its obligations under its appointment in
respect of the development whether before or after the novation agreement.
[7]
The collateral warranty granted by the first defender provided that, in the event of a
breach, the first defender would be entitled to rely, in any proceedings by the pursuer, on
any limitation or defence, excluding rights of set-off, retention and counterclaim, as it would
have had against the landlord (clause 1 of the warranty dated 16 July 2008). The warranty
granted by the second defender provided that, excluding the second defender's rights of
set-off, retention and counterclaim, the second defender would have no greater liability to
the pursuer under the warranty than it owed under its appointment in respect of the
development (clause 2.2).
[8]
Practical completion of that part of the development which included the hotel was
certified on 18 February 2009. The hotel was leased by the landlord to the pursuer by way of
a lease dated 8 December 2009. In terms of the lease, the pursuer undertook a full repairing
obligation: clause 3.7.1 of the lease obliged the pursuer:
"... to keep the Property in good and substantial repair and condition and tidy and
clean and ... maintained to the reasonable satisfaction of the Landlords and in whole
or in part, when necessary, to rebuild, reinstate or renew the same irrespective of the
cause of damage, destruction, deterioration or decay necessitating such repair,
rebuilding, reinstatement or renewal as aforesaid. ..."
4
The pursuer's obligations under the lease also included the following:
"To permit the Landlords or the Managing Agents or any of them with or without
workmen and others at all reasonable times in a day (except in the case of
emergency) upon giving to the Tenants not less than two Working Days' prior notice
thereof (except in the case of emergency) to enter upon the Property for the purpose
of examining the state and condition thereof and, in case any defect, default or want
of maintenance, repair, rebuilding, reinstatement, renewal or decoration or
cleanliness shall appear for which the Tenants are liable under the obligations herein
contained, upon notice thereof in writing being given to the Tenants, to cause the
same to be made good, maintained, repaired, rebuilt, reinstated, renewed, decorated
or cleaned in compliance with the said obligations within such reasonable period of
time as is specified in the notice..." (clause 3.11)
[9]
In the present proceedings, the pursuer alleges that the hotel's cladding system is
defective. The pursuer avers that the defects were caused by, or at least materially
contributed to by, breaches of the obligations owed to it by the defenders both as a matter of
contract and in delict. The pursuer seeks the cost of repairing the cladding which it
contends it is obliged, under the lease, to carry out. The present proceedings were raised in
February 2021.
The prescription arguments
The pursuer's averments
[10]
The pursuer's pleadings in respect of prescription are all contained in Article 13 of
condescendence. The material parts of the pursuer's averments in respect of the application
of sections 6 and 11 of the 1973 Act are in the following terms:
"With reference to the defenders' averments anent prescription, explained and
averred that entering the Lease was not loss, injury and damage for the purposes of
sec. 11 (1) of the Prescription and Limitation (Scotland) Act 1973 (cap. 52) (the
`1973 Act'). The pursuer did not incur wasted expenditure in doing so. The pursuer
did not acquire ownership of an asset that was worth less than it expected. The
Cladding Defects were latent defects. They were not visible defects requiring repair.
The need to repair them was not inevitable from the point of entering the Lease. The
pursuer did not in fact suffer loss, injury, and damage until it came under an
obligation to repair the Cladding Defects. That obligation only arose when the state
5
of disrepair arising from the Cladding Defects became known about. The discovery
of the Cladding Defects was prompted by inspections of the Property conducted by
the Landlord after the Grenfell tower fire on 14 June 2017. At the very earliest, the
Landlord was aware of some (but not all) of the Cladding Defects around
18 September 2017. On or around that date, Wintech produced a report of a cladding
survey conducted on the Property. At the very earliest, the pursuer became aware of
some (but not all) of the Cladding Defects around 16 December 2020 when they were
informed about them by the Landlord following the Landlord's investigation."
[11]
In respect of section 11(3), the pursuer's pleadings were as follows:
"Esto the pursuer did suffer loss, injury and damage for the purpose of sec. 11 (1) of
the 1973 Act more than 5 years prior to the raising of this action, which is denied,
explained and averred that the pursuer was not aware, and could not with
reasonable diligence have become aware, of having suffered such loss, injury and
damage until, at the earliest, 16 December 2020. Reference is made to sec. 11 (3) of the
1973 Act."
[12]
In respect of section 6(4), the pursuer averred as follows in respect of the first
defender:
"Separatim, and in any event, the Landlord was induced to refrain from making any
claim for reparation in respect of the Cladding Defects against the first defender
between practical completion of the Works in February 2009 and around
18 September 2017. The Landlord et separatim the first defender were induced to
refrain from making any claim for reparation against the second defender until
around 18 September 2017. The pursuer was also induced to refrain from making
any claim for reparation in respect of the Cladding Defects against the first defender
between entering the Lease in December 2009 and around 16 December 2020. This
was due to errors induced by the first defender under and in terms of sec. 6 (4) of the
1973 Act. Accordingly, these periods do not fall to be reckoned as part of any
prescriptive period in respect of either the Landlord or the pursuer. In particular, the
first defender was under contractual duties to identify and report defects in the
Works such as the Cladding Defects to the Landlord and Sweett as the Employer's
Agent. Reference is made to Clauses 2.5.6 and 5.3.1, and the `Management of the
Works', `Quality Standards / Control', and `Building and Accommodation
Requirements' sections of the Employer's Requirements in the Building Contract.
Without prejudice to that generality, the first defender was expressly obliged to
report any defects in the existing construction to Sweett as Employer's Agent
without delay and obtain instructions before proceeding with the work. The first
defender omitted to advise, inform, or otherwise draw the Landlord and/or Sweett's
attention to the Cladding Defects. That omission contained an implied
6
representation that no such defects existed. Further, the pursuer is unaware of any
sums outstanding under the Building Contract. In the circumstances, it is believed
and averred that the first defender continued to apply for payments under the
Building Contract. Those payments could not have been properly claimed in respect
of that part of the Works comprising the Cladding Defects. In applying for payment,
the first defender impliedly represented that the Works had been properly done.
The Landlord had no reason to suspect that was not the case. Further, and in any
event, in the Contractor's Collateral Warranty, the first defender warranted to the
pursuer inter alia that they had carried out and completed the Development in
conformity with the Building Contract; complied with, observed, and performed the
obligations of the Contractor in the Building Contract. Reference is made to
Clause 1.1 ­ 1.4 of the Contractor's Collateral Warranty. In warranting to the pursuer
they had complied with their obligations when in fact they had not done so, the
pursuer was induced to believe that the first defender had complied with its
obligations and that no defects such as the Cladding Defects existed in the Property.
By all of these omissions and acts, the first defender represented to, and induced a
belief in, both the pursuer, and the Landlord, that they had each complied with their
obligations and that no defects such as the Cladding Defects existed in the Property.
