The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 No. 811

BAILII [Home] [Databases] [World Law] [Multidatabase Search] [Help] [Feedback]

United Kingdom Statutory Instruments


You are here: BAILII >> Databases >> United Kingdom Statutory Instruments >> The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 No. 811
URL: http://www.bailii.org/uk/legis/num_reg/2024/uksi_2024811_en_1.html

[New search] [Help]


Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Statutory Instruments

2024 No. 811

Infrastructure Planning

The National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024

Made

11th June 2024

Coming into force

12th June 2024

The National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024 (“ the 2024 Order”)( 1), which granted development consent within the meaning of the Planning Act 2008 (“ the Act”)( 2), contained correctable errors within the meaning of the Act( 3). Before the end of the relevant period, as defined in paragraph 1(6)(a) of Schedule 4 to the Act, the Secretary of State received a written request from the applicant( 4) for the correction of errors in the 2024 Order.

The Secretary of State has informed the relevant local planning authorities for the area in which the land to which the 2024 Order relates is situated, that the request has been received in accordance with paragraph 1(7) of Schedule 4 to the Act.

The Secretary of State, in exercise of the powers conferred by section 119 of, and paragraphs 1(4) and (8) of Schedule 4 to, the Act, makes the following Order.

Citation and commencement

1.  This Order may be cited as the National Grid (Yorkshire Green Energy Enablement Project) (Corrections) Order 2024 and comes into force on the day after the day on which it is made.

Corrections to the 2024 Order

2.—(1) The 2024 Order is corrected as set out in the table in Schedule 1 of this Order, where—

(a) column 1 sets out where the correction is to be made;

(b) column 2 sets out how the correction is to be made; and

(c) column 3 sets out the text to be substituted, inserted or omitted.

(2) Schedule 1 to this Order has effect.

Signed by authority of the Secretary of State for Energy Security and Net Zero

John Wheadon

Head of Energy Infrastructure Planning Delivery

Department for Energy Security and Net Zero

11th June 2024

Article 2

SCHEDULE 1 Correctable Errors

Provision How correction is to be made Text to be substituted, inserted or omitted
Article 2, Interpretation, Definition of traffic regulation order plan For “article 498” substitute “article 48”
Article 19 (Discharge of Water) Paragraph 10 Omit entire paragraph “(10) Any application for consent under paragraph (3) or approval under paragraph (4)(a) must include a statement that the provisions of paragraph (9) apply to that application.”
Article 19 (Discharge of Water) Paragraph 11 For “(11) In relation to any works executed” substitute “(10) In relation to any works executed”
Article 21 (Authority to survey and investigate the land) Paragraph 1(a) After “investigate the land” omit “;”
Article 48 (Certification of plans, etc.) Paragraph (k) After “Figure 3.10-3.12” omit “,”
Article 48 (Certification of plans, etc.) Paragraph (k) After “Figure 3.10-3.12” insert “in”
Schedule 3, Requirement 2 (Time Limits) Paragraph 2 For “If any proceedings are begun to challenge that validity of this Order, the period specified in sub-paragraph (1) is extended by” substitute “If any proceedings are begun to challenge the validity of this Order, the period specified in paragraph (1) is extended by”
Schedule 3, Requirement 2 (Time Limits) Paragraph 3 For “sub-section (2)(a)” substitute “paragraph (2)(a)”
Schedule 3, Requirement 10 (Replacement planting) Paragraph 1 After “under Requirement 9” insert “(retention and protection of existing trees)”
Schedule 3, Requirement 10 (Replacement planting) Paragraph 2 After “under Requirement 8” insert “(landscaping at Overton, Tadcaster and Monk Fryston)”
Schedule 3, Requirement 18, (Approval of details having regard to the Design Approach to Site Specific Infrastructure) Paragraph 2 For “(2) Any non-linear site permanent security fencing at” substitute “(2) Any permanent site security fencing for a non-linear work at”
Schedule 3, Requirement 18, (Approval of details having regard to the Design Approach to Site Specific Infrastructure) Paragraph 3 For “under sub-paragraphs” substitute “under paragraphs”
Schedule 3, Requirement 19 (Site specific mitigation scheme) Paragraph 2 For “in sub-paragraph” substitute “in paragraph”
Schedule 3, Requirement 19 (Site specific mitigation scheme) Paragraph 3 For “In the event that significant effects of notice or vibration are identified on receptors SEL16 and SEL17 as shown within the Noise and Vibration Figures (Document 5.4.14), the scheme referred to in sub-paragraph (1) must include mitigation measures to reduce the significant effects as far as practicable.” substitute “In the event that significant effects of noise or vibration are identified on receptors SEL16 and SEL17 as shown within the Noise and Vibration Figures (Document 5.4.14), the scheme referred to in paragraph (1) must include mitigation measures to reduce the significant effects as far as practicable.”
Schedule 3, Requirement 19 (Site specific mitigation scheme) Paragraph 4 For “in sub-paragraph” substitute “in paragraph”

Schedule 15, Protective Provisions, Part 6 (For the protection of National Highways Limited) Paragraph 62 (Interpretation)

Definition of “Highway detailed design information” sub-paragraph (d)

After “standards for Highways” insert “;”
Schedule 15, Protective Provisions, (For the protection of National Highways Limited), Paragraph 67, (Prior approvals and security) Sub-paragraph 2 (e) For “under sub-paragraph (c)(v) above;” substitute “under sub-paragraph (c)(iv) above;”
Schedule 15, Protective Provisions, (For the protection of National Highways Limited), Paragraph 68, (Construction of the specified works) Sub-paragraph 7 For “under sub-paragraph (6) or sub-paragraph (7)” substitute “under sub-paragraph (5) or sub-paragraph (6)”

EXPLANATORY NOTE

(This note is not part of the Order)

The Order corrects errors and omissions in the National Grid (Yorkshire Green Energy Enablement Project) Development Consent Order 2024, a development consent order under the Planning Act 2008, following a request under paragraph 1(5)(a) of Schedule 4 to that Act.

( 2)

2008 c.29. Paragraph 1 of Schedule 4 was amended by paragraph 128(2) of, and paragraph 70 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20). There are other amendments to the Act which are not relevant to this Order.

( 3)

As provided for in Schedule 4 of the Act.

( 4)

As defined in paragraph 4 of Schedule 4 to the Act.