![]() |
[Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback] | |
The Judicial Committee of the Privy Council Decisions |
||
You are here: BAILII >> Databases >> The Judicial Committee of the Privy Council Decisions >> Water and Sewerage Authority of Trinidad and Tobago v Waterworks Ltd (Trinidad and Tobago) [2025] UKPC 9 (18 February 2025) URL: http://www.bailii.org/uk/cases/UKPC/2025/9.html Cite as: [2025] UKPC 9 |
[New search] [Printable PDF version] [Help]
[2025] UKPC 9
Privy Council Appeal No 0066 of 2021
JUDGMENT
Water and Sewerage Authority of Trinidad and Tobago (Respondent)
v
Waterworks Ltd (Appellant) (Trinidad and Tobago)
From the Court of Appeal of the Republic of Trinidad and Tobago
before
Lord Lloyd-Jones
Lord Sales
Lord Leggatt
Lord Burrows
Lady Rose
JUDGMENT GIVEN ON
18 February 2025
Heard on 31 October 2024
Rowan Pennington-Benton
Nicholas Leah
(Instructed by Sheridans (London))
Respondent
Ian Benjamin SC
Raphael Ajodhia
(Instructed by Signature Litigation (Gibraltar) Ltd)
Introduction
"Upon such termination, the Engineer shall determine the value of the work done and issue a Payment Certificate which shall include:
(a) the amounts payable for any work carried out for which a price is stated in the Contract;
(b) the Cost of Plant and Materials ordered for the Works which have been delivered to the Contractor, or of which the Contractor is liable to accept delivery ...;
(c) any other Cost or liability which in the circumstances was reasonably incurred by the Contractor in the expectation of completing the Works;
..."
Factual background
The High Court proceedings
"From an examination of the relevant documents I am satisfied that the arrangement between [the Contractor] and MAAK was not for the actual obtaining of the equipment at that time but rather an arrangement by which [the Contractor] agreed to procure the equipment from MAAK at some time in the future at the prices quoted to it by MAAK in 2008. What [the Contractor] did by entering into these contracts therefore was to secure the equipment at the quoted price. The cost of that benefit to [the Contractor] was that it was required to bind itself to purchasing the equipment from MAAK and commit itself to the payment of 30% of the contract price if it cancelled the contracts. In other words in 2008 [the Contractor] sourced the equipment and entered into an arrangement by which the equipment was to be made available to them in the future at a price fixed at the time the equipment was sourced."
Decision of the Court of Appeal
(i) Having found that actually to purchase equipment for the water treatment plants at such a preliminary stage would have been premature, and therefore unreasonable, the judge should have concluded that it was also premature to commit to liabilities to pay charges that were intended to arise upon the cancellation of such purchases.
(ii) The judge's finding that the purchase orders issued by the Contractor were not for the actual supply of the equipment was inconsistent with the clear language of the contractual documents and was not sustainable.
(iii) Even if the judge's finding about the nature of the purchase orders had been correct, the judge failed to consider whether it was reasonable to agree to a cancellation charge of 30% of the prices quoted for the equipment if the orders were cancelled before MAAK actually purchased the equipment.
(iv) The judge was wrong to find that the preliminary designs on which the quotations were based were sufficiently detailed to allow the equipment to be identified and ordered. It was illogical to infer, as the judge did, that because the preliminary designs were sufficient to ascertain the likely cost of the equipment for the purpose of making a tender, they were also sufficient to identify the equipment with the degree of detail needed for construction of the plants.
This appeal
The meaning of "reasonably incurred"
Was it premature to purchase equipment?
"Construction to such designs and drawings shall not commence until the Employer's Representative has consented thereto."
The nature of the MAAK contracts
"1) Applicable Terms. These terms govern the sale of products and systems (Product) by MAAK Technologies Group Inc (MAAK). Any additional, different or conflicting terms contained in Buyer's request for proposal, specifications, purchase order or any other written or oral communication from Buyer shall not be binding in any way on MAAK unless explicitly agreed with written confirmation.
2) Delivery. Product shall be delivered FOB as specified on quotation. MAAK point of shipment with title to the Product and risk of loss or damage for the Product passing to buyer at that point. Buyer shall be responsible for all transportation, insurance and related expenses including any associated taxes, duties or documentation. MAAK may make partial shipments. Shipping dates are approximate only and MAAK shall not be liable for any loss or expense (consequential or otherwise) incurred by Buyer or Buyer's customers if MAAK fails to meet the specified delivery schedule.
3) Pricing & Payment. (a) Payment - Unless otherwise stated, all payments shall be net 30 days from invoice date payable in the currency quoted. ...
...
10) Applicable Law. The agreement and terms shall be governed by the laws of the province of Ontario, Canada.
...
12) Cancellation. Buyer shall be liable for cancellation charges, as follows: (a) Minimum amount equal to 30% of the quoted price of Product and additional expenses as may be notified [to] the Buyer by MAAK as incurred in connection with the Agreement. (b) Maximum amount of 100% of the quoted price of Product depending on the time of cancellation."
The Contractor's burden of proof
Conclusion