That was an error. As a result of that error, both the Landlord and the pursuer
refrained from making any claim for reparation against the first defender."
[13]
Finally, the pursuer made the following averments in respect of section 6(4) in
relation to the second defender:
"Separatim, and in any event, the pursuer was induced to refrain from making any
claim for reparation in respect of the defects hereinbefore condescended upon
against the second defender between entering the Lease in December 2010 and
around 16 December 2020. This was due to an error induced by the second defender
under and in terms of sec. 6 (4) of the 1973 Act. Accordingly, that period does not
fall to be reckoned as part of the prescriptive period. In particular, the second
defender was under contractual duties to identify and report defects in the Works
such as the Cladding Defects to inter alios the Landlord and first defender. Reference
is made to, Clause 9.2, 9.4, 11.4, 13.2, 16, 37.3 and Paragraphs 7, 27, 34, 35, 49, 51, 53,
82 of Part 2 of Part 1 of the Schedule to the Architect's Appointment; Clauses 7.1 - 7.3
of the Architect's Novation Agreement. The second defender omitted to advise,
inform, or otherwise draw the Landlord and/or the first defender's attention to the
Cladding Defects. Further, the pursuer is unaware of any sums being outstanding to
any of the defenders under the various agreements hereinbefore condescended upon.
In the circumstances, it is believed and averred that they each claimed payment of
the substantial remuneration due to them under each of the relevant Appointments.
Further, in the Architect's Collateral Warranty, the second defender warranted to the
pursuer that they had duly performed and observed all of the terms of the relevant
7
Appointment. Reference is made to Clause 2.1 of the Architect's Collateral
Warranties. In representing to the pursuer they had complied with their obligations
when in fact they had not done so, the pursuer was induced to believe that they had
complied with their obligations and no defects such as the Cladding Defects existed
in the Property. By these omissions and acts, the second defender represented to,
and induced a belief in, the pursuer, the Landlord, and the first defender that they
had complied with their obligations and that no defects such as the Cladding Defects
existed in the Property. That was an error. As a result of that error, the pursuer, the
Landlords, and the first defender refrained from making any claim for reparation
against the second defender in respect of the Cladding Defects."
The defenders' arguments
[14]
The defenders argued that, in terms of sections 6 and 11(1) of the Prescription and
Limitation (Scotland) Act 1973, the pursuer's case had prime facie prescribed. The defenders
argued further that that prime facie position was not altered by the application of the terms of
either section 11(3) or section 6(4) of the 1973 Act.
[15]
The issue of prescription arose in two ways. First, it applied to the pursuer's claim.
Second, insofar as the pursuer's claim relied on obligations owed to it by the defenders in
terms of the collateral warranties, it was also necessary to consider the issue of prescription
from the perspective of the original employers of each of the defenders. In the case of the
first defender, that was the original developer ­ the landlord. In the case of the second
defender, it was the landlord and then, following the novation agreement, the first defender.
The pursuer's claim
[16]
On the pursuer's averments, it had suffered a loss as soon as it had entered into the
lease on 8 December 2009. That date was after practical completion had been certified and
was more than five years before the present proceedings had been raised. On this date, the
pursuer became responsible for repairing the cladding defects which formed the basis of the
present action in terms of clause 3.7.1. This point could be tested by asking whether,
8
immediately after the pursuer had signed the lease, it would have been possible for the
landlord to enforce the repairing obligation in the lease against the pursuer in respect of the
alleged cladding defects. On the basis of the pursuer's averments, the answer to that
question was yes.
[17]
It was submitted that this represented a straightforward application of the law of
obligations. Clause 3.7.1 imposed an obligation on the pursuer "to keep the Property in
good and substantial repair". With such an obligation, all that was required for it to arise
was that the property was out of that condition (Scottish Widows Services Ltd v Harmon/CRM
Facades Limited (in liquidation) 2010 SLT 1102 at paragraph 33). In the present case, there was
no dispute that at the time that the pursuer entered the lease, the disrepair, being the
cladding defects, existed. Viewed from this perspective, it was clear that, contrary to its
averments, in entering the lease, the pursuer had acquired an asset which was worth
significantly less than it had anticipated. This was because entering the lease carried with it
the onerous repairing obligations.
[18]
Accordingly, on the basis of the pursuer's averments, in terms of sections 6 and 11(1)
of the 1973 Act, the five year prescriptive period started running from 8 December 2009.
On the pursuer's averments, by this date there was a concurrence of the alleged failure
(whether breach of contract or delict) by the defenders, and the loss said to have been caused
by that failure.
[19]
In terms of section 11(3) of the 1973 Act, the fact that the pursuer averred that it was
unaware of the position until later was irrelevant (see paragraph 11). The pursuer's loss
arose from entering into the lease. The pursuer was perfectly well aware of the terms of the
lease including the tenant's obligation to repair. The defenders relied on Lord Hodge's
judgment in Gordon's Trustees v Campbell Riddell Breeze Paterson LLP 2017 SLT 1287 at
9
paragraphs 20 to 23. The test was objective and Lord Hodge had recognised that it might
seem harsh for creditors but it produced certainty.
[20]
Turning to section 6(4) of the 1973 Act, the defenders emphasised that the pursuer
required to aver that there was a period during which the pursuer had been induced not to
make a claim as a result of an error induced by the words or conduct of the debtor or anyone
acting on behalf of the debtor. This was subject to the proviso that any period during which
the creditor could with reasonable diligence have discovered the error, was to be
discounted.
[21]
In relation to both defenders, the pursuer relied upon the fact that each of the
defenders had granted a collateral warranty in favour of the pursuer. The pursuer averred
in the case of the defenders that each had warranted that it had observed and performed its
respective obligations under the building contract and the appointment. However, these
averments were inconsistent with the sequence of events. In both cases, the granting of the
collateral warranties pre-dated the achievement of practical completion (see paragraphs 6
to 8 above). The pursuer made no averment as to when the alleged breaches by the
defenders in respect of the cladding had occurred and, in particular, whether those breaches
occurred before or after the granting of the warranties.
[22]
In respect of the achievement of completion of the development, the warranties each
contained a promise as to future conduct. The defenders were warranting that they would
continue to comply with their respective obligations under the building contract and
appointment. As such, the warranties could not affect the running of prescription through
section 6(4). If it were the case that a prospective statement ­ a statement which pre-dated
the coming into existence of the claim ­ could "induce an error" on the part of the creditor in
terms of section 6(4) then, it was contended, a coach and horses would be driven through the
10
law of prescription. On this basis, the warranties granted by the defenders were no different
to any normal contractual stipulation in terms of which one party undertook to another
party to act in a particular way. If section 6(4) were to be construed as contended for by the
pursuer, it would have a very wide impact, potentially affecting all contractual
relationships. It was submitted that this could not be the intention of parliament. In relation
to the pursuer's reliance on Rowan Timber Supplies (Scotland) Limited v Scottish Water Business
Stream Limited [2011] CSIH 26, the defenders submitted that the facts of this case were
wholly different and it did not assist the pursuer on the issue of the timing of conduct relied
upon.
[23]
The defenders also submitted that the averments in respect of the alleged conduct by
the defenders which related not to the pursuer but to others could not be relied on by the
pursuer in relation to section 6(4). The pursuer made averments about failures by the first
defender to report the cladding defects to the landlord and to the employer's agent, Sweett.
In the same vein, the pursuer made averments concerning failures by the second defender to
report defects to the landlord and the first defender. These averments could not be relevant
to inducement of an error on the part of the pursuer.
[24]
In the same way, the averments made by the pursuer in respect of alleged conduct by
the defenders in granting the collateral warranties could not be relied by the pursuer in
relation to the issue of prescription viewed from the perspective of the original employers of
each of the defenders.
[25]
In light of these averments, the defenders did not have fair notice of the case being
advanced against them. That part of the pursuer's case which relied on section 6(4) was thus
contradictory, irrelevant and ought to be excluded from probation.
11
Claims by the employers
[26]
Senior counsel for the first defender submitted that, as the pursuer's case against it
depended on the collateral warranty granted by the first defender, the starting point was
that the collateral warranty would be subject to the same time-bar as applied under the
building contract (see [7] above). Accordingly, if claims against the first defender under the
building contract had been extinguished by prescription, then the pursuer would be barred,
as a matter of contract on the basis of the terms of the collateral warranty, from bringing a
like claim against the first defender (British Overseas Bank Nominees Ltd v Stewart Milne Group
Ltd 2020 SC 24 (IH) at paragraphs 14 to 16). Senior counsel for the second defender
essentially adopted the same argument based on the terms of the collateral warranty granted
by the second defender (see [7] above).
[27]
The prescriptive period for any claim by the landlord against both of the defenders
had, on the face of the pursuer's pleadings, commenced at the latest on 18 February
2009 - the date of practical completion of the section of works which included the hotel.
Thereafter, essentially, for the same reasons advanced in respect of the pursuer's claim, the
defenders submitted that the pursuer had not averred a relevant case in relation to either
section 11(3) or section 6(4). In respect of the former, on the factual basis upon which the
pursuer's case proceeded, the landlord would undoubtedly have incurred wasted
expenditure in respect of the development prior to practical completion of the building
contract as a whole on 29 October 2009. In respect of the latter, senior counsel referred back
to the submissions made in respect of the pursuer's averments in relation to the prescription
issues arising from its own claim.
[28]
Finally, senior counsel for the first defender also objected to the averments which the
pursuer had made concerning the fact that the pursuer was unaware of any sums being
12
outstanding under the building contract (see above at [12]). The pursuer sought to use this
as a basis for seeking to infer ­ through the use of the formulation "Believed and
averred" - that the first defender continued to apply for payments under the building
contract. However, the pursuer was not actually offering to prove that any payments were,
in fact, either applied for or made. The pursuer's lack of awareness as to sums outstanding
did not give rise to a necessary inference that applications were either made or paid. These
averments were irrelevant and ought to be excluded from probation.
The pursuer's response
[29]
Counsel for the pursuer submitted that, having heard the arguments advanced on
behalf of the defenders, he did not consider that there was a significant difference between
the parties as to the relevant legal principles to be applied. Rather, the parties differed as to
the consequence for the pursuer's case of the application of those principles.
[30]
Counsel also accepted that, as its case was based on the collateral warranties granted
by each of the defenders, the pursuer required to address potential prescription issues
arising both in respect of its case and which might arise in respect of a case brought by either
of the employers of the defenders under the building contract or appointment respectively.
The pursuer's claim
[31]
In relation to its own claim, the pursuer's position was, first of all, that the conclusion
of lease was not loss for the purposes of section 11(1) of the 1973 Act. Counsel referred to
the analysis of the Supreme Court decision in Gordon's Trustees (above at [19]) by the Inner
House in WPH Developments Ltd v Young and Gault LLP 2022 SC 28 (in particular, at
paragraphs 29 to 31). Lord Malcolm, in giving the opinion of the court, had stressed that, for
13
the purposes of section 11(3), what was necessary was contemporaneous knowledge of the
objective facts which constituted the loss or detriment. It was not necessary for there to be
any knowledge of the circumstances which rendered it detrimental.
[32]
Against this background, the pursuer's primary position was that entry into the lease
did not constitute loss because, at the point of entry, loss was not inevitable. Loss only
manifested itself at the point at which the pursuer's obligation to carry out repairs in terms
of the lease was triggered. This analysis was consistent with the nature of the relevant
repairing obligation, clause 3.7.1 (above at [8]): the pursuer was required to carry out work
"when necessary". The obligation was onerous and ought not to be given an expansive
interpretation (see Westbury Estates Ltd v The Royal Bank of Scotland Plc 2006 SLT 1143,
paragraph 33 (Lord Reed)). Construed in this way, the pursuer's obligation under the lease
was contingent on the necessity becoming apparent during the currency of the lease.
[33]
The pursuer's secondary position was that even if, as a matter of analysis, the
pursuer had suffered a loss on entering the lease and the requirements of section 11(1) were
fulfilled, it could not be said that the pursuer had the knowledge required for section 11(3).
This was because the pursuer did not have either actual or constructive knowledge of the
objective facts which constituted the loss. The pursuer was not in the equivalent position to
someone purchasing an asset for what turns out to have been more than its market value or
incurring expenditure which later transpires to have been wasted (cf Gordon's Trustees
(above) at paragraph 21). The most that could be said was that the pursuer knew that it was
subject to the repairing obligation. However, that was not sufficient. In order to know that
loss had occurred, the pursuer required to know, either actually or constructively, that the
cladding defects existed. Accordingly, on the basis of this secondary position, the
commencement of the prescriptive period was, on the pursuer's averments, deferred until
14
16 December 2020 when the pursuer was informed by the landlord of the existence of the
cladding defects.
[34]
In respect of section 6(4), counsel for the pursuer submitted that the pursuer's
pleadings were sufficiently clear. In respect of the pursuer's own claim, the pursuer relied
solely on representations which had been made to it. In other words, the pursuer relied
upon the representations which both defenders had made in granting collateral warranties
to it.
[35]
In respect of the argument advanced by the defenders based on the timing of the
warranties, counsel submitted that it was somewhat unsatisfactory that this argument had
only been fully developed during the course of oral submission at the debate before me.
This issue had not been raised by either defender either in their respective pleadings or in
the notes of argument. Accordingly, counsel submitted that were I to find that the timing of
the works said to give rise to the cladding defects in relation to the granting of the
warranties was critical, he would seek an opportunity to address this issue in the pursuer's
pleadings.
[36]
However, the pursuer's position was that the defenders' argument was misconceived
in that the defenders took an unduly restrictive approach to the section 6(4). In this regard,
the pursuer referred to Rowan Timber Supplies (as above at [22]). The facts of that case
concerned claims by the pursuer for the repayment of charges which had been levied, in
error, for many years by the defender. The pursuer's claim for repayment was met by a plea
of prescription. The pursuer, in turn, responded to this plea by arguing that the defender
had induced it, in terms of section 6(4), to refrain from claiming by repeatedly rendering
notices to the pursuer in respect of the charges. The defender challenged the relevancy of
15
this approach. However, the defender's argument was rejected by the Inner House. In the
view of the Lord President, delivering the opinion of the court, it was a matter for proof:
"[17] The only conduct of Scottish Water relied on by the [pursuers] is their issuing
of the charge notices. It was argued for the [defenders] that each obligation of
repetition had to be viewed distinctly and that conduct inducing the creditor `to
refrain from making a relevant claim in relation to the obligation` must, logically, be
conduct which post-dates the coming into existence of that obligation. As each
obligation came into existence only after the charge had been raised and paid, the
raising of the charge could not constitute a relevant inducement.
[18] In our view this submission adopts an unduly restrictive approach to the
statutory provision and to the [pursuers'] averments. It will in the end be for the
[pursuers] to prove what in fact induced them to refrain from making their several
claims earlier than they did. But it would be within the scope of their averments to
seek to establish that the periodical and repeated issuing of charges (carrying the
implication that the sums charged were due) induced them to refrain from pursuing
a claim for repetition of a sum earlier charged and paid. It may also be that, looking
at each transaction distinctly, the implicit representation contained in the notice was
such that it not only induced payment but also subsequently induced the error which
in turn induced the [pursuers] to refrain from making a relevant claim in repetition.
These issues are properly for proof."
[37]
Counsel submitted that the pursuer in the present case could not be in a worse
position than the pursuer in Rowan Timber Supplies on the basis that in this case the
representation was express whereas in that case the representation, in the form of the
rendering of the notices, was implicit.
Claims by the employers
[38]
The pursuer accepted that the prescriptive period for the claims against the first
defender and the second defender in terms of the building contract and appointment,
respectively, would have started by 18 February 2009, that being the date of practical
completion of the hotel.
[39]
In respect of the claim by the landlord against the first defender, the pursuer pled
two alternative defences. First, the pursuer submitted that the landlord was unaware of the
16
cladding defects until after it had carried out investigations following the Grenfell Tower
fire. The pursuer averred that the earliest that the landlord was aware of the cladding
defects was 18 September 2017. On this basis, the pursuer submitted that the
commencement of the prescriptive period fell to be postponed until this date in terms of
section 11(3). Counsel for the pursuer argued that in claims against a building contractor,
payments to the contractor itself did not fall to be characterised as a loss or as "wasted
expenditure". These payments were properly to be understood to be payments made under
the contract (see Loretto Housing Association Limited v Cruden Building and Renewals
Limited [2019] CSOH 78).
[40]
Secondly, the pursuer averred that the landlord had been induced not to claim
against the first defender as a result of the first defender's actions in failing to identify or
report the cladding defects during the currency of the works. On this basis, the pursuer
averred that a period between practical completion of the works in February 2009 and
around 18 September 2017 fell to be discounted from the prescriptive period in terms of
section 6(4).
[41]
In this regard, counsel submitted that the first defender's challenge to the pursuer's
averments to the effect that it was unaware of any sums outstanding under the building
contract was surprising. Counsel submitted that, in the circumstances, it was reasonable for
the pursuer to infer that first defender had applied for and been paid under the building
contract. Given that the hotel had been completed, this inference seemed more likely than
that the first defender had carried out its work gratuitously.
[42]
In respect of the second defender, the pursuer again relied upon its averments that
the first defender had been induced not to claim as a result of the actions of the second
defender during the course of the works in failing to identify and report defects including
17
the cladding defects. On this basis, the pursuer submitted that it had pled a relevant case in
terms of section 6(4) of the 1973 Act.
Decision on prescription arguments
[43]
The issue before me in relation to prescription is whether the pursuer has averred a
relevant case which ought to be admitted to probation in respect of each of the defenders.
[44]
That issue can be further broken down. First, it is necessary to consider the issues of
prescription which arise from the pursuer's case against each of the defenders. Second,
there are the issues of prescription which arise as matter of contractual bar because the
pursuer's case is founded on the collateral warranties granted by each of the defenders.
Resolution of the issues which arise as an issue of contractual bar require the issue of
prescription to be considered from the perspective of the employers of the first and second
defender. These are, respectively the landlord and, following the novation of the second
defender's appointment, the first defender.
The pursuer's case
[45]
In relation to the pursuer's case, the first task is to determine when, in terms of
section 11(1) of the 1973 Act, the prescriptive period commenced in respect of each of the
defenders. That involves establishing when there is a concurrence of a legal wrong and loss
caused by that wrong.
[46]
There is no dispute in respect of the first of these. In the present case, it is accepted
that the alleged breaches by each of the defenders must have occurred prior to the date on
which the hotel was practically complete on 18 February 2009.
18
[47]
In respect of the second, the pursuer avers that it suffered no loss until "it came
under an obligation to repair" the cladding defects and, further, that this obligation only
arose when the state of disrepair arising from the cladding defects became apparent. On the
other hand, the defenders submit that, as a matter of law and on the pursuer's own
averments, this is wrong. The defenders contend that, on the hypothesis upon which the
pursuer's case proceeds, the pursuer suffered loss when it entered into a lease of the hotel on
8 December 2009. That is because, so the defenders argue, of the coincidence of two factors.
First, as soon as the pursuer entered into the lease of the hotel, it became obliged, in terms of
clause 3.7.1 of lease "...to keep the Property in good and substantial repair and condition..."
Second, on 8 December 2009, the hotel already contained the cladding defects which, it is
accepted, must have been present at practical completion.
[48]
I consider that the defenders' analysis is correct on this point. I reach this conclusion
primarily because I consider that, properly construed, the obligation in clause 3.7.1 to keep
the property in good and substantial repair is triggered as soon as the property is out of that
condition (see Scottish Widows (above at [17]) at paragraph 33). This part of the obligation in
clause 3.7.1 is not qualified by the phrase "when necessary" as is the case in respect of the
obligation "to rebuild, repair or renew" which appears later on in the clause. Further, unlike
other clauses in the lease, there is no requirement for the landlord to notify the pursuer or
otherwise trigger the pursuer's obligation (cf clause 3.11). I do not consider that the wording
of the clause, which begins with the words "At all times during [the term of the lease]",
provides any support for deferring the pursuer's obligation until the state of disrepair
becomes apparent.
19
[49]
On the basis of this finding, it becomes necessary to consider whether the pursuer
has relevantly averred a case in respect of either or both sections 11(3) and 6(4) of the
1973 Act.
[50]
I consider that the pursuer has done so in respect of both sections.
[51]
In respect of section 11(3), the pursuer avers that it was not aware and could not with
reasonable diligence have become aware that it had suffered a loss until 16 December 2020
which was the date when the pursuer was informed by the landlord of the cladding defects
(see paragraph 11). The defenders challenge the relevancy of this averment on the basis that
it falls foul of Lord Hodge's analysis in Gordon's Trustees: the pursuer's loss arises from the
pursuer's agreement of the lease and there can be no doubt, so the defenders contend, that
the pursuer was aware of that.
[52]
As Lord Hodge makes clear in Gordon's Trustees, the wording of section 11(3)
postpones the commencement of the prescriptive period until the creditor first becomes
aware, or could with reasonable diligence have become aware, of the objective fact of the
loss or detriment (at paragraphs 19 and 20). Importantly, in terms of section 11(3), a creditor
does not require to know that he or she has suffered a detriment or that something has gone
awry. As Lord Hodge puts it: "It is sufficient that a creditor is aware that he or she has not
obtained something which the creditor had sought or that he or she has incurred
expenditure." (paragraph 21).
[53]
In the present case, I do not consider that the objective facts of the pursuer's loss can
be said to have been comprised solely by the pursuer's agreement to the terms of the lease.
The pursuer's loss arises not solely because it has an obligation in terms of clause 3.7.1 of the
lease to carry out repairs. The loss arises because the pursuer has this obligation and the
hotel contains the alleged cladding defects which require to be repaired.
20
[54]
Therefore, on the pursuer's averments, it was not aware, either actually or
constructively, of the objective facts which constituted its loss. That is because knowledge of
loss required knowledge both of the obligation to repair contained in the lease and also of
the existence of the alleged defect which required to be repaired. While the pursuer
remained in ignorance of the need to carry out repairs, it did not have knowledge of the
objective facts which constituted its alleged loss. Unlike the examples given by Lord Hodge
in paragraph 21 of Gordon's Trustees, there is no question in the present case that the pursuer
was aware that it had failed to obtained something which it had sought or that it had
incurred expenditure.
[55]
In any event, I also consider that the pursuer has averred a relevant case in respect of
section 6(4). As I understood the defenders' arguments, two arguments were advanced on
this point.
[56]
First the defenders argued that the pursuer's averments were irrelevant because they
relied, in respect of the question of the prescription of the pursuer's own case, on conduct
which was not directed to the pursuer. Read fairly, and in light of the pursuer's
submissions, I do not consider that there is any such reliance by the pursuer. The averments
made by the pursuer in respect of section 6(4) clearly address the issue of prescription both
as it arises in relation to the pursuer's own case and, separately, as it arises in respect of each
of the defenders' employers as a matter of contractual bar. To the extent that the pursuer
has made averments about conduct directed towards: the landlord; Sweett, the employer's
agent; and/or the first defender, it is clear that these are pled in support of the pursuer's
case based on section 6(4) which relates to the prescription in the context of contractual bar.
On this basis, there is no lack of fair notice of the pursuer's position.
21
[57]
Second, the defenders argue that the pursuer's averments in respect of the collateral
warranties granted by each of them are irrelevant essentially because the granting of these
warranties pre-dates the achievement of practical completion.
[58]
The defenders are undoubtedly correct that the pursuer's pleadings in respect of the
collateral warranties are inconsistent with the sequence of events in which the granting of
those warranties pre-dated the practical completion of the hotel (see paragraphs 12 and 13
above). In this regard, I also note that this issue was not one which was raised by either of
the defenders until oral submissions were made on behalf of the defenders in the course of
the debate before me.
[59]
However, I do not consider that this issue materially affects the relevance of this part
of the pursuer's case. In short, it is clear from the pursuer's averments that it contends that it
was, as a result of the granting of the collateral warranties, induced to believe that both
defenders had complied with their respective obligations and therefore refrained from
making a claim. Although the warranties were granted prior to practical completion, the
undertakings made by each defender to the pursuer in respect of the development related
both to what they had already done and what they were yet to do in order to achieve
completion.
[60]
As the Lord President made clear in Rowan Timber Supplies (above at [36]), the
wording of section 6(4) does not support the restrictive construction argued for by the
defenders: the conduct relied upon by the creditor need not post-date the coming into
existence of the obligation. Following the approach of the Inner House in Rowan Timber
Supplies, it will be a matter for the pursuer to prove what in fact induced it to refrain from
claiming. It would be open to the pursuer, on the basis of its averments, to prove that it was
induced to believe that the cladding defects did not exist as a result of the representations
22
made as to both past and future conduct in the collateral warranties granted by each of the
defenders. These are matters properly for proof.
[61]
For completeness, I also reject the submissions, made on behalf of the defenders, that
the construction of section 6(4) argued for by the pursuer and approved by the Inner House
in Rowan Timber Supplies will have a dramatic impact on the law of prescription. First, I note
that Rowan Timber Supplies has now been followed in a series of cases, see most recently:
Scottish Ministers v Scotland Gas Networks plc [2023] CSOH 77; Highlands and Islands
Enterprise v Galliford Try Infrastructure Limited [2023] CSOH 21; Legal and General Assurance
(Pensions Management) Limited v Halliday Fraser Munro [2023] CSOH 81; and Loretto Housing
Association Limited v Cruden Building and Renewals Limited [2019] CSOH 78. I do not consider
that this construction, which flows from the plain words of section 6(4), has resulted in any
dramatic change to the understanding of the law of prescription. Second, as to the principle
underlying the construction of section 6(4), I respectfully agree with the analysis of
Lord Harrower in Legal and General Assurance at paragraphs 33 and 34 (which was issued
shortly after the debate I heard).
Claims by the employers
[62]
In the debate before me, there was no dispute that the pursuer's claims, which were
founded on the collateral warranties granted by each of the defenders, would also be subject
to the same time bar which applied under, respectively, the building contract in respect of
the first defender, and the appointment in respect of the second defender (British Overseas
Bank Nominees, as at [26] above, paragraphs 14 to 16).
23
[63]
The pursuer also accepted that the prescriptive period in terms of the building
contract and appointment, respectively, would have started by 18 February 2009, being the
date of practical completion of the hotel.
[64]
Accordingly, for present purposes, the question is whether the pursuer has pled a
relevant case in respect of either section 11(3) or section 6(4) of the 1973 Act. Again, I am
satisfied that the pursuer has done so.
[65]
In respect of section 11(3), the pursuer only makes the argument in relation to the
claim against the first defender. The pursuer's position is that the landlord was unaware of
the cladding defects until June 2017 when the property was inspected following the Grenfell
Tower fire. The first defender argues that, on the factual basis upon which it proceeds, the
landlord would have incurred wasted expenditure prior to practical completion and would
necessarily have been aware that it had incurred such expenditure. However, that
characterisation is denied by the pursuer.
[66]
I do not consider that I can conclude, without hearing evidence, that the pursuer's
averments made to engage section 11(3) in respect of a claim by the landlord, if proved, will
necessarily fail. The pursuer contends that the payments made by the landlord under the
building contract did not fall to be characterised as wasted expenditure because they were
being made under and in terms of that contract. I note that none of the parties' pleadings
address the nature of the landlord's expenditure in any detail. In the circumstances, without
an inquiry into the facts, I am not persuaded that I ought to determine that the pursuer's
position is obviously wrong (cf Loretto Housing Association at paragraphs 34, 35 and 54).
[67]
However, even if I am wrong about that, I consider that the pursuer has pled a
relevant case to engage section 6(4) in respect of both of the defenders. The criticisms
advanced by the defenders were essentially pleading points.
24
[68]
The principal argument was that the pursuer's pleadings relied on averments in
respect of the claims by the landlord on conduct which was directed towards the pursuer.
This was essentially the same argument with which I have already dealt above in the context
of the pursuer's own claim (see paragraph 56 above). As I have noted above, I consider that
the pursuer's averments are sufficiently clear: the conduct relied upon in respect of the
claim by the landlord against the first defender and by the landlord and/or the first defender
against the second defender, is conduct which was directed to those parties. In other words,
I do not understand the pursuer to be relying upon the granting of the collateral warranties
in relation to the application of section 6(4) to the claims by the employers of the defenders.
[69]
The only additional argument, which was made by counsel for the first defender,
was that which concerned the pursuer's use of the formulation "believed and averred" in
connection with the first defender's applications for payment under the building contract
(see paragraph 28 above). This argument is misconceived.
[70]
It is necessary to consider the pursuer's averment: "In the circumstances, it is
believed and averred that the first defender continued to apply for payments under the
Building Contract." against the background of the pursuer's averments as a whole. The
pursuer's averments include: the incorporation of the building contract (in Article 2) which,
in turn, includes the contractual payment provisions; the practical completion of the works
(in Article 11); and that the pursuer is unaware of any sums outstanding under the building
contract (in Article 13). Viewed in this light, I do not consider that the pursuer's averment
can be said to be irrelevant and I decline to exclude this averment from probation.
25
The defenders' remaining arguments
[71]
Separate from their arguments in relation to prescription, both of the defenders
sought dismissal of the action, which failing the exclusion of certain averments from
probation on the grounds of relevancy and specification.
[72]
The starting point for the second defender's arguments were the calls which the
second defender had inserted in its pleadings calling upon the pursuer specifically to aver
three matters:
the respects in which it was alleged any duties were owed by it in terms of the
appointment and the collateral warranty;
the basis upon which the alleged breaches of duty were said to have caused or
materially contributed to the cladding defects averred; and
the basis upon which the pursuer had quantified the remedial scheme
condescended upon and the extent to which remedial works had been carried
out.
Senior counsel drew attention to the fact that although these calls had been inserted in the
defences by adjustment on 5 July 2023, they had not been answered.
[73]
Against this background, senior counsel recognised that advancing arguments based
on a lack of specification in your opponent's pleadings was a relatively unusual occurrence
in a commercial action. However, at its heart, the defenders' argument was
straightforward - the pursuer failed to give fair notice of its position. Senior counsel
recognised that, although never expressly overturned, pleading practice had moved on since
the decision of the Inner House in Eadie Cairns v Programmed Maintenance Painting
Limited 1987 SLT 777. That had been recognised by Lord Tyre in Grier v Lord Advocate 2021
SLT 371 (at paragraph 39). However Lord Tyre had also recognised that "[t]he principle,
26
nevertheless, remains the same: fair notice must be given by each party of the facts relied
upon and of which evidence will be led".
[74]
The defenders focussed, in particular, on three areas of the pursuer's case: (i) the
substantive allegations of breach of contract; (ii) the question of joint and several liability;
and (iii) the quantum of the claim.
Allegations of breach
[75]
The defenders drew attention to the fact that the pursuer's averments set out the
terms of the building contract (Article 3); the first defender's collateral warranty (Article 4);
the second defender's appointment (Articles 6 and 7); the novation agreement (Article 8);
the second defender's collateral warranty (Article 9); and practical completion and the lease
(Article 9).
[76]
In Article 12, the pursuer made averments about a series of defects which it is
contended the cladding contains. These defects are collectively referred to as the "Cladding
Defects". The defenders highlighted that the pursuer had not specified in respect of the
majority of the defects detailed whether each of the defects arose from the fault of the first
defender, the second defender or both of them. The exceptions were the defects referred to
in Articles 12.7 and 12.10 but even these paragraphs specified neither the breach of which
obligations was said to have caused the defect nor any other explanation.
[77]
The averments of breach and causation were contained in Article 13:
"The Cladding Defects were caused, or at least materially contributed to, by breaches
of the obligations owed by the defenders to the pursuer, including without prejudice
to that generality by breaches of all of the obligations of each of the defenders
condescended upon above, such breaches have caused the pursuer loss and damage.
But for breaches of those obligations, the Cladding Defects would not have
occurred."
27
The defenders highlighted that it followed from these averments that the pursuer's case was
that every one of the obligations referred to in the foregoing articles of condescendence had
been breached and that every one of those breaches has caused the cladding defects as
defined. The defenders also pointed out that these averments were not exhaustive. The
"without prejudice to that generality" formulation left open the possibility that the pursuer
was seeking to contend that there were other breaches not condescended upon which had
caused or materially contributed to the cladding defects.
[78]
When one read the earlier articles of condescendence which set out multiple diverse
obligations owed by each of the defenders, in light of what was said in Article 13, it was
entirely unclear both how these breaches were said to arise and how each was said to have
contributed to the cladding defects.
[79]
Senior counsel recognised that the pursuer referred to and incorporated two expert
reports prepared by Euan Geddes of HKA. Including appendices, these two reports
comprised more than 1000 pages. In this regard, senior counsel referred to Lord Macfadyen
in The Royal Bank of Scotland plc v Holmes 1999 SLT 563 at 570 G-H on the particular
circumstances in which it was appropriate to incorporate a lengthy document into the
pleadings. However, these reports did not and, in any event, could not provide the
necessary specification in respect of breaches which should be set out in the pursuer's
pleadings. It was not the proper function of an expert to set out the legal basis on which a
claim is being advanced.
[80]
In these circumstances, the defenders were not being given fair notice of the case
against them. The defenders could not, it was submitted, be expected to prepare for proof
on this basis.
28
Joint and several liability
[81]
The starting point of this part of the defenders' argument was that the pursuer
convened both defenders on a joint and several basis (see first conclusion). Senior counsel
for the defenders recognised that it was competent for two parties being sued under
separate contracts to be convened on this basis (Grunwald v Hughes and others 1965 SLT 209).
The test was whether the two defenders have contributed albeit in different ways to cause a
single wrong.
[82]
The short point was that the pursuer had made no averment to that effect on record.
The pursuer had provided no explanation as to the interaction of the alleged breaches of
each defender either cumulatively or in respect of the individual breaches detailed in
Article 12. It was not sufficient for the pursuer to say, in effect, both defenders were
involved in the design and construction of the cladding, there are defects in the cladding,
therefore the defenders are jointly and severally liable.
Quantum
[83]
The pursuer's averments in respect of quantification were set out in Article 13. The
pursuer set out, at very high level, a series of remedial steps and then averred: "The
pursuer's loss and damage is reasonably estimated at £5,575,243.51. That is the sum
concluded for." No further specification was provided. The sum concluded for was clearly
not a round number. It was said to be a "reasonable estimate" but no averments were made
as to how it had been calculated. Again, the defenders' submission was that fair notice had
not been given by the pursuer of its case.
[84]
Drawing these three strands together, the defenders' primary submission was that
the pursuer's case ought to be dismissed. In the alternative, the defenders argued that I
29
should refuse probation in respect of the averments in question. Senior counsel for the
second defender recognised that this might seem an unattractive submission but he
reminded me of the calls that had been placed on the pursuer.
[85]
In the event that I was not with the defenders in respect of either submission, the
defenders' final position was that the pursuer ought to be required to provide adequate
specification in respect of the issues raised by the defenders.
The pursuer's response
[86]
The pursuer submitted that the criticisms made by the defenders of its pleadings
were without merit and should be rejected. The pursuer submitted that it had provided fair
notice of its case.
[87]
The approach adopted by the pursuer had been in accordance with the guidance set
down in paragraph 13a of Practice Note Number 1 of 2017:
"Pleadings in traditional form are not normally required or encouraged in a
commercial action. The default position is that pleadings should be in abbreviated
form. ... Where the pursuer's position on any matter is contained in another
document, such as a Scott Schedule or the conclusions of an expert report, it is
permissible to adopt the document, or a specified part thereof, as part of the
pursuer's case. Where damages are sought, a summary statement of the claim or a
statement in the form of an account will normally be sufficient."
Allegations of breach
[88]
In respect of the averments made in Article 13 (above at [77]), counsel for the pursuer
noted first of all that the breaches which the pursuer averred had caused the cladding
defects were breaches of the obligations the defenders owed to it. In other words, the
pursuer relied upon breaches of the obligations owed by each of the defenders in terms of
the two collateral warranties (see Articles 4 and 9).
30
[89]
Thereafter, the pursuer submitted that the further specification sought by the
defenders was to be found in the report prepared by Euan Geddes dated 13 September 2023.
This report contained a table in section 2 (on page 8) which set out, in respect of each of the
five types of alleged cladding defects condescended upon in Article 12, the particular clauses
of the building contract and the second defender's appointment which were said to have
been breached. The clauses referred to in the table had been set out in the corresponding
parts of the pursuer's pleadings.
[90]
Counsel accepted that the reference to "including without prejudice to that
generality" in Article 13 had remained in the pleadings, in error, from the initial drafting of
the summons. He also accepted that it would have been possible to make reference in the
pursuer's pleadings to the particular part of Mr Geddes' report dated 13 September 2023
which was relied upon ­ namely section 2.
Joint and several liability
[91]
In relation to the issue of the joint and several liability of the defenders, the pursuer's
position was that each of the defenders had contributed, through their breaches of contract,
to creating a cladding system for the hotel which was defective. The pursuer's loss was the
cost of repairing the cladding.
[92]
In this regard, counsel referred to the opinion of Lord Drummond Young in Scottish
Widows (as above at [17]) at paragraphs 49 to 51. That case was analogous in that it involved
a claim for the cost of repairing a defective cladding system which was claimed against
separate defenders on the basis of collateral warranties. Lord Drummond Young, following
Grunwald (see [81] above), considered that it was essential to identify the loss that the
pursuer claimed to have sustained. His Lordship went on:
31
"The loss in the Harmon action is the construction of a building with defective
cladding, resulting in the building's not being wind and watertight. On the pursuers'
averments, I am of opinion that that loss is claimed to be the result of breaches of
contract by both Harmon and BDP. As in Grunwald, the contracts entered into by
Harmon and by BDP, including the collateral warranties, are inter-related in the
sense that they were granted for the purposes of the same building project."
[93]
The pursuer submitted that it was in the same position as the pursuer in the Harmon
action referred to by Lord Drummond Young. Its case was that both defenders, in breach of
their respective obligations in the collateral warranty agreements, had caused or at least
materially contributed to the cladding defects. As a result of those breaches, the pursuer
had suffered a loss which was quantified as the cost of repairing the cladding system. It was
not necessary for the pursuer to aver that both of the defenders had caused all of the loss
claimed. It was sufficient to aver that they had each contributed in material but different
ways to a single result or loss (McGillivray v Davidson 1993 SLT 693 at 695 to 696).
Quantum
[94]
The pursuer's short response to this part of the defenders' argument was that it had
set out the remedial works it contended were required in Article 13 and detailed the
estimated cost. Nothing further was required. Counsel for the pursuer accepted that if the
case were to proceed to proof, he would expect further specification to be produced in the
form of an expert report.
[95]
Counsel for the pursuer finally submitted that in considering the defenders'
complaints of a lack of specification in the pursuer's case, it was necessary to have regard to
what he characterised as a lack of engagement with the pursuer's case by each of the
defenders in their own pleadings.
32
Reply by the defenders
[96]
In reply, the defenders were prepared to accept the explanation provided by the
pursuer as to the specification of the alleged breaches contained in section 2 of Mr Geddes'
report dated 13 September 2023. However, the provision of this specification gave rise to
further issues.
[97]
When one considered the table contained in section 2 of Mr Geddes' report, it was
apparent that no allegation of breach by the second defender was made in respect of the
alleged defects relating to the granite cladding (see paragraph 12.9 of condescendence) one
of the five cladding defects founded upon by the pursuer. Accordingly, on the pursuer's
own averments, the alleged breaches by each of the defenders could be separated.
However, the pursuer had made no such attempt in relation to the losses claimed and no
explanation had been provided as to why it was not possible to sub-divide the sum claimed.
This appeared inconsistent with the averments the pursuer made in respect of the required
remedial works and undermined the pursuer's position in respect of the alleged joint and
several liability of the defenders. The case of Scottish Widows relied upon by the pursuer
turned on its own particular facts and was not of general application.
Decision
[98]
Before considering the particular arguments advanced by the defenders in this case,
it is perhaps helpful to remind oneself of the approach to pleadings adopted in a commercial
actions. The current practice is set out in Practice Note 1 of 2017 as follows:
"Pleadings in traditional form are not normally required or encouraged in a
commercial action. The default position is that pleadings should be in abbreviated
form. Provided that paragraphs 10 - 12 of this Practice Note (pre-action
communication) have been complied with, parties will be aware of each other's
position before the action has been commenced. The overriding requirement is one
33
of fair notice: the purpose of the pleadings is to give notice of the essential elements
of the case to the court and to the other parties to the action. ... Where the pursuer's
position on any matter is contained in another document, such as a Scott Schedule or
the conclusions of an expert report, it is permissible to adopt the document, or a
specified part thereof, as part of the pursuer's case. Where damages are sought, a
summary statement of the claim or a statement in the form of an account will
normally be sufficient." (at paragraph 13a)
It follows from the fact that the parties are neither required nor encouraged to set out their
pleadings in traditional form that, as the Lord President put it in Marine & Offshore (Scotland)
Ltd v Hill 2018 SLT 239 at paragraph 16, the rules applicable to averments in an ordinary
action do not normally apply with the same rigour in a commercial action. However, as
Lord Tyre noted in Grier (at [73] above) this apparent relaxation does not take away from the
fundamental need to give fair notice: "[t]he principle, nevertheless, remains the same: fair
notice must be given by each party of the facts relied upon and of which evidence will be
led".
[99]
As the passage quoted from the Practice Note above makes clear, where a party's
position on any matter is contained in another document, it is permissible to incorporate that
document or a part of it as part of that party's case. Clearly, where such an approach avoids
repetition in the pleadings of detailed and technical information which can be more easily
understood in another format ­ for example, a schedule or table ­ it is to be welcomed.
In such a case, there is no question that the other parties to the action are not being given fair
notice of the case against them.
[100]
As Lord Macfadyen emphasised in Royal Bank of Scotland (as at [79] above), the
question of whether the incorporation of documents into the pleadings does indeed
represent a satisfactory way of providing specification will depend on the particular
circumstances of the case including, obviously, both the nature of the case and the nature of
the document being incorporated.
34
[101]
Applying this approach to the first criticism made by the defenders of the pursuer's
case ­ namely, that the pursuer had failed adequately to specify the allegations of breach
upon which it founded ­ I am sympathetic to the defenders' position.
[102]
First, considering the pursuer's pleadings on their own terms and, at this stage,
setting the reports of Mr Geddes to one side, the averments in Article 13 (see above at [77])
self-evidently do not give fair notice of the particular breaches that the pursuer founds upon.
Apart from anything else, this much must follow from the use by the pursuer of the
formulation "including without prejudice to that generality".
[103]
From that starting point, I do not consider that this lack of specification is cured by
the blanket incorporation of the over one thousand pages of Mr Geddes' two reports.
Leaving to one side the sheer volume of information contained in the two reports, the
pursuer's positon is not assisted by the fact that it is unclear from their face how the two
reports are supposed to inter-relate.
[104]
However, although I consider that for these reasons there is some merit in the
defenders' criticisms of the pursuer's pleadings, I have also had the benefit of the
informative submissions of pursuer's counsel. In light of those submissions, I understand
that the pursuer founds its case only on the breaches which are set out in the table contained
in section 2 of Mr Geddes' report dated 13 September 2023. On the basis of the way the
argument developed before me, I understand further that, at least as regards their first
criticism, the defenders accept, in light of the submissions made on behalf of the pursuer,
that adequate notice of the pursuer's case on breach has been provided.
[105]
In these circumstances, I consider that either to dismiss the pursuer's case or to
exclude the averments in question from probation (which in the circumstances would seem
to amount to the same thing) would be entirely disproportionate and not in the interests of
35
justice. But I also consider that it would be of assistance both to the parties and to the court
were the pursuer to clarify its pleadings to bring them into line with the submissions made
at debate before the case proceeds further.
[106]
As to the two remaining criticisms made by the defenders which relate to the
pursuer's pleadings in respect of the basis of the defenders' joint and several liability and the
quantification of the pursuer's loss, I consider that the key to both lies in the relatively
undeveloped pleadings of the pursuer in respect of the repair works it contends require to
be carried out and the estimated costs of those works.
[107]
In respect of the issue of the defenders' joint and several liability, the pursuer argues
that both defenders, in breach of their respective obligations in the collateral warranty
agreements, caused or at least materially contributed to the cladding defects. As a result of
those breaches, the pursuer claims that it has suffered a loss in that the cladding system was
defective and required to be repaired. This being a single loss caused by or at least
contributed to by both defenders, it was competent to sue the defenders on a joint and
several basis in line with Grunwald and Scottish Widows. This is what the pursuer avers in
Article 13 (see above at paragraph 77).
[108]
On the other hand, the defenders argue that the pursuer's averred position of a
single loss is inconsistent with the pursuer's position in submissions in respect of the
breaches upon which it founds. The thrust of the defenders' position is to ask, insofar as the
breaches upon which the pursuer founds can be identified and the remedial steps to be
taken are capable of being broken down, on what basis, in the absence of any averred
explanation, can the pursuer assert that what is being claimed is indeed a single loss.
36
[109]
As such, the issue of joint and several liability links to the defenders' final criticism of
the pursuer's pleadings ­ namely the lack of specification of the way in which the sum sued
for of £5,575,243.51 has been calculated.
[110]
During the course of the debate, counsel for the pursuer conceded that, were the case
to proceed to a proof, further specification of the pursuer's position would be provided.
[111]
Against this background, the question which I require to address is whether, in light
of the present admittedly undeveloped state of the pursuer's pleadings on quantum, I can
uphold either the defenders' arguments in respect of the joint and several liability or, more
generally, in respect of the lack of specification.
[112]
In respect of the joint and several liability argument, I do not consider that it can be
concluded, at this juncture, that the pursuer's averments are irrelevant and cannot succeed.
Equally, as was conceded by counsel, it is clear that some further development of the
pursuer's position in respect of quantum is required before any hearing of evidence.
[113]
In the circumstances, therefore, I again do not consider it appropriate either to
dismiss the action or to exclude the averments in question from probation. Instead, I am
minded to order the pursuer to provide further specification of the quantification of its loss.
This will, in itself, address the defenders' third criticism as well as enabling the positions of
all parties on the joint and several liability issue to be clarified.
Disposal
[114]
In light of my decisions in respect of the matters argued before me, I reject the
defenders' motions for dismissal.
37
[115]
Given my decisions in respect of the defenders' arguments in relation to the
specification of the pursuer's case (at paragraphs 105 and 113), I will put the case out by
order in order that I can be addressed on further procedure in light of those decisions.
[116]
I will reserve all questions of expenses meantime.


BAILII: Copyright Policy | Disclaimers | Privacy Policy | Feedback | Donate to BAILII
URL: http://www.bailii.org/scot/cases/ScotCS/2024/2024_CSOH_43.